Pre-Summer Sale Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

APMG-International AgilePM-Practitioner Dumps

Agile Project Management (AgilePM) Practitioner Exam Questions and Answers

Question 1

Which statement should be recorded under the High-level change approach heading?

Options:

A.

Existing UniCo staff only have skills in providing the installation of large-scale computer systems.

B.

Fast-track training of the Sales staff means taking a member of staff away from the sales operational work.

C.

The senior management will be asked to share examples of other companies undertaking, and successfully overcoming, similar challenges.

D.

All four Change Initiative elements will be required to produce a monthly formal report for the CEO.

Question 2

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Is the measure requested by the Customer Services Director likely to be affected by any of the practical considerations of data analytics?

Options:

A.

No, because customer feedback should be prioritized over internal analysis.

B.

No, because the data would be collected by Customer Services’ operations after the changes.

C.

Yes, because the measure is not providing feedback on progress when action can be taken.

D.

Yes, because the measure may be inaccurate through restricting the data source to one area.

Question 3

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Do the measures to be monitored by the CEO represent appropriate ‘leading’, result-oriented measures for the effectiveness of the change interventions?

Options:

A.

No, because ‘leading’ metrics must be based on quantitative data.

B.

No, because these metrics are lagging, output-focused indicators.

C.

Yes, because these indicators will identify if UniCo sales continue to decline.

D.

Yes, because these metrics monitor benefits realization at senior management level.

Question 4

Sales staff failed to achieve last month’s sales targets when training in the mobile products and supporting sales systems and processes was first started. This month the sales team is working after hours and weekends to try to meet the current targets while developing the new skills needed. It is generally felt that this situation is unsustainable.

Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?

Options:

A.

Visibly celebrate examples of the Sales staff using the new skills and systems.

B.

Allow those Sales staff with opposing attitudes to use the old systems in parallel.

C.

Identify the options available for moving people out of the Sales area to other jobs.

D.

Assign some of the sales team to work exclusively on developing the necessary skills.

E.

Provide a clear timetable of change to those Sales staff preparing for future operations.

Question 5

Answer the following questions about applying the principles for building

engagement to the Change Programme, defined by Hodges.

Which 2 actions demonstrate inclusivity?

Options:

A.

Consider providing everyone at the next staff event with pens and notebooks with the UniCo logo and an image representing this change programme.

B.

Define in early key messages how the inclusion of Selco links to the strategic repositioning of UniCo in the marketplace.

C.

Encourage the team from Selco to continue to use their old logo as a way of maintaining some familiar symbolism they can identify with.

D.

Provide opportunities for staff who had volunteered to act as mentors during the Change Programme to meet to resolve resistance issues.

E.

Invite those staff who are asking questions about the Change Programme proposals to suggest what might work for them.

Question 6

Answer the following questions about using facilitation of a workshop to co-

design organizational change.

When facilitating a workshop to design a process, which recommendation is MOST likely to create a good solution?

Options:

A.

The focus should be on immediate action to reduce the organizational costs.

B.

The workshop should be held off-site to create independent thought.

C.

The participants should cover all elements of the process and its implementation.

D.

Only the senior decision-makers should attend to ensure implementation is viable.

Question 7

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions. Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.

On seeing plans for the office move, the Selco staff are worried that some desk allocations do not have access to natural light. The relocation leadership team held a workshop as soon as the issue was raised and has allocated these desks to be ‘hot-desks,’ not used by staff permanently based in the office.

Is this an appropriate approach to reward the brain in the need for ‘certainty,’ and why?

Options:

A.

No, because a change solution needs to be permanent to achieve ‘certainty.’

B.

No, because the resolution of the issue should be delegated to those affected.

C.

Yes, because loss of ‘certainty’ mostly affects those at lower organizational levels.

D.

Yes, because ‘certainty’ is rewarded when issues can be resolved promptly and openly.

Question 8

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Which 2 statements BEST explain why the CEO is appropriate for the role of Sponsor for the Change Programme?

Options:

A.

Has a reserved, thoughtful leadership style which allows others to establish new behaviors without fear of criticism.

B.

Will provide an alternative view, due to a personal unease that the different direction for UniCo is outside the CEO’s own experience.

C.

Likes to be involved in the operational detail in order to have control of changes as they happen.

D.

Appreciates that expenditure has to happen promptly and assigns budget appropriately to support the change.

E.

Is committed to promoting this change as the future direction and has the authority to make it a priority.

Question 9

The Applications Manager agreed to the acquisition by UniCo because they knew that growing Selco needed more investment than they could raise and that they personally didn’t have the skill set to move from technical leader to business leader.

Which preference does this behavior BEST display?

Options:

A.

Extravert.

B.

Introvert.

C.

Thinking.

D.

Feeling.

Question 10

Which statement should be recorded under the High-level timing considerations heading?

Options:

A.

The traditional market has changed over the last year and UniCo can no longer rest on its previous success.

B.

UniCo lost significant market share in the last six months and faces ongoing increased competition in the next year.

C.

UniCo’s new finance system was delivered in the last quarter and training in the new system is almost complete.

D.

Completing the large contract with a Utilities company over the next nine months is a vital step to achieving the end vision.

Question 11

Answer the following question about different language style preferences

identified by Pashler et. al. using VARK preferences.

As part of the Capability and skills development workstream, the Human

Resources (HR) Manager is considering the training needs of staff

managers undertaking staff appraisals. The HR Manager is designing the

learning activities so that they will appeal to differing ways for receiving

and processing information.

Column 1 is a list of learning activities that could be used to develop the staff.

For each learning activity in Column 1, select from Column 2 the VARK

preference to which it relates. Each selection from Column 2 can be used

once, more than once or not at all.

as

as

Options:

Question 12

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?

Options:

A.

Is good at quietly implementing directions without challenging decisions at every step.

B.

Is well-positioned to bring together other line leaders facing similar change situations.

C.

Has a strong network due to supporting all staff at all levels organization-wide.

D.

Has direct line authority over the staff who will be changing internal IT systems.

E.

Wants to gain experience in change management to improve future implementations of IT systems.

Question 13

The Legal Specialist has reviewed the plans for the rebranding work and has assessed how this will affect current and future contracts. They are now pressing the Change Manager to establish the deadlines and to schedule when their input will be most needed.

Which preference does this behavior BEST display?

Options:

A.

Thinking.

B.

Feeling.

C.

Judging.

D.

Perceiving.

Question 14

For cognitive learning, which is the BEST example of providing ' learning feedback ' ?

Options:

A.

Giving supervisor feedback on return to work.

B.

Testing before and after learning.

C.

Reviewing learners’ ideas in a group discussion.

D.

Discussion at the learners ' next annual performance reviews.

Question 15

Column 1 is a list of individuals from within the Xan Insurance Company

and their key responsibility within the Web project.

For each individual in Column 1, select from Column 2 the Agile Project

Management team role they are fulfilling. Each selection from Column 2 can

be used once, more than once or not at all.

Column 1

Manager of Web & Digital

Media - will oversee and report

progress on the delivery of the

overall system.

Finance Director - has

budgetary control and will

release finance for the project

subject to expected benefits.

Sales Manager - will formulate

design options for new

business processes that do not

adversely affect business as

usual.

Operations Manager - oversees

the design and integrity of the

technical aspects of the

solution.

Column 2

    Business Sponsor

    Business Analyst

    Business Ambassador

    Business Advisor

    Solution Developer

    Technical Coordinator

    DSDM Coach

    Project Manager

as

Options:

Question 16

Which 2 statements represent appropriate entries for the Prioritised

Requirements List?

Options:

A.

Creation of a new coffee shop insurance product on the existing website

is expected to increase the insurance company ' s revenues by up to 10%

per week.

B.

All correspondence sent to coffee shop owners by the new system should

contain the XAN logo in the top left hand corner of the page.

C.

Further website developments to allow existing customers to access

services online are NOT to be included within the scope of this project.

D.

The Business Visionary will provide a formal acceptance of the coffee

shop insurance product.

E.

An assessment will be made of the effectiveness of the techniques used

on the project, in line with the principles of Agile Project Management.

Question 17

Time is running short and the Must Have requirements for the data entry screen

of the web page, as recorded in the Prioritised Requirements List, are not going

to be completed on time.

What action should the Project Manager take?

Options:

A.

Change the end date of the Timebox.

B.

Ensure that this issue is escalated to the project level roles.

C.

Amend the end date in the Delivery Plan.

D.

Accept that the Must Have requirements will not be delivered on time.

Question 18

Answer the following questions about actions to be taken by different

roles.

The Business Sponsor has decided that the new coffee shop insurance

product website pages will include the financial transaction functionality to

support the end-to-end sales process. The Business Sponsor views this as a

valuable sales tool, enabling customers to pay for insurance policies online. If

successful, this new financial transaction functionality is to be made available

across all other insurance products. This is a new Must Have requirement.

All parties are to be invited to a workshop to discuss the additional work

required to deliver the required solution including the new Must Have

requirement. The areas to be discussed include specialist skills required and

possible legal, financial and technical standards to be adhered to.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 actions should the Business Sponsor take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Check the viability of the project, following the inclusion of the new Must

Have requirement.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

E.

Assess the impact of the new Must Have requirement on the original

Business Case.

Question 19

Which 2 actions should the Technical Coordinator take to implement the new

Must Have requirement?

Options:

A.

Ensure that the latest version of the website design in the Solution

Architecture Definition is provided to all members of the Solution

Development Team.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

D.

Consolidate and circulate an agenda for the workshop.

E.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

Question 20

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

as

Options:

Question 21

Resources are limited. The Sales Manager has two marketing assistants who

may be able to give a few hours a week between them to the project.

What action should the Project Manager take?

Options:

A.

Try to secure formal agreement as to how many hours per week the

marketing assistants will spend on the project.

B.

Accept that members of the Solution Development Team will be

inconsistent.

C.

Make each Timebox as long as possible to ensure the marketing

assistants have enough time to complete any work allocated to them

within the boundaries of the Timebox.

D.

Schedule the two marketing assistants to work at different times so they

can hand matters over to one another.

Question 22

A difference of opinion on the outcome of an earlier project has created a

' them and us ' culture between the Sales Department and the Operations

Department.

What action should the Project Manager take to resolve this?

Options:

A.

Allow the different skillsets to work independently of one another so as

not to create further conflict.

B.

Brief the team and the Business Visionary on the use of an Agile Project

Management approach and the requirement to collaborate.

C.

Appoint only those members of staff who are prepared to work

collaboratively.

D.

Circulate a copy of the Business Case to all members of the Solution

Development Team and project-level roles and invite feedback.

Question 23

Xan Insurance Company is a friendly company with no separate private offices

for individual managers. Staff members prefer to wander around the office

space and have one-to-one chats rather than use email or have lots of

meetings.

What action should the Project Manager take when planning for effective

communication throughout the Web project?

Options:

A.

Identify those individuals with power and influence over the project and

what information they require.

B.

No action is required as the existing form of spontaneous informal

communication is suitable for all project level and Solution Development

Team members.

C.

As this is already common practice, assume all Solution Development

Team members have effective communication skills.

D.

Mandate the use of email so that all communications are recorded for

future reference.

Question 24

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

' all members of the project understand and accept the DSDM approach ' .

What action should the Project Manager take?

Options:

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Question 25

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification ' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Question 26

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Question 27

Which 2 actions should the Project Manager take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

C.

Update the Delivery Plan to show the new financial transaction

functionality as a deliverable.

D.

Source and hire a web developer with experience in developing online

financial transaction functionality.

E.

Consolidate and circulate an agenda for the workshop.

Question 28

Which 2 statements represent appropriate entries for the plan for Post-Project

activities?

Options:

A.

The Sales Manager will create a company-wide email showing the

number of policies sold weekly by each of the sales assistants.

B.

Before the product is deployed, the Sales Manager will circulate a copy of

the revised sales procedure for processing coffee shop insurance sales.

C.

The Project Manager will attend Daily Stand-up meetings to observe

progress.

D.

A report showing the number of application forms completed online

through the website for coffee shop insurance policies will be produced

weekly.

E.

Once the new system has been deployed, the time it takes to process

sales online will be compared with the time it takes to process new

policies sold through telephone sales.

Question 29

Answer the following questions about the use of the Agile principles.

Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional

wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.

Which Agile principle MOST influences this course of action?

Options:

A.

Collaborate.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Communicate continuously and clearly.

Question 30

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

Options:

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels ' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Question 31

The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the

agreement of the team.

Which Agile principle MOST influences this course of action?

Options:

A.

Deliver on time.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Question 32

Answer the following questions about the tracking and control activities carried out within the project.

Decide whether each activity has been applied appropriately and select the response that supports your decision.

During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager

organized a Facilitated Workshop with the project team to discuss and agree the requirements.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because discussing requirements in the presence of project stakeholders will promote communication and buy-in.

B.

Yes, because this will allow each team member working in a Timebox to raise any issues which may hinder their progress.

C.

No, because early and frequent delivery of the product features will on its own be sufficient to maintain engagement with the stakeholders.

D.

No, because a Review Session should have been scheduled to enable the Solution Development Team to validate their understanding of the stakeholders '

expectations.

Question 33

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because this will allow the Solution Development Team to focus on the quality of the Solution Development Timebox ' s deliverable as a whole, in order to keep focus on the business need.

B.

Yes, because it will be easier to set acceptance criteria for the Solution Development Timebox as a whole, rather than setting specific acceptance criteria for each individual requirement.

C.

No, because the acceptance criteria for the Solution Development Timebox are just the amalgamation of the individual requirements ' acceptance criteria, with nothing extra.

D.

No, because the Solution Development Timebox objective will change if any new requirements emerge or any lower priority requirements are de-scoped.

Question 34

What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?

Options:

A.

The Project Manager should extend the timescale of Timebox B and shorten Timebox C.

B.

The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List.

C.

The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.

D.

The Project Manager should move a Must Have requirement from Timebox B into Timebox C.

Question 35

A three-month timeframe has been specified to catch the seasonal sales window.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Question 36

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?

Options:

A.

The Feasibility Assessment should contain a detailed description of costs and benefits associated with the refurbishment.

B.

Enough description of the required refurbishment work should be provided to enable the Architecture Angels ' Finance Director to decide whether the project should proceed.

C.

During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.

D.

The Outline Business Case should demonstrate the mitigation of all business risks associated with the refurbishment.

E.

The Outline Business Case should describe the full team structures to be engaged for the later phases of the project.

Question 37

Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1. The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.

2. The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.

3. Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.

4. The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.

5. The Gardener began planting the borders and has placed an order for further bulbs to complete this task.

Column 2:

A) Thought

B) Action

C) Conversation

as

Options:

Question 38

The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are

four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and

to know who should be where. Some of the contractors have started to turn up late to the site.

Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The

Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.

Answer the following questions about motivating the contractor teams according to Agile Project Management.

How should the Project Manager encourage the resources to operate more successfully?

Options:

A.

Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan.

B.

Hold a separate Daily Stand-up meeting for contractors only.

C.

Provide a detailed plan of activity for each contractor team.

D.

Schedule the electrical and plumbing teams so that they work on different Timeboxes.

Question 39

Which 2 statements explain why the Timber Tigers ' Site Manager would be an appropriate Solution Developer?

Options:

A.

Accustomed to bringing in contract staff for short periods of time.

B.

Closely manages the building team so that they consistently produce high-quality work.

C.

Is able to represent the team in all daily meetings.

D.

An experienced builder who is good at turning a brief into a practical design.

E.

Is empowered by Timber Tigers ' management to make decisions on the building work.

Question 40

When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?

Options:

A.

Hints and tips on how to influence and persuade others.

B.

An understanding of the decision-making process.

C.

Background to the disagreement and the reasons for this.

D.

Empowerment to discuss any wider project issues that may arise during the workshop.

E.

A step-by-step guide to running an effective workshop.

Question 41

What action should the Project Manager take to plan the deployment activities?

Options:

A.

Prepare a Timebox Plan for the next Development Timebox.

B.

Check the Delivery Plan for deployment activities and update as required.

C.

Create a plan of activities to deploy the solution at the end of Timebox C.

D.

Update the Timebox Plan for Timebox C with the activities required to deploy the solution.

Question 42

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project

Management when developing the Delivery Plan?

Options:

A.

The Project Manager should include any known constraints associated with planning permission.

B.

The Project Manager should NOT need to identify any risks this early in the project.

C.

The approach to the project should be based on the Project Approach Questionnaire responses.

D.

The Earth Excavations ' Head Gardener should be excluded from discussions related to deliverables since contracts are NOT yet signed.

E.

The Architecture Angels ' Marketing Director should be involved in the development of the Delivery Plan.

Question 43

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

as

(Which one of the following statements does NOT align with AgilePM ' s MoSCoW prioritization?)

Options:

A.

' Must Have ' requirements are essential to success, without them the solution is unworkable, unsafe, illegal, or pointless.

B.

' Should Have ' requirements are important and must be delivered for the project be deemed successful.

C.

' Could Have ' requirements are valuable and desirable from a business perspective but will only be delivered if time and resources allow.

D.

' Won ' t Have this time ' requirements are explicitly out of scope of the current Solution Increment but should be reconsidered for inclusion later.

Question 44

As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:

. Heavy rainfall affecting the Wellness Garden.

. Local supplier issues causing material delivery delays.

· Dependency on external contractors for hydrotherapy equipment.

The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the

context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.

In addition to the Developers, the teams include:

as

(Hira decides to update the Delivery Plan to prioritize the delivery of the hydrotherapy facilities first for early testing.

Is this action appropriate?)

Options:

A.

Yes, because the Delivery Plan should adapt to real-world conditions.

B.

Yes, because all sequencing changes should be documented in the Delivery Plan.

C.

No, because the Delivery Plan is fixed after the Foundations phase unless a Must Have requirement is at risk.

D.

No, because sequencing should be a collaborative decision, not determined by Hira alone.

Question 45

(During the Foundations phase, Lee Tan raised concerns about the lack of detailed upfront requirements for the Eco-spa, fearing confusion, constant changes, uncertainty and inefficiency.)

Options:

A.

Approach-based, because there is lack of clarity of purpose preventing development from starting.

B.

Approach-based, because Lee should understand AgilePM uses iterative development and increment delivery, translating high-level requirements into valuable solutions.

C.

VUCA-based, because market shifts and changing guest expectations require detailed definition of requirements.

D.

VUCA-based, because external sustainability pressures create uncertainty that requires a flexible scope.

Question 46

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

as

(Which 2 of the following actions align with AgilePM practices for defining and estimating the work of Project Increment 4 during the Foundations phase?)

Options:

A.

Conduct a full analysis of Spa treatments to create a fixed guest service specification.

B.

Host a stakeholder workshop to prioritize integrating the Spa into the resort experience.

C.

Develop high-level estimates of effort and cost for Spa facilities and IT systems.

D.

Prepare a risk report on aligning Spa services with guest experience.

E.

Define work items in enough detail for Developers to start design work on treatments.

Question 47

(Which one of the following actions should Hira take to balance the benefit of agile leadership whilst ensuring alignment of the Project Increment with project objectives?)

Options:

A.

Create a Delivery Plan outlining high-level activities for an aligned Eco-spa solution.

B.

Organize workshops with Brinda, the Delivery Teams and stakeholders to co-create a shared vision.

C.

Delegate to Team Leaders the task of defining deliverables that align with Brinda ' s vision.

D.

Collaborate with Brinda and Sukra to define actionable Product Backlog items.

Question 48

(There were several responses to Brinda Vyas ' suggestion of a tranquil garden for guided meditation. While all valid and valuable, which opinion does NOT align with AgilePM responsibilities?)

Options:

A.

Brinda Vyas emphasized the garden ' s strategic importance in enhancing guest experience and meeting business goals.

B.

Brinda Vyas linked the garden to the resort ' s long-term objectives and the project ' s business case.

C.

Sukra Aroon considered technical feasibility and identified risks in infrastructure requirements.

D.

Sukra Aroon dismissed the garden rationale, saying guided meditation could happen in a treatment room.

E.

Mira Bachar prioritized the garden against other deliverables, ensuring alignment with stakeholder needs and project goals.

F.

Mira Bachar clarified the Product Goals for the Delivery Teams to deliver to contribute to the overall solution.

G.

A local expert shared how the garden ' s design could enhance meditation experiences for guest in line with well-being principles.

Question 49

As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:

. Heavy rainfall affecting the Wellness Garden.

. Local supplier issues causing material delivery delays.

· Dependency on external contractors for hydrotherapy equipment.

The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the

context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.

In addition to the Developers, the teams include:

as

(Sarah Lark asks Mira Bachar how Spa treatments will remain aligned with the demands of guests post-launch. Mira explained that the Operations Delivery Team will address this in the final Sprint.

Is this approach aligned with AgilePM?)

Options:

A.

Yes, because Delivery Teams should focus on delivery until the final Sprint.

B.

Yes, because realization planning can reasonably happen in the final Sprint.

C.

No, because realization is the Business Visionary ' s responsibility, NOT the Delivery Teams.

D.

No, because realization planning should be part of the business case before development starts.

Question 50

(Brinda Vyas has been absent for two weeks, leaving Mira Bachar and the Delivery Teams to make decisions. Recent strategic adjustments haven ' t been communicated to the Delivery Teams causing frustration and risk of rework.

Which 2 statements describe how this risk should be handled within the AgilePM framework?)

Options:

A.

Continue increment work based on the backlog, assuming adjustments can be made when Brinda Vyas returns.

B.

Mira Bachar and the Delivery Teams should document assumptions behind decisions and continue progress without validation.

C.

Hira should engage other business stakeholders to assume Brinda Vyas ' responsibilities to ensure the Delivery Teams receives strategic guidance.

D.

Hira should escalate to Sarah Lark, the Business Sponsor, to replace Brinda Vyas with another qualified Business Visionary.

E.

The Delivery Teams should focus on backlog items with clear business direction and pause tasks that require Brinda Vyas ' input until guidance is available.

Question 51

(Lee Tan, General Manager of EPR Southeast Asia, is serving as a Business Advisor during Project Increment 4. He has not attended any Sprint Reviews, calling them " project meetings " and " a waste of time. " He later complains to Sarah about the lack of project awareness.

Which of the following actions reflects an AgilePM approach?)

Options:

A.

Meet with Lee to explain the value of Sprint Reviews and plan his engagement.

B.

Provide Lee with Sprint summaries to keep him informed without wasting his time.

C.

Ask Sarah to require Lee ' s attendance at all Sprint Reviews.

D.

Schedule briefings with Lee before each Sprint using Project Planning insights.

Question 52

Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

as

(Which of the following describes AgilePM ' s approach to estimation?)

Options:

A.

Estimates should be avoided whenever possible, as Agile projects must prioritize flexibility over predictability.

B.

Estimates should be as detailed as possible from the start to minimize uncertainty and reduce the need for later refinement.

C.

The precision of estimates may vary as the project progresses, but they should always be as accurate as possible.

D.

Estimates should only be revisited if stakeholders challenge them, as refining estimates too frequently causes unnecessary rework.

Question 53

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

as

(When defining and estimating work for Project Increment 4, the Delivery Teams must account for uncertainty in integrating the Eco-spa into the guest experience.

Which 2 of the following approaches align with AgilePM principles for managing uncertainty in estimation?)

Options:

A.

Use broad estimation ranges for high-uncertainty work and refine estimates as more information becomes available.

B.

Avoid committing to estimates for uncertain work until all unknowns are resolved.

C.

Identify key assumptions behind estimates and revisit them regularly as the project evolves.

D.

Ensure all estimates are fixed early to maintain control over scope and budget.

E.

Exclude uncertain work from estimation until development is underway and clearer details emerge.

Question 54

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

as

(Which of the following actions is appropriate when defining prioritizable Product Backlog items for the ' Hydrotherapy in Mineral-Rich Spring Pools ' Product Goal?)

Options:

A.

Break the Product Goal into smaller Backlog items, each justified by the value it contributes to the hydrotherapy experience described.

B.

Create a Backlog item for every infrastructure need to ensure nothing is missed from the range of features to be prioritized.

C.

Use MoSCoW to prioritize Product Backlog items based on technical feasibility and cost of delivery each feature described.

D.

Defer the prioritization of Product Backlog items until Sprint Planning so that the Delivery Teams can decide what is achievable at that time.

Question 55

(Three months after launch, Mira Bachar informs Brinda Vyas that Spa usage has fallen below expectations. Guest feedback reveals that many were simply unaware that Spa experiences were available.)

Options:

A.

Approach-based, because realization planning should have included guest communication to effectively communicate the Spa experiences on offer.

B.

Approach-based, because marketing and operations should have collaborated during the Foundations phase to ensure Spa experiences were promoted.

C.

VUCA-based, because guest demographics or preferences change unpredictably making it difficult to predict engagement.

D.

VUCA-based because external uncertainty affects how guests discover new services making it difficult to control.

Page: 1 / 18
Total 184 questions