Agile Project Management (AgilePM) Practitioner Exam Questions and Answers
Which statement should be recorded under the High-level change approach heading?
Using the information provided in the additional information, answer the following question on building a change analytics strategy.
Is the measure requested by the Customer Services Director likely to be affected by any of the practical considerations of data analytics?
Using the information provided in the additional information, answer the following question on building a change analytics strategy.
Do the measures to be monitored by the CEO represent appropriate ‘leading’, result-oriented measures for the effectiveness of the change interventions?
Sales staff failed to achieve last month’s sales targets when training in the mobile products and supporting sales systems and processes was first started. This month the sales team is working after hours and weekends to try to meet the current targets while developing the new skills needed. It is generally felt that this situation is unsustainable.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?
Answer the following questions about applying the principles for building
engagement to the Change Programme, defined by Hodges.
Which 2 actions demonstrate inclusivity?
Answer the following questions about using facilitation of a workshop to co-
design organizational change.
When facilitating a workshop to design a process, which recommendation is MOST likely to create a good solution?
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions. Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.
On seeing plans for the office move, the Selco staff are worried that some desk allocations do not have access to natural light. The relocation leadership team held a workshop as soon as the issue was raised and has allocated these desks to be ‘hot-desks,’ not used by staff permanently based in the office.
Is this an appropriate approach to reward the brain in the need for ‘certainty,’ and why?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 statements BEST explain why the CEO is appropriate for the role of Sponsor for the Change Programme?
The Applications Manager agreed to the acquisition by UniCo because they knew that growing Selco needed more investment than they could raise and that they personally didn’t have the skill set to move from technical leader to business leader.
Which preference does this behavior BEST display?
Which statement should be recorded under the High-level timing considerations heading?
Answer the following question about different language style preferences
identified by Pashler et. al. using VARK preferences.
As part of the Capability and skills development workstream, the Human
Resources (HR) Manager is considering the training needs of staff
managers undertaking staff appraisals. The HR Manager is designing the
learning activities so that they will appeal to differing ways for receiving
and processing information.
Column 1 is a list of learning activities that could be used to develop the staff.
For each learning activity in Column 1, select from Column 2 the VARK
preference to which it relates. Each selection from Column 2 can be used
once, more than once or not at all.


To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?
The Legal Specialist has reviewed the plans for the rebranding work and has assessed how this will affect current and future contracts. They are now pressing the Change Manager to establish the deadlines and to schedule when their input will be most needed.
Which preference does this behavior BEST display?
For cognitive learning, which is the BEST example of providing ' learning feedback ' ?
Column 1 is a list of individuals from within the Xan Insurance Company
and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project
Management team role they are fulfilling. Each selection from Column 2 can
be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
Business Sponsor
Business Analyst
Business Ambassador
Business Advisor
Solution Developer
Technical Coordinator
DSDM Coach
Project Manager

Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
Answer the following questions about actions to be taken by different
roles.
The Business Sponsor has decided that the new coffee shop insurance
product website pages will include the financial transaction functionality to
support the end-to-end sales process. The Business Sponsor views this as a
valuable sales tool, enabling customers to pay for insurance policies online. If
successful, this new financial transaction functionality is to be made available
across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work
required to deliver the required solution including the new Must Have
requirement. The areas to be discussed include specialist skills required and
possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 actions should the Business Sponsor take to implement the new Must
Have requirement?
Which 2 actions should the Technical Coordinator take to implement the new
Must Have requirement?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.

Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
A difference of opinion on the outcome of an earlier project has created a
' them and us ' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?
Xan Insurance Company is a friendly company with no separate private offices
for individual managers. Staff members prefer to wander around the office
space and have one-to-one chats rather than use email or have lots of
meetings.
What action should the Project Manager take when planning for effective
communication throughout the Web project?
Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
' all members of the project understand and accept the DSDM approach ' .
What action should the Project Manager take?
Answer the following questions about the DSDM Lifecycle.
Decide if each observation is an appropriate application of Agile Project Management for
this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance
Manager that it was a fixed price for a fixed specification ' project. The Project Manager
has decided that the best way to tackle it would be to leave the development of the least
valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Which 2 actions should the Project Manager take to implement the new Must
Have requirement?
Which 2 statements represent appropriate entries for the plan for Post-Project
activities?
Answer the following questions about the use of the Agile principles.
Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional
wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.
Which Agile principle MOST influences this course of action?
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the
agreement of the team.
Which Agile principle MOST influences this course of action?
Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?
A three-month timeframe has been specified to catch the seasonal sales window.
Which Agile principle MOST influences this course of action?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
2. The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
3. Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
4. The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
5. The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
Column 2:
A) Thought
B) Action
C) Conversation

The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are
four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and
to know who should be where. Some of the contractors have started to turn up late to the site.
Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The
Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.
Answer the following questions about motivating the contractor teams according to Agile Project Management.
How should the Project Manager encourage the resources to operate more successfully?
Which 2 statements explain why the Timber Tigers ' Site Manager would be an appropriate Solution Developer?
When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?
What action should the Project Manager take to plan the deployment activities?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project
Management when developing the Delivery Plan?
Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:
Hydrotherapy in Mineral-Rich Spring Pools
Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote
deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush
and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.
In addition to the Developers, the teams include:

(Which one of the following statements does NOT align with AgilePM ' s MoSCoW prioritization?)
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(Hira decides to update the Delivery Plan to prioritize the delivery of the hydrotherapy facilities first for early testing.
Is this action appropriate?)
(During the Foundations phase, Lee Tan raised concerns about the lack of detailed upfront requirements for the Eco-spa, fearing confusion, constant changes, uncertainty and inefficiency.)
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Which 2 of the following actions align with AgilePM practices for defining and estimating the work of Project Increment 4 during the Foundations phase?)
(Which one of the following actions should Hira take to balance the benefit of agile leadership whilst ensuring alignment of the Project Increment with project objectives?)
(There were several responses to Brinda Vyas ' suggestion of a tranquil garden for guided meditation. While all valid and valuable, which opinion does NOT align with AgilePM responsibilities?)
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(Sarah Lark asks Mira Bachar how Spa treatments will remain aligned with the demands of guests post-launch. Mira explained that the Operations Delivery Team will address this in the final Sprint.
Is this approach aligned with AgilePM?)
(Brinda Vyas has been absent for two weeks, leaving Mira Bachar and the Delivery Teams to make decisions. Recent strategic adjustments haven ' t been communicated to the Delivery Teams causing frustration and risk of rework.
Which 2 statements describe how this risk should be handled within the AgilePM framework?)
(Lee Tan, General Manager of EPR Southeast Asia, is serving as a Business Advisor during Project Increment 4. He has not attended any Sprint Reviews, calling them " project meetings " and " a waste of time. " He later complains to Sarah about the lack of project awareness.
Which of the following actions reflects an AgilePM approach?)
Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(Which of the following describes AgilePM ' s approach to estimation?)
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(When defining and estimating work for Project Increment 4, the Delivery Teams must account for uncertainty in integrating the Eco-spa into the guest experience.
Which 2 of the following approaches align with AgilePM principles for managing uncertainty in estimation?)
Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:
Hydrotherapy in Mineral-Rich Spring Pools
Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote
deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush
and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.
In addition to the Developers, the teams include:

(Which of the following actions is appropriate when defining prioritizable Product Backlog items for the ' Hydrotherapy in Mineral-Rich Spring Pools ' Product Goal?)
(Three months after launch, Mira Bachar informs Brinda Vyas that Spa usage has fallen below expectations. Guest feedback reveals that many were simply unaware that Spa experiences were available.)





