Spring Sale Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

API API-SIEE Dumps

Page: 1 / 11
Total 110 questions

Source Inspector Electrical Equipment Questions and Answers

Question 1

What is the process that aims to find potential defects in a product before it is released for delivery?

Options:

A.

Inspection

B.

Examination

C.

Quality Control

D.

Quality Assurance

Question 2

Who is responsible for verifying that Non-conformance report NCR disposition has been properly implemented?

Options:

A.

Vendor's Quality Manager

B.

Inspection Coordinator

C.

Source Inspector

D.

Manufacturing Engineer

Question 3

What standard defines the maximum number of conductors permitted in outlets, devices and junction boxes, and conduit bodies?

Options:

A.

NFPA 70

B.

IEEE 112

C.

IEC 60079 series

D.

NEMA 250

Question 4

Each source inspection assignment should have a detailed Inspection and Test Plan ITP which identifies the:

Options:

A.

day the inspection is to start.

B.

individuals involved in the inspection.

C.

activities to be performed during the inspection.

D.

activities to be performed and the acceptance criteria.

Question 5

What electronic instrument is used for measuring electrical potential difference between two points in an electric circuit?

Options:

A.

Amp meter

B.

Wheatstone bridge

C.

Voltmeter

D.

Potentiometer

Question 6

According to ANSI C57.12, the tank pressure under rated conditions of sealed transformers shall not exceed what value?

Options:

A.

One atmosphere

B.

Two atmospheres

C.

Three atmospheres

D.

Four atmospheres

Question 7

Laminations in a motor stator core are used to reduce:

Options:

A.

AC voltage.

B.

frequency.

C.

energy loss.

D.

DC voltage.

Question 8

What method is used to verify tightness of accessible bolted electrical connections?

Options:

A.

Compression of the lock-nut

B.

Visual inspection of torque markings

C.

Verification of assembly check sheet

D.

Calibrated torque wrench

Question 9

According to ANSI C57.12, each line terminal of a winding shall be tested to what maximum value?

Options:

A.

Switching Impulse Insulation Level

B.

Chopped Wave Insulation Level

C.

Wye-Winding Insulation Level

D.

Basic Lightning Impulse Insulation Level

Question 10

What is the purpose of labeling the temperature range on electrical equipment used in a Class I hazardous area?

Options:

A.

To verify the process temperature and the equipment temperature have the same Class I rating

B.

To ensure that the equipment maximum temperature does not exceed the autoignition temperature of the specific gas or vapor to be encountered

C.

To ensure the equipment is compatible with the other Class I devices

D.

To verify the maximum process temperature does not exceed high levels

Question 11

Before starting surveillance, the source inspector should confirm that the supplier/vendor has:

Options:

A.

only the latest code editions, regardless of contract requirements

B.

the most current project documents specified in the engineering design

C.

only verbal instructions from procurement

D.

internal procedures but not drawings

Question 12

The highest voltage rating on a piece of medium voltage equipment is the:

Options:

A.

basic impulse level.

B.

AC high potential.

C.

DC high potential.

D.

nominal voltage.

Question 13

Which source inspection effort level is MOST appropriate for the highest-risk equipment?

Options:

A.

No source inspection

B.

Final source inspection only

C.

Intermediate source inspection

D.

Resident source inspection

Question 14

Any reports, such as Material Test Reports, that have been modified or corrected should be:

Options:

A.

accepted after clarification.

B.

cause for immediate rejection.

C.

rejected at the discretion of the source inspector.

D.

accepted after signatures are verified.

Question 15

Which of the following is identified in the guide as a key MCC design item?

Options:

A.

Ground bus

B.

Transformer conservator

C.

Buchholz relay

D.

Tap changer handle

Question 16

According to ANSI/NETA/ATS, when performing a dielectric withstand test on each bus section, the test voltage shall be applied for how long?

Options:

A.

One second

B.

One minute

C.

One hour

D.

One day

Question 17

In addition to purchase order requirements and company standards, what document would provide the details for correct coatings application?

Options:

A.

Quality Plan

B.

Manufacturers' Recommendations

C.

ASME BPVC Section II

D.

Inspection and Test Plan

Question 18

Metallic shielding components such as tapes, wires, or braids shall be connected to a:

Options:

A.

equipment grounding busbar.

B.

low voltage ceramic insulator.

C.

low voltage connector.

D.

center tap of a transformer.

Question 19

Circuit breakers over 1000 V equipped with stored energy mechanisms shall perform which of the following functions?

Options:

A.

Indicate whether power is available to the circuit breaker

B.

Identify the presence of fault current flow through the circuit breaker

C.

Locate the position of the charging mechanism

D.

Prevent the release of the stored energy unless the mechanism has been fully charged

Question 20

According to the guide definitions, a junction box used within a control building or instrument enclosure may also be referred to as an:

Options:

A.

interface box

B.

breaker cubicle

C.

bus duct

D.

starter cell

Question 21

Areas where ignitable concentrations of flammable gases or vapors are present continuously or for long periods of time are classified as:

Options:

A.

Class I Zone 0.

B.

Class I Zone 1.

C.

Class I Division 2.

D.

Class I Zone 2.

Question 22

NEMA rated motor controllers require a minimum range of conductor sizes for a specific size controller. Which of the following conductor sizes is appropriate for a Size 2 controller?

Options:

A.

2/0 AWG -250MCM at 60°C rated cable and 2/0 AWG -350MCM at 75°C rated cable

B.

2-2/0 AWG at 60°C rated cable and 2-4/0 AWG at 75°C rated cable

C.

10-2/0 AWG at 60°C rated cable and 10-4/0 AWG at 75°C rated cable

D.

10-4 AWG at 60°C rated cable and 10-6 AWG at 75°C rated cable

Question 23

According to API 541, prior to mechanical running test, each mounting foot shall be checked for “soft feet.” How is this check conducted?

Options:

A.

Feeler gauges are used at the foot to base interface to verify gap tolerance has not been exceeded

B.

After torquing mounting bolts, a vertically oriented, zeroed, dial indicator is attached to each foot and a reading taken after loosening of the bolt torque to verify movement is within tolerance

C.

A dial indicator is oriented vertically and zeroed prior to base bolt tightening with a reading taken after tightening to confirm movement is within tolerance

D.

Mounting bolt torque is verified with a calibrated torque wrench with no visible gaps observed between the foot and base interface

Question 24

What is the purpose of an equipment risk assessment in the source inspection process?

Options:

A.

To identify the level of risk associated with failure of the supplier/vendor’s quality system

B.

To identify the level of effort for source inspection activities during the manufacture/fabrication phase of a project at the supplier/vendor facility

C.

To identify which shops will be able to bid on certain types of equipment i.e. to identify the shops that can supply equipment critical to project success

D.

To determine the level of business insurance required in the event the supplier/vendor is unable to deliver the product on time while meeting contractual agreements

Question 25

A circuit breaker is defined as:

Options:

A.

a one-shot device that causes the current carrying element to melt open, disconnecting the load from the source voltage.

B.

a type of device used to provide voltage protection.

C.

a means of energizing and de-energizing an electrical circuit.

D.

one or more enclosed vertical sections containing voltage.

Question 26

According to API 541, for the bearing temperature rise test, motor bearing stable temperature is defined:

Options:

A.

by the manufacturer's FAT procedure.

B.

as a change of not more than 1°C in 30 minutes.

C.

as a rise of not more than 1°C in one hour.

D.

as a rise of not more than 2°C in one hour.

Question 27

What document is used for petroleum and chemical industry premium-efficiency, severe-duty, totally enclosed fan-cooled TEFC squirrel cage induction motors up to and including 370 kW 500 hp?

Options:

A.

API 546

B.

IEEE 141

C.

IEEE 841

D.

NFPA 70

Question 28

Which definition BEST matches an Instrument Ground Bus (IGB)?

Options:

A.

A temporary grounding point used only during shipping

B.

A grounding system independent from AC safety ground for instrumentation signals, tied at one point

C.

A neutral bus used for normal load current

D.

A bus used only for lightning protection

Question 29

According to API 541, totally enclosed machines TEFC, TEPV, TEWAC, and TEAAC are equipped with which of the following?

Options:

A.

Low-point drain

B.

Heat exchanger cooling fan

C.

Bearing RTDs

D.

Surge protectors

Question 30

According to API 541, subsequent to completion of manufacture and testing, the vendor shall revise and resubmit the previously supplied purchase data including all the following except:

Options:

A.

rotor-balance report.

B.

operating manual.

C.

as-built data sheet.

D.

shop test data.

Question 31

Which item is part of typical final inspection and shipping preparation for a liquid-immersed transformer?

Options:

A.

Verification that all FAT issues are resolved

B.

Reclassification of the project risk register

C.

Reissue of procurement bid tabs

D.

Elimination of all documentation requirements

Question 32

According to NFPA 70, the number of bends permitted between pull points for rigid metal conduits RMC shall not be more than:

Options:

A.

the equivalent of six quarter bends.

B.

the equivalent of four quarter bends 360 degrees total.

C.

four bends provided the radii is less than 5 times the conduit diameter.

D.

four bends provided the bend radii is at least 10 times the conduit diameter for conduit greater than 3/4 inch 19 mm.

Question 33

According to ANSI C57.12, the average winding temperature rise above ambient temperature shall not exceed what value?

Options:

A.

65°C

B.

70°C

C.

80°C

D.

90°C

Page: 1 / 11
Total 110 questions