Adobe Workfront Project Manager Certified Professional Questions and Answers

Question 1

Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.

Why may this be the case?

Options:

A.

The primary task owner has time off logged in Workfront.

B.

The team needs to review the task before confirming the start date.

C.

The task duration and planned hours are set to begin on Friday.

Question 2

A system administrator has created a Marketing Request Queue that routes to the marketing team. This team needs to manage various incoming requests from the organization through emails, instant messaging, and conversations. Team members receive request notifications in their emails but are still having difficulties monitoring and prioritizing incoming requests.

Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?

Options:

A.

Four reports showing the entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, a third report that shows recently completed requests, and a fourth report that shows the schedule assigned to each team member.

B.

Two reports showing the priority and actual completion date of each request, i.e., one that shows active requests and another that shows recently completed requests.

C.

Three reports showing the priority and entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, and one that shows recently completed requests.

Question 3

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

Options:

A.

Actual Completion Date

B.

Progress Status

C.

Status

Question 4

A resource manager wants to review how resources are utilized across multiple projects to make staffing decisions.

Which Workfront tool should the resource manager use?

Options:

A.

Scenario Planner

B.

Timesheets

C.

Workload Balancer

Question 5

A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.

How should the project manager keep these team members apprised of updates?

Options:

A.

Subscribe the team members to the request.

B.

Ask the team members to add the request to their favorites.

C.

Make the team members all primary contacts on the request.

Question 6

Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?

Options:

A.

Update the project status.

B.

Recalculate the project timeline.

C.

Update the project baseline.

Question 7

A video designer is spending an excessive number of hours on a project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this project are necessary and suspects that the number of hours budgeted for the video designer ' s time on this project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this project so that the designer can still meet commitments on other assigned work.

Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this project vary from the Actual Hours spent on the project?

Options:

A.

Utilization

B.

Workload Balancer

C.

Hours

Question 8

A project manager would like to assign tasks across projects to a team without having to navigate to each project.

How can the project manager do this?

Options:

A.

Assign work using the Resource Planner.

B.

Assign work by drag-and-drop.

C.

Assign work in bulk.

Question 9

A creative team accesses their assigned work in a My Tasks list report. The team would like to easily see any New tasks highlighted for visibility. How can the project manager accommodate the team’s request?

Options:

A.

Schedule a daily automatic report delivery of the New tasks in the report to the team.

B.

Create a grouping for task Progress Status and use a custom color pie chart for visibility.

C.

Create a Filter that uses conditional formatting to display New tasks only.

D.

Create a View that uses Column Rules to format the New tasks for visibility.

Question 10

A project manager has been asked to create a report showing the planned completion date for all the project manager ' s projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a new report. In the filter, update the project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date and set the default view to “Calendar View.”

B.

Visit the Calendars page and create a new calendar. In the filter, update the date field to Planned Dates and update the Project Owner ID field with the project manager’s name. Set the color to purple.

C.

Visit the Reports page and create a new calendar. In the filter, update the Project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date.

Question 11

Which project Condition is set when the Progress Status of the project is Behind or At Risk?

Options:

A.

Late

B.

At Risk

C.

In Trouble

Question 12

A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.

Which action should the stakeholder take to log the risk?

Options:

A.

Log a risk as part of the project business case and identify it as a " schedule " risk.

B.

Log an issue on the project and explain that the completion date is at risk.

C.

Create a task in the project and set the Planned Completion Date for 2 weeks.

Question 13

Which wildcard should be used in a task report when using an Assigned To filter to show the logged-in user all tasks to which she is assigned as the primary task owner?

Options:

A.

USER.NAME

B.

USER.ID

C.

USER.roleID

Question 14

Which aspect of a project determines the Progress Status?

Options:

A.

Timeline

B.

Critical Path

C.

Milestone Tasks

Question 15

A project manager is assigned to a new Workfront request. The request specifies that the management team’s sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?

Options:

A.

Convert the issue into a project using a project template.

B.

Email the management team and request their approval.

C.

Use a customized approval process to route the issue for approval.

Question 16

What item, when shared with a user, can never give that user inherited permission to a project?

Options:

A.

Portfolio

B.

Task

C.

Report

Question 17

Which date type on tasks can a project manager manually modify?

Options:

A.

Planned

B.

Estimated

C.

Projected

Question 18

A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?

Options:

A.

Set the task condition to At Risk.

B.

Update the Commit Date on the task.

C.

Work on the task and complete it in the given duration.

Question 19

Which initial project setting would a project owner use to identify and report on key tasks on a project?

Options:

A.

Milestone Path

B.

Schedule

C.

Resource Leveling Mode

Question 20

An assignee clicks Work On It for a task, and a new finish date appears on the task while the original planned finish stays the same.

What does this new date communicate to the project manager?

Options:

A.

It indicates that the assignee’s finish date is wrong and should be ignored.

B.

It indicates that the assignee’s finish date replaces the Planned Completion Date.

C.

It indicates the assignee’s own estimate of when they expect to finish the task, which can differ from the Planned Completion Date.

Question 21

A contract requires custom billing rates.

Where can a project manager update this on the project?

Options:

A.

Project Details > Billing Information

B.

Project Settings > Access Levels

C.

Project Finances > Override Project-Level Billing Rates

Question 22

What occurs when an individual enters a new commit date that is after the original planned date of a task?

Options:

A.

The assignee of any task that has the original task set as a predecessor is notified.

B.

The Project Owner is notified whether this change will impact the Project Timeline.

C.

The Planned Completion Date of the task automatically changes to match the new Commit Date.

Question 23

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

Options:

A.

Utilization section

B.

Hours tab

C.

Finance section

Question 24

A project manager needs to locate the fixed revenue and costs of a project. Where should the project manager look to find this information?

Options:

A.

Business Case

B.

Billing Records

C.

Project Details

Question 25

A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?

Options:

A.

Create a new approval process in the global setup area that will ensure that an approval process is attached to all Marketing Projects.

B.

Create a single-use approval process on each project that routes to the Project Sponsor for approval once the project status is set to Complete.

C.

In the project template, add an approval process routing to the Project Sponsor for approval once the project status is set to Complete.

Question 26

An executive wants to see the actual cost of projects within a selected portfolio, allowing for multiple reports with the option to select a specific portfolio, sorted in a descending order, so the most expensive projects appear on top. Which steps should be taken to create this report?

Options:

A.

Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. From the Reporting Settings dropdown, add a prompt for Portfolio Name.

B.

Visit the Reports area and create a new Project report. Group the results by Portfolio Name. Add a column for Actual Cost and summarize this column by SUM.

C.

Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. Group the results by Portfolio Name.

Question 27

Which field is used to create a milestone step on a milestone path in the Setup area?

Options:

A.

Status

B.

Description

C.

Key

Question 28

A project manager has assigned a task to a team. One of the members of the team wants to volunteer to complete the task.

Where would the volunteer navigate to do this?

Options:

A.

Team Settings > Select Assign to

B.

Team Settings > Work on it

C.

Team Requests > Work on it

D.

Team Requests > Select Assign to