Weekend Sale Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

CMAA Construction-Manager Dumps

Certified Construction Manager (CCM) Questions and Answers

Question 1

Which schedule process determines the earliest times that schedule activities can start and Finish, and the total project duration?

Options:

A.

Master Schedule Review

B.

Forward Pass

C.

Schedule Update

D.

Backward Pass

Question 2

As the owner’s representative, you are providing on-site construction management services to a municipality for their new design-build city hall project.

The mechanical subcontractor discovers that his ductwork will not fit in the above-ceiling area of the Mayor’s office. Which entity is best-suited to resolve this risk?

Options:

A.

Owner (Municipality)

B.

Architect (DOR)

C.

Owner’s rep

D.

Design-Build Team

Question 3

Float, date, and duration are examples of

Options:

A.

schedule elements.

B.

schedule parameters.

C.

constraints.

D.

logic elements.

Question 4

Which of the following provides details about the front-end activities of the project during the pre-design and design phases, and highlights major project milestones such as substantial and final completion?

Options:

A.

Baseline Schedule

B.

Milestone Schedule

C.

As-Built Schedule

D.

Master Schedule

Question 5

An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?

Options:

A.

The owner should plan for delayed completion.

B.

Direct both the architect and GC to mitigate each delay and have the agency CM perform a schedule impact analysis to allocate delay responsibility.

C.

The architect and GC should be directed to add resources to mitigate each of their delays at no additional cost to the owner.

D.

The owner should charge the contractor daily liquidated damages.

Question 6

While conducting an inspection of the work in progress for a design-bid-build project, a CM notices that some of the completed work does not conform to the construction documents. The FIRST thing the CM should do is

Options:

A.

document the non-conforming work and distribute the documentation to the contractor, design professional, and client.

B.

discuss the concerns with the owner.

C.

direct the contractor to correct the non-conforming work.

D.

schedule a meeting with the design professionals and the client to discuss the issues.

Question 7

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

Options:

A.

Put the contractor's unopened bid in tight security until the bid opening has been completed.

B.

Send the bid back to the contractor and apologize for the mishap.

C.

Include the unopened bid. since it clearly was an oversight.

D.

Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Question 8

A relatively new general contractor has executed three projects. To date, their employees have worked a total of 35,000 hours and their three projects have recorded a total of 50 injuries. What is their recordable case rate?

Options:

A.

0.0014

B.

150

C.

286

D.

700

Question 9

When applying Business Intelligence (also known as data mining) to manage large volumes of construction project data, the source data must

Options:

A.

first exist in hard copy format.

B.

include advanced algorithms.

C.

first exist in digital format.

D.

include outliers and missing data.

Question 10

An agency CM is overseeing the construction of a large, complex multi-story, high security building in a remote area. The building had a specialized spire installed at the top, which serves as an encrypted signal transmitter. Construction is complete and the contractor has de-mobilized, but then it is discovered that the signal transmitter is not transmitting the signal. The owner's QC plan required testing for the functionality of the transmitter, but the contractor has not shown test results reflecting adequate performance. Who is responsible for the cost of remobilization?

Options:

A.

Designer of record

B.

Agency CM

C.

Contractor

D.

Owner

Question 11

A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.

Which statement most accurately portrays program status?

Options:

A.

On schedule, pay application accurately reflects percentage complete.

B.

Behind schedule, pay application exceeds percentage complete.

C.

Behind schedule, pay application accurately reflects percentage complete.

D.

On schedule, pay application exceeds percentage complete.

Question 12

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the client's Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

Options:

A.

Put the contractor's unopened bid in tight security until the bid opening has been completed.

B.

Send the bid back to the contractor and apologize for the mishap.

C.

Include the unopened bid. since it clearly was an oversight.

D.

Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Question 13

Under the Brooks Act, professional services of architects and engineers on federal projects must be

Options:

A.

funded by public dollars.

B.

audited every six months.

C.

qualification-based rather than bid.

D.

contracted before GC services.

Question 14

A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am–7pm, 5 days per week and that the bridge would be completed by September 1.

The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.

The CM should

Options:

A.

tell the contractor they have until September 1 and can only work 7am–7pm.

B.

discuss with the owner and tell the contractor to do only 1/2 of the bridge.

C.

meet with the owner and contractor to vet all issues/options and make a decision.

D.

meet with the contractor to go over realistic time frames and make a decision.

Question 15

It is ideal for the CM to assist in mitigating potential impacts and unforeseen issues that may develop as early as the

Options:

A.

construction phase.

B.

post-construction phase.

C.

design phase.

D.

pre-design phase.

Question 16

A project manager is working on a new transit station project. This client has never used an agency CM before. The project manager wishes to engage the client in defining the scope, budget, schedule, environmental conditions, and basic systems to be utilized. Which of the following would be MOST useful in engaging the client and defining the project requirements?

Options:

A.

Quality Management Plan

B.

Project Procedures Manual

C.

Kickoff Partnering Meeting

D.

Project Management Plan

Question 17

Industry best practice is to conduct a pre-bid conference. The intent of the pre-bid conference is to

Options:

A.

survey existing conditions and reveal unforeseen conditions.

B.

mitigate change orders and delays.

C.

limit the number of bidders on the project.

D.

resolve any questions about contract requirements and scope of work.

Question 18

A dispute arises during construction after the contractor encounters what they feel is unsuitable material. The CM is not notified about the areas of concern, and the contractor hauls 10.000 cy of material offsite. Three months later, the contractor submits a claim for additional cost to haul the material off. The CM should advise the owner that

Options:

A.

the owner should pay for the haul.

B.

the claim is not valid because the contractor failed to provide timely notice.

C.

the owner should pay the claim due to lack of owner information.

D.

the owner should pay 50% of the haul since the contractor did not notify the CM first.

Question 19

The narrative accompanying a CM-developed construction cost estimate during the design phase should include which of the following?

Options:

A.

Written confirmation of verbal data and assumptions made

B.

Suggestions for value management of building systems and other opportunities for savings

C.

CM's recommendation of improvements to specifications and quality of materials

D.

Means and methods of construction

Page: 1 / 7
Total 65 questions