Summer Sale Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

Autodesk BIM_MGT_101 Dumps

Page: 1 / 6
Total 57 questions

Autodesk Certified Professional in BIM Management for Building Design Questions and Answers

Question 1

A team member accidentally unpinned and dragged a linked CAD file, and it is no longer aligned according to the Shared Coordinates.

How can the BIM manager realign the linked CAD file in the Revit model?

Options:

A.

Publish the Coordinates from the host model to the linked CAD file.

B.

Select the linked CAD file and use the Move command to realign the link.

C.

Select the Shared Site of the linked CAD file and move the instance to the defined Site.

D.

Ask the consultant to update the CAD file and relink it.

Question 2

A BIM manager is preparing to onboard a group of subcontractors into Autodesk Forma for a large healthcare project. These subcontractors need access to a limited set of model files related only to interior partitions, but should not be able to view or modify structural, MEP, or scheduling content.

What two actions should the BIM manager take to manage data security in this scenario? (Select two.)

Options:

A.

Create and share a Package with specific set-up content.

B.

Provide access to the entire model set but watermark any non-applicable content.

C.

Assign full project access and ask team leads to verbally explain access limitations.

D.

Hide coordination issues from the subcontractors to limit liability.

E.

Assign role-based permissions and folder-level access aligned with the subcontractors’ scope.

Question 3

A multidisciplinary healthcare project has multiple firms contributing to a federated model. Early coordination reviews reveal data inconsistencies, unauthorized edits, and missed communication between design teams.

What is the most appropriate first step to establish effective coordination and risk mitigation across the delivery team?

Options:

A.

Assign responsibility for each firm to review and maintain its own models, document identified issues, and present findings during scheduled coordination meetings.

B.

Implement tighter access controls within the Common Data Environment by defining permissions, monitoring edits, and restricting changes to authorized team members.

C.

Develop and communicate protocols that clarify model ownership, editing rights, quality-control procedures, and expected communication channels.

D.

Require each discipline to submit a detailed modelling strategy, document its assumptions, and use this information to identify and resolve potential design conflicts.

Question 4

The BIM manager is launching a civic center project with strict sustainability and lifecycle data goals. During early planning, each discipline proposes different modelling approaches, and there is concern that downstream data handoff may be inconsistent.

To establish BIM goals and uses that ensure alignment from design through operations, what should the BIM manager do first?

Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.

Options:

A.

Ask each team to submit its standard BEPs for review and consolidate them into one reference document.

B.

Finalize the LOD matrix and data drops based on similar past projects, updating it during the design process as needed.

C.

Begin developing the internal BIM templates and content, assuming they will be applicable to this project.

D.

Host a stakeholder session to review the project-specific requirements and BIM uses, and establish mobilization needs and modelling requirements.

Question 5

A museum project anticipating generative iterations is being designed by a team working across multiple time zones under a tight schedule. The client hosts weekly meetings to review various façade options, document sustainability goals, and evaluate numerous energy analyses.

What project-specific training should the design technology team provide to prepare the team for client meetings and ensure successful project execution?

Options:

A.

AutoCAD, Autodesk Forma, generative design.

B.

Generative design, AutoCAD, Civil 3D.

C.

Forma Site Design, generative design, Autodesk Forma.

D.

Sustainability certification, Revit, Forma Site Design.

Question 6

Refer to the exhibits.

as

as

as

as

The firm’s technical group would like to show demolished elements as dashed red in all future projects. The BIM manager is updating the Revit template to meet this new standard.

Which Phase Graphic Override will accomplish this?

as

as

as

as

Options:

A.

Exhibit 4

B.

Exhibit 2

C.

Exhibit 1

D.

Exhibit 3

Question 7

A BIM manager is reviewing a consultant’s architectural model before the next coordination milestone. The project requires each model to conform to a defined naming convention, include COBie parameters, and populate shared parameters according to the Model Element Table. The BIM manager notices that several elements are missing metadata and that some naming is inconsistent.

Which step best supports a systematic evaluation of completeness and compliance with project standards?

Options:

A.

Manually review each element in the Model Browser to confirm naming and parameter completeness.

B.

Use a model checker or data-validation tool to compare parameter presence, naming conventions, and required values against the established project standard.

C.

Ask the design team to re-export the model with updated information based on verbal clarification and metadata from the BIM Execution Plan.

D.

Filter out incomplete elements in a 3D view and hide them to avoid confusion during coordination.

Question 8

During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.

Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)

Options:

A.

Email PDFs to the contractor every week.

B.

Update Publish Settings to include sheets.

C.

Create blank sheets for all disciplines.

D.

Enable Model Coordination.

E.

Schedule Publishes in Design Collaboration.

Question 9

The BIM manager received a subcontractor’s 3D model containing specialty equipment to be integrated into the federated model. Upon review, they observe that:

    Many elements lack consistent object styles and category assignments.

    Some components are modelled with excessive detail, affecting performance.

    Embedded data does not follow the project’s naming conventions outlined in the BEP.

What is the most appropriate next step when evaluating this geometry and content?

Options:

A.

Instruct the subcontractor to simplify geometry and reduce file size, even if some metadata and classifications are lost.

B.

Approve the model as-is to avoid delaying coordination and document the issues for review at the next quality-control milestone.

C.

Review the model against content standards, document noncompliance, and request revisions aligned with agreed deliverable requirements.

D.

Import the model into the coordination environment and apply view filters to hide excessive detail and inconsistencies.

Question 10

For a project that is well into its Design Development phase, it is discovered that there is an easement on the property that increases the setback by 1 ft 6 in. (450 mm).

Which method for updating the geolocation of the project would be least disruptive to the extended design team?

Options:

A.

Specify coordinates at a point along the setback edge using the new data.

B.

Reposition the civil site property-boundary resource file, then publish the new position coordinates to the civil file.

C.

Select all model elements in a 3D view and move them away from the increased setback boundary.

D.

Reset coordinates, reposition the site property-boundary resource file, then acquire coordinates from the repositioned civil file.

Question 11

The BIM manager is working in an Architectural model that uses the phases Existing and New Construction . They have linked in a Structural model that uses only Phase 1 for existing and Phase 2 for new construction. After linking, they notice that demolition elements from the Structural model do not display correctly in the demolition views.

Which approach allows the BIM manager to display linked elements correctly based on this phase setup, without changing the phases in the linked model?

Options:

A.

Apply a phase-filter override to the linked model using Visibility/Graphics settings.

B.

Open the linked model and manually change its phase names to match the host model.

C.

Map the linked model’s phases to the host model’s phases in the Revit Link properties.

D.

Override the linked view’s phase settings using view templates in the host model.

Question 12

A new project being set up requires consistency across all floor plans. However, because of variations in floor-to-floor heights, the project team needs a different View Range for each level.

What is the most efficient way to accommodate this?

Options:

A.

Deselect the Include box for View Range in the View Template.

B.

Keep one View Range for all plans and add Plan Regions as needed.

C.

Remove the View Template and control View Range through Visibility/Graphics.

D.

Duplicate the View Template for each view to control its View Range.

Question 13

During a weekly BIM health review, the BIM manager compares two versions of the same architectural Revit model submitted one month apart. The newer model’s file size has doubled, synchronization time has increased by 40%, and users report sluggish performance. A model audit reveals no major geometry changes, but warnings have increased from 600 to 750, and several Civil CAD files are now imported.

What is the most likely root cause of the model performance degradation?

Options:

A.

A rise in geometry complexity.

B.

An accumulation of audit history and backup data.

C.

The presence of imported Civil CAD files.

D.

The increase in model warnings.

Question 14

A regional user group raised awareness about a third-party add-on tool that enables a team to establish thresholds for model warnings. In addition, it automates suppressing warnings deemed negligible to a specific project.

Which two data points should a BIM manager gather to build a business case to have the tool approved for use across the firm? (Select two.)

Options:

A.

The cost per user multiplied by the number of entire office staff, including the cost of time to implement and train on the tool.

B.

How many of the firm’s competitors are already using the tool.

C.

The language that available training materials on the tool are in.

D.

The reliability of the tool creator and the time to install, test, and create training materials on the tool.

E.

The relevant user group, the projected cost to supply the group, and the anticipated time savings and/or risk mitigation that the tool would provide.

Question 15

A design team is distributing models to a construction team’s coordinator, who reports that the various models are not aligned to each other when linked into the coordination environment.

What step should the design team’s lead BIM manager take to resolve the positioning issue?

Options:

A.

Reset coordinates and advise the coordinator to link all models by Internal Origin to Internal Origin.

B.

Publish coordinates from the Main Model out to all linked consumed consultant files.

C.

Report coordinates to provide the coordinator with the desired positioning of each model for them to reposition.

D.

Advise consultants to acquire coordinates from the primary design team’s model and resubmit updated models.

Question 16

Refer to the exhibit.

as

A client has provided the design team with a title block family and a Shared Parameters file that must be used as part of their standards. Those provided parameters must be applied both in the Project Information area as well as the title block.

When the design team is in the project model and attempts to fill in information into the title block parameters, a question mark appears. What is the likely cause of this?

Options:

A.

The shared parameters were included in the title block family but were not loaded into the project file.

B.

The parameters were not included in the Shared Parameters file provided by the client.

C.

The Shared Parameters file was not added to the title block family and was using text instead of a label.

D.

The Sheet and Project Information fields were overwritten in the title block.

Question 17

An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client’s preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model’s compatibility with internal systems.

As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)

Options:

A.

Any add-ins required.

B.

Project units.

C.

Software version and build.

D.

Shared Coordinates.

E.

Graphic standards.

Page: 1 / 6
Total 57 questions