Question 1

Which of the following are recognized DSDM styles of Timebox?

1. Unstructured

2. Consolidated

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

Question 2

Which purpose relates to the instrumental Success Factors?

Options:

A.

Underpins the prioritization of requirements

B.

Informs the development of the Business Case

C.

Positions DSDM projects for a successful outcome

D.

Inform the development of the Terms of Reference

Question 3

When is a Product Backlog Item considered ‘ready’ to be brought into a Sprint?

Options:

A.

It has been added to the Product Backlog prioritized list

B.

It is small enough to become ‘done’ within a given timeframe

C.

It is selected by Developers during a Sprint Planning event

D.

It is documented as a User Story on a physical card

Question 4

During what DSDM phase is it established how quality to be assured?

Options:

A.

During Feasibility

B.

As part of Foundations

C.

At the start of Evolutionary Development

D.

During each timebox during Evolutionary Development

Question 5

Which of the following is a DSMD principle?

Options:

A.

Build incrementally from firm foundations

B.

Build incrementally from Feasibility onwards

C.

Build incrementally in Timeboxes

D.

Build incrementally

Question 6

Which of the following statements about a 'Force Field Analysis' are true?

    It can reveal both barriers to overcome and possible sources of resistance.

    It should be created independently by the change manager.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 7

Which of the following statements about an agile approach to projects is true?

    Deploying the Solution incrementally throughout the project to validate the solution.

    Early release of Solution Increments helps test assumptions about value.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

Question 8

What DSDM product is identified as a governance product because if may be used for purposes such as prioritization of a project within a portfolio?

Options:

A.

Terms of Reference

B.

Business Case

C.

Prioritized Requirements List

D.

Feasibility Assessment

Question 9

In neuroscience, which particularly rewards the brain's need for certainty?

Options:

A.

Change delivered in small stages.

B.

Delegated decision-making through change.

C.

Group social events.

D.

Public praise.

Question 10

Identify the missing words in the following sentence.

Principles 1 –Focus on the Business Need suggests that every decision taken during a project should be [?] – to deliver what the business needs to be delivered.

Options:

A.

The responsibility of the Business Sponsor

B.

Share between all of the project roles

C.

Viewed in light of the overriding project goal

D.

Made collaboratively

Question 11

Which competence is NOT required within the Solution Development team?

Options:

A.

All members to be multi-skilled experts

B.

Business knowledge

C.

Technical expertise

D.

Willingness to work with other

Question 12

Which of the following statements, about ways in which we communicate and connect with people, are true?

    Non-verbal communication can be written.

    Our actions can speak volumes without saying a word.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 13

Which of the following are values in the Agile Manifesto?

    Individuals and interactions over processes and tools

    Responding to change over following a plan (correcting “Responsible to change”)

    Customer collaboration over contract negotiation

    Comprehensive documentation over working solutions

Options:

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

Question 14

Why might the priority of a requirement in the Product Backlog differ from what might otherwise be shown?

Options:

A.

Different budget

B.

Different resources

C.

Different timeframe

D.

Different quality

Question 15

Which skill is MOST relevant to helping people through the change curve?

Options:

A.

Time management.

B.

Negotiation.

C.

Decision-making.

D.

Active listening.

Question 16

What event can be added to the structure of a Sprint to help facilitate cross-team planning?

Options:

A.

Project Sprint Planning

B.

Project planning event

C.

Sprint Planning

D.

Sprint Retrospective

Question 17

Which of the following statements about diverse teams are true?

    Quicker to make decisions than teams of 'similars.'

    Members understand each other immediately.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 18

Where should the specific measures be recorded, to check whether the beneficiary of a User Story can use it?

Options:

A.

Criteria

B.

Conversation

C.

Confirmation

D.

Context

Question 19

Which should always be the first step in the Continuous Change Management Cycle?

Options:

A.

Ideas.

B.

Prioritization.

C.

Discovery.

D.

Action.

Question 20

According to the Agile Manifesto Principles, what is the most effective way to convey information?

Options:

A.

Transparently

B.

Collaboratively

C.

Face-to-face

D.

Continuously

Question 21

Which is a factor used in the 'change formula' (Beckhard and Harris)?

Options:

A.

Level of dissatisfaction with the status quo.

B.

Expected return on investment and benefits.

C.

The quality of the leadership.

D.

Elapsed time it will take to achieve the change.

Question 22

In the context of AgilePM, what two types of Increment are associated with what is delivered?

Options:

A.

Solution and Product

B.

Timebound and Freeform

C.

Product and Process

D.

Team and Individual

Question 23

How does the Post-Project phase add value to a project?

Options:

A.

Define how the operation of the solution will be managed

B.

Iteratively explores the low- level detail of the requirements

C.

Checks how well the expected business benefits have been met

D.

Brigs a baseline of the Evolving Solution into operational use

Question 24

Which of the following helps to build competence in collaboration?

    Rewarding individual efforts

    No blame culture

    Asking for help

    Setting clear goals

Options:

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

Question 25

Which of the following statements about positive characteristics of an effective change team (Lencioni) are true?

    Members should be encouraged to draw attention to colleagues' failures to meet commitments.

    Conflict should be avoided to maintain good relationships.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 26

Which project role is responsible for mitigating the risk if there is a lack of commitment in the business opportunity?

Options:

A.

Business Sponsor

B.

Business Visionary

C.

Business Advisor

D.

Business Consortium

Question 27

Which of the following is an AgilePM principle?

Options:

A.

Never compromise your integrity

B.

Never compromise quality

C.

Never compromise the team

D.

Never promise quality

Question 28

Which of the following statements, about selecting the appropriate communication channels for a change initiative, are true?

    If the aim is to achieve active engagement, then rich communication is essential.

    Leaner channels are suitable where there is little chance of misinterpretation.

Options:

A.

Only 1 is true.

B.

Only 2 is true.

C.

Both 1 and 2 are true.

D.

Neither 1 nor 2 is true.

Question 29

How is contingency typically managed in a DSDM project?

Options:

A.

Not needed in a DSDM project.

B.

Allowed adding a percentage to the high-level estimates.

C.

Managed by varying the features to be delivered.

D.

Managed by varying time and cost

Question 30

Identify the missing word in the following sentence.

The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.

Options:

A.

Governor

B.

Champion

C.

Visionary

D.

director

Question 31

Which definition describes 'transition' in Bridges’ model of human transitions?

Options:

A.

The planned actions required to make a change.

B.

The emotional process of adjusting to a change.

C.

The time elapsed between letting go of the old and experimenting with new ways.

D.

The physical process of adopting new changes.

Question 32

When assessing the impact and severity of options on how to handle change, not all costs are financial. What type of cost is reflected in the downtime experienced while staff are trained to use a new process or system?

Options:

A.

Productivity dip.

B.

Safety & Wellbeing.

C.

Reputational.

D.

Opportunity.

Question 33

Which statement applies to the DSDM process?

Options:

A.

Can be configured and calibrated to cater for light or strong governance

B.

DSDM projects can deliver the phases in the DSDM process in any order

C.

Does not require the elaboration of supporting products for complex projects

D.

Provides an approach that can be used for all projects without change

Question 34

In the context of the project organization, which of the following are classed as External Stakeholders by Agile?

    Regulatory Authorities

    Developers

    Customers

    Employees

Options:

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

Question 35

In combination with Scrum, what does AgilePM provide for Scrum Masters?

Options:

A.

An opportunity to serve the organization by leading, training, and coaching the organization in its Scrum adoption

B.

A set of practices, tools, techniques, and methods to enhance the use of Scrum

C.

A framework that helps teams generate value through adaptive solutions for complex problems

D.

An incremental and evolutionary approach to product development that evolves with time

Question 36

In which step of the Continuous Change Management Cycle should change actions be broken into smaller tasks?

Options:

A.

Discovery.

B.

Ideas.

C.

Prioritization.

D.

Action.

Question 37

Which responsibility relates to the role of the Business Ambassador?

Options:

A.

Provide the team with strategic direction.

B.

Responsible for the Business Case and project budget.

C.

Resolve business issues and make financial decisions

D.

Provide day-to-day detail of the requirements during timeboxes

Question 38

Which of the following describes the role of the Scrum Master?

Options:

A.

Accountable for establishing Scrum, both within the Scrum Team and the wider organization, and for helping everyone understand and enact Scrum theory, practices, rules, and values.

B.

Accountable for maximizing the value of the product or service resulting from the work of their scrum teams.

C.

Responsible for monitoring progress against the baselined Delivery Plan

D.

Responsible for approving the solution as technically fit for purpose prior to deployment.

Question 39

When initially creating MoSCoW priorities, what is the primary focus?

Options:

A.

Project priorities

B.

Project increment priorities

C.

Timebox priorities

D.

Iterative Development priorities

Question 40

Which statement about change is correct for DSDM?

Options:

A.

Change is a symptom of an inability to define requirements properly

B.

Avoid change whenever possible

C.

Change is inevitable and males estimating very difficult

D.

Project operate with a changing world

Question 41

When using the Iterative Development technique, which of the following should each cycle include?

1. Though

2. Action

3. Control

4. Conversation

Options:

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

Question 42

Which of the following statements about the Project Approach Questionnaire (PAQ) are true?

    Should be revisited at the end of Foundations.

    Should be revisited each time Foundations is revisited.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

Question 43

If two separate development teams are required to work on the same project, how will this be managed?

Options:

A.

Both teams can share the same Product Owner

B.

Each team will need a different Scrum Master

C.

Each team will have a different Business Visionary

D.

There will be two projects with different project roles

Question 44

According to the brain science of resistance, which of the key neural factors is an example of a fixed mindset?

Options:

A.

Routine seeking.

B.

Emotional reaction to forced change.

C.

Cognitive rigidity.

D.

Short-term focus.

Question 45

Which of the following statements about the MoSCoW rules for the ratio of prioritized Requirements are true?

    The minimum Usable Subset must not exceed 60% of the total number of requirement

    It is recommended that around 20% of available effort should be allocated to Could requirements.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 true