Question 1

In a free format Timebox, when should reviews take place?

Options:

A.

During the Kick-Off phase

B.

Throughout the body of the Timebox.

C.

During the Close.Out phase

D.

After the Timebox has been completed

Question 2

Identify the missing words in the following sentence.

Principles 1 –Focus on the Business Need suggests that every decision taken during a project should be [?] – to deliver what the business needs to be delivered.

Options:

A.

The responsibility of the Business Sponsor

B.

Share between all of the project roles

C.

Viewed in light of the overriding project goal

D.

Made collaboratively

Question 3

What is the MoSCoW technical used for?

Options:

A.

Understanding and managing priorities.

B.

Ensuring a team-based approach through visual and verbal communication and collaboration.

C.

Creating a visual representation of a problem or a solution.

D.

As an opportunity to share information across the team and to do any day.to.day re-planning and reorganizing as necessary when issues occur.

Question 4

What phase will decide on which projects are started, based on a clearly defined objective?

Options:

A.

Pre-Project

B.

Feasibility

C.

Foundations

D.

Post-project

Question 5

How is contingency typically managed in a DSDM project?

Options:

A.

Not needed in a DSDM project.

B.

Allowed adding a percentage to the high-level estimates.

C.

Managed by varying the features to be delivered.

D.

Managed by varying time and cost

Question 6

Which statement about DSDM roles is true?

Options:

A.

In DSDM, one person must hold several roles

B.

One DSDM roles does NOT necessarily mean one person

C.

All DSDM roles should be shared

D.

DSDM roles should NOT be split between two people

Question 7

What is the purpose of the Foundations Summary?

Options:

A.

To document how stakeholders will be engaged and standards that will be applied.

B.

To define the tools, techniques, customer, practices and standards that will be applied

C.

To provide enough information to decide whether the project is likely to deliver return on investment

D.

To define the scope of the requirements that the project needs to address