Summer Sale Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

CompTIA PK0-005 Dumps

Page: 1 / 46
Total 460 questions

CompTIA Project+ Certification (2026) Questions and Answers

Question 1

A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).

Options:

A.

Update the issue log

B.

Create a project charter

C.

Validate the status report

D.

Monitor performance

E.

Approve deliverables

F.

Baseline the project schedule

Question 2

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

Options:

A.

Exploit

B.

Share

C.

Transfer

D.

Accept

Question 3

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

Options:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Question 4

Which of the following statements best describes Kanban?

Options:

A.

A workflow management method to maximize efficiency and enable continuous improvement.

B.

A board representing the different stages of a software solution.

C.

A dashboard used to facilitate scope alignment with the project team.

D.

A spreadsheet representing development tasks and how they relate to the business process being improved.

Question 5

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

Options:

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

Question 6

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

Options:

A.

IaaS

B.

XaaS

C.

DaaS

D.

SaaS

Question 7

A number of unexpected issues have occurred during the execution of a project that will negatively impact the timeline and costs. Which of the following would be best for the project manager to do to mitigate this situation?

Options:

A.

Update the issue log.

B.

Communicate with stakeholders.

C.

Use the contingency reserves.

D.

Review the risk register.

Question 8

Which of the following is a reason to use a SOW on a project?

Options:

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Question 9

During a project kickoff meeting, the project manager wants to set expectations for all of the team members. Which of the following actions should the project manager take to accomplish this goal?

Options:

A.

Assign tasks and responsibilities to the team members

B.

Provide an overview of the project objectives and timeline

C.

Develop a project communication plan

D.

Set a meeting cadence for the rest of the project

Question 10

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

Options:

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

Question 11

Participant attendance has been poor at the last few weekly meetings. The project manager wants to validate who the participants should be, how often the meetings should occur, and on which day and at what time the meeting should be held. Which of the following is the best place to validate this information?

Options:

A.

Project communication plan

B.

Project management plan

C.

Project business case

D.

Project schedule

Question 12

Which of the following provides a layered approach to logging in to systems that contain an organization ' s most valuable intellectual property?

Options:

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Question 13

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Options:

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

Question 14

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

Options:

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

Question 15

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Question 16

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Options:

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Question 17

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

Options:

A.

Remove access.

B.

Complete the project sign-off.

C.

Release the resources.

D.

Outline the lessons learned.

Question 18

A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?

Options:

A.

At home, using home internet and the company’s computer

B.

At a coffee shop, using free Wi-Fi and the corporate computer

C.

At home, using home internet and the corporate virtual private network

D.

Anywhere the team member would like, using a mobile device and mobile internet

Question 19

Which of the following best describes a rollback plan?

Options:

A.

Apply an alternative plan if the original plan does not work.

B.

Return to the operational state of a system before applying a requested change.

C.

Restart the project with new resources to avoid failures from previous ones.

D.

Repeat the tasks suggested in the requested change until they work.

Question 20

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

Options:

A.

Change the precedence of the tasks to " finish-to-start " .

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

Question 21

A member keeps bringing up unrelated topics during a team meeting. Which of the following should the protect manager do to keep the discussion on track?

Options:

A.

Remind the team member about the meeting agenda and invite the member to add the topic to the next meeting ' s agenda.

B.

Ask the team member to leave the meeting and create a new meeting to discuss these topics.

C.

Adjust the current meeting ' s agenda to accommodate the team member ' s topics.

D.

Allow the team member to bring up the topics, which could lead to important discussions and insights.

Question 22

A project team evaluates the potential risks to a project that uses legacy applications. Which of the following should be the main concern of the project team?

Options:

A.

Infrastructure end of life

B.

Company reorganization

C.

Digital transformation

D.

Major cybersecurity event

Question 23

A PM is working on the schedule for a project that has technical tasks and requires a SME ' s knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

Options:

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Question 24

A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?

Options:

A.

Scrum

B.

Extreme programming

C.

Waterfall

D.

Kanban

Question 25

Which of the following can a project manager infer from the following velocity chart?

as

Options:

A.

The project is on schedule.

B.

The project Is ahead of schedule.

C.

The project is behind schedule.

D.

The project is at risk.

Question 26

Which of the following is the focus of DevSecOps?

Options:

A.

Securing, testing, and maintaining new software

B.

Developing, testing, and maintaining software

C.

Developing, maintaining, and securing software

D.

Developing, securing, and testing software

Question 27

Which of the following activities would a project manager perform during the closing phase? (Select THREE).

Options:

A.

Lessons learned

B.

Risk analysis

C.

Removing resources

D.

Acquiring resources

E.

Statement of work sign-off

F.

Stakeholder analysis

G.

Removing access

Question 28

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

Options:

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Question 29

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

Options:

A.

Waterfall

B.

SDLC

C.

XP

D.

Scrum

Question 30

While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps should the project manager take next?

Options:

A.

Reassess the resource pool.

B.

Review the QA plan from a similar project.

C.

Check on available resources for additional team members.

D.

Escalate the issue to the project sponsor.

Question 31

A project manager is reviewing deliverables during the planning phase of a project to validate their completeness. Which of the following must be completed at this stage?

Options:

A.

Project objectives

B.

Access requirements

C.

Preliminary scope statement

D.

QA plan

Question 32

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Question 33

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

Options:

A.

Development

B.

Production

C.

Testing

D.

QA

Question 34

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

Options:

A.

Information disposal

B.

Information classification

C.

Information access administration

D.

Information backup

Question 35

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

Options:

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps

Question 36

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

Options:

A.

Shared folder

B.

Infrastructure

C.

Multitiered architecture

D.

Data warehouse

Question 37

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

Options:

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

Question 38

Which of the following requires the MOST availability from the business team?

Options:

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Question 39

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined.

B.

There is a non-disclosure agreement in place.

C.

There are multiple requirements for the product.

D.

The PM wants to simplify the logistics of the required product.

Question 40

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

Options:

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Question 41

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

Options:

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Question 42

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined

B.

There is a non-disclosure agreement in place

C.

There are multiple requirements for the product

D.

The PM wants to simplify the logistics of the required product

Question 43

A project manager is comparing the documentation attached to invoices from main vendors with the requirements described in the SOW in order to decide if all are correct. Which of the following best describes what is being performed?

Options:

A.

Approving deliverables

B.

Enforcing vendor rules of engagement

C.

Reporting overall process

D.

Scheduling team touch points

Question 44

Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?

Options:

A.

To develop a detailed project plan and timeline

B.

To enable a lessons learned session

C.

To identify and assess potential vendors for the project

D.

To ensure that all stakeholders have a shared understanding of the project ' s objectives

Question 45

A project manager is working on an existing, large, complex project that involves regulatory and environmental considerations. The development of a detailed project plan will be critical. Which of the following should the project manager do first?

Options:

A.

Review the project charter.

B.

Start the process of engaging the stakeholders.

C.

Arrange a kickoff meeting.

D.

Evaluate potential risks.

Question 46

A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?

Options:

A.

Project charter

B.

Requirements traceability matrix

C.

Project communications plan

D.

Project risk register

Question 47

The project manager must create a project charter. Which of the following should be included in the charter?

Options:

A.

Project schedule

B.

Resource allocation

C.

Risk plan

D.

Stakeholder identification

Question 48

Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

Options:

A.

Social

B.

Regulatory

C.

Environmental

D.

Governmental

Question 49

Which of the following offers administrators more direct control over operating systems?

Options:

A.

Infrastructure as a service

B.

Software as a service

C.

Functions as a service

D.

Platform as a service

Question 50

Which of the following BEST identifies the intent and purpose of a project closeout report?

Options:

A.

To provide documentation of lessons learned

B.

To document variances from the initial project baseline

C.

To validate that a project has been successfully completed

D.

To release resources and terminate all access rights

Question 51

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

as

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Question 52

A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?

Options:

A.

An issue

B.

A goal

C.

A backlog item

D.

An epic

Question 53

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

Options:

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Question 54

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Question 55

A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?

Options:

A.

Identify and assess stakeholders.

B.

Hold daily status meetings.

C.

Remove access and plan the project sign-off.

D.

Review assumptions and constraints for input to the risk register.

Question 56

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Question 57

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

Options:

A.

Exploit the risk.

B.

Accept the risk.

C.

Avoid the risk.

D.

Transfer the risk.

Question 58

Which of the following tasks should the project manager complete first when validating deliverables?

Options:

A.

Assess the documentation.

B.

Obtain stakeholder feedback.

C.

Review the project objectives.

D.

Mitigate risks.

Question 59

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

as

as

Select the new critical path.

Option A

Option B

Option C

as

Options:

Question 60

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

Options:

A.

PRINCE2

B.

Scrum

C.

SAFe

D.

XP

Question 61

Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).

Options:

A.

Real-time surveys/polling

B.

Wiki knowledge base

C.

Spreadsheets

D.

Meetings/face-to-face

E.

Real-time, multi-authoring editing software

F.

Charting/diagramming

Question 62

A team member identifies a critical issue in production. Which of the following should the project manager apply?

Options:

A.

Compliance check

B.

Release plan

C.

Rollback plan

D.

Validation check

Question 63

Which of the following best describes the meaning of timeboxing in the context of a project kickoff meeting?

Options:

A.

Allowing a discussion to proceed until a decision is made

B.

Allowing the meeting attendees more time for deeper conversation

C.

Allowing for a flexible timeline so all aspects of the project are covered

D.

Allowing a conversation to continue for a predefined period of time

Question 64

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

Options:

A.

Remove the team member ' s access.

B.

Release the project resources.

C.

Collect the stakeholders’ feedback.

D.

Have the closeout report approved.

Question 65

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Question 66

A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).

Options:

A.

Formal

B.

Internal

C.

Informal

D.

Verbal

E.

Indirect

F.

External

Question 67

A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

Options:

A.

Resource management system

B.

Issue log

C.

Ticketing system

D.

Backlog

Question 68

Which of the following best represents the project impact to a company ' s brand value?

Options:

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.The project meets the expected milestones and finishes on time and within budget.

Question 69

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

Options:

A.

Issue, issue

B.

Issue, risk

C.

Risk, issue

D.

Risk, risk

Question 70

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

Options:

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Question 71

Which of the following demonstrates awareness of regulations and standards when conducting a project?

Options:

A.

Establishing a measurement system for the team members ' performance

B.

Controlling project costs to fall within the company-approved variance

C.

Reviewing advertising trends in the market before launching a new product

D.

Submitting architectural plans for approval before commencing construction

Question 72

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

as

Which of the following is the current status of the process?

Options:

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.

Question 73

Which of the following PRINCE2 processes includes creating the project plan?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Managing product delivery

D.

Directing a project

Question 74

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?

Options:

A.

Monitoring the project team

B.

Creating a handoff process

C.

Colocating the project team

D.

Creating a separate statement of work

Question 75

As a result of an unpredicted risk, a project manager is documenting a request in the change control log. Which of the following change control processes should the project manager do last?

Options:

A.

Escalate to the change control board.

B.

Update the project plan.

C.

Test the implemented change request.

D.

Communicate the change deployment.

Question 76

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

Options:

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Question 77

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

Options:

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Question 78

A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

Options:

A.

Multiauthoring software

B.

Word processor

C.

Real-time polling

D.

Conferencing platforms

Question 79

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

Options:

A.

Escalate the finding to the change control board.

B.

Add a risk to the risk register for validation.

C.

Consult the RACI matrix to identify ownership of the risk.

D.

Have a meeting with the project sponsor and main stakeholders.

Question 80

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

Options:

A.

Defect log

B.

Change log

C.

Issue log

D.

Risk log

Question 81

Which of the following best represents an intellectual property breach?

Options:

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.

Question 82

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

Options:

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Question 83

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?

Options:

A.

Obtain details from the owner of the project.

B.

Update the critical path for the project.

C.

Apply contingency reserves.

D.

Reestimate epic user stories.

Question 84

A project manager makes a list of the smallest activity components in the project. Which of the following is the project manager building?

Options:

A.

Milestone chart

B.

Task board

C.

Work breakdown structure

D.

Detailed project plan

Question 85

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager ' s objective for the vendor meeting?

Options:

A.

Reassigning resources

B.

Removing access

C.

Closing contracts

D.

Evaluating the project

Question 86

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

Options:

A.

Bringing attention to the project sponsor

B.

Sharing lessons learned

C.

Collecting feedback

D.

Celebrating the team ' s hard work

Question 87

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RFI

D.

RFP

Question 88

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens ' complaints. Which of the following solutions would be BEST?

Options:

A.

Enterprise resource planning and end user applications

B.

Electronic document and record management systems

C.

Customer relationship management and databases

D.

Content management and financial systems

Question 89

Which of the following is a characteristic that defines a project?

Options:

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

Question 90

A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?

Options:

A.

Execute the contingency plan

B.

Perform a work-around

C.

Escalate to senior management

D.

Assign a risk owner

Question 91

During project initiation, a project manager needs to establish the communication channel that will be used to deliver weekly presentations to stakeholders who are across the country. Which of the following would be the best communication channel to use?

Options:

A.

In-person meetings

B.

Email

C.

Telephone

D.

Videoconference

Question 92

A software development team completed the development and testing of a new accounting software system for a client. Which of the following should the team do next?

Options:

A.

User acceptance testing

B.

Unit testing

C.

Performance testing

D.

Audits and inspections

Question 93

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

Options:

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Question 94

Which of the following is the most important activity for the project manager during the closure of a project?

Options:

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Question 95

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

Options:

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Question 96

Which of the following best explains why companies apply background screening during the employment process?

Options:

A.

To increase access restrictions

B.

To define KPIs for new employees

C.

To evaluate PHI

D.

To apply operational security

Question 97

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

as

C)

as

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Question 98

An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

Options:

A.

The ticket system provided access by default without any approval.

B.

The project manager did not perform proper project planning.

C.

The system is lacking proper access controls.

D.

Sensitive data was incorrectly classified during the audit process.

Question 99

The sales department accidentally has access to all project files, including employee personal information. Which of the following security concepts is this violating?

Options:

A.

Need-to-know

B.

Intellectual property

C.

Multifactor authentication

D.

Facility access

Question 100

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

as

Which of the following most likely represents the number of items in the backlog?

Options:

A.

23

B.

5

C.

10

D.

15

Question 101

A company is designing a new ERP system. The SOW includes modules for different departments. During a meeting, a stakeholder requests an additional feature. Which of the following action should the project manager take next?

Options:

A.

Document the change request in the change log.

B.

Communicate the change request to stakeholders.

C.

Determine the decision makers for the change request.

D.

Validate the change request.

Question 102

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

Options:

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Question 103

A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?

Options:

A.

Use a software tool during the meeting that can create a transcript of what is discussed.

B.

Have a standing agenda that is vague enough so that it can be used again.

C.

Delegate the roles and responsibilities to improve meeting management.

D.

Reprimand project team members for not completing assigned action items.

Question 104

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

Options:

A.

Start-to-start

B.

Start-to-finish

C.

Finish-to-finish

D.

Finish-to-start

Question 105

During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?

Options:

A.

Issue log

B.

Defect log

C.

Risk register

D.

Change log

Question 106

A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?

Options:

A.

The project is ahead of schedule and under budget.

B.

The project is behind schedule and over budget

C.

The project is ahead of schedule and over budget.

D.

The project is behind schedule and under budget

Question 107

Which of the following best describes a benefit of the CI/CD process?

Options:

A.

Software delivery is sped up without compromising quality.

B.

Incremental changes are done at the end of the project.

C.

The software is integrated with other projects easily.

D.

Updates are released every sprint.

Question 108

Which of the following is the best example of CapEx?

Options:

A.

Taxes

B.

Vehicles

C.

Salaries

D.

Utilities

Question 109

A project team is determining how an application will be moved to production, who the users will be, and what training is needed. Which of the following best describes what is being developed?

Options:

A.

Contingency plan

B.

Scope statement

C.

Transition plan

D.

Communication plan

Question 110

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

Options:

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Question 111

Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

Options:

A.

Telephone

B.

Videoconference

C.

Face-to-face

D.

Email

Question 112

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options:

A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

Question 113

Given the information in the chart,

as

which of the following techniques should the project manager use to improve the project schedule in Sprint 1?

Options:

A.

Validating

B.

Crashing

C.

Training

D.

Avoiding

Question 114

During the project initiation phase, a project manager needs to assign individual roles and responsibilities to various team members. Which of the following would best enable them to do so?

Options:

A.

ERP

B.

RAM

C.

JAR

D.

CCB

Question 115

A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:

Options:

A.

the preferred sponsor ' s communication channel.

B.

the preferred project manager ' s communication channel.

C.

the preferred reported communication channel.

D.

email communication as the preferred communication channel.

Question 116

Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

Options:

A.

Assign action items to attendees.

B.

Distribute an agenda.

C.

Email the minutes from the previous meeting.

D.

Schedule a convenient time.

Question 117

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

Options:

A.

Gantt chart

B.

Maintenance window schedule

C.

Functional requirements

D.

Test results

Question 118

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

Options:

A.

Some work packages are missing from the WBS.

B.

Information is missing from the RACI matrix.

C.

New knowledge bases were introduced.

D.

Team touch points are missing.

Question 119

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

Options:

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Question 120

Which of the following is a potential challenge that may arise from language barriers among a project team?

Options:

A.

A project team is unable to communicate effectively due to a lack of common technical terminology and jargon.

B.

A project team refuses to learn foreign languages to cater to remote colleagues.

C.

A project team cannot use communication tools due to a lack of IT knowledge.

D.

A project team member located in a different time zone fails to access project resources.

Question 121

A PM is working with the development team and stakeholders to determine how to relate first name, last name, and address in a database. Which of the following identifies these types of data elements?

Options:

A.

PCI

B.

PII

C.

PHI

D.

CMS

Question 122

A project manager is unclear about the budget and timeline prior to the start of a project. Which of the following best describes what type of meeting needs to take place?

Options:

A.

Kickoff

B.

Demo

C.

Stand-up

D.

Status call

Question 123

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

Options:

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.

B.

Require everyone to turn on their cameras and use the same background filter.

C.

Encourage the use of the chat and use plain language when speaking.

D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.

Question 124

Which of the following are primary features provided by a standard laaS solution? (Select two).

Options:

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

Question 125

A project manager is concerned about the performance of a developer who is struggling with the new coding language. Which of the following actions should the project manager take?

Options:

A.

Send a request to the project sponsor to add an additional developer.

B.

Provide the developer with only non-critical tasks.

C.

Assign the developer training to improve the developer ' s skills.

D.

Remove the developer from the project team.

Question 126

A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?

Options:

A.

Too much time might be spent generating project delays.

B.

The project manager might be seen as weak.

C.

The number of change requests throughout the project might be reduced.

D.

Some stakeholders might not be completely satisfied.

Question 127

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

Options:

A.

SLA

B.

TOR

C.

SOW

D.

NDA

Question 128

A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

Options:

A.

List both positively and negatively impacted stakeholders.

B.

Update the communication plan with the new findings.

C.

List the negatively impacted stakeholders only.

D.

List the positively impacted stakeholders only.

Question 129

Which of the following is a quantitative key performance indicator?

Options:

A.

The project sponsor ranked the graphics of an application as four out of five.

B.

The project implements the application in ten different geographical regions.

C.

The workers complete tasks on average 25% faster using a new application.

D.

The use of a multimedia interface appeals more to users under the age of 21.

Question 130

Which of the following is the best alternative to allow multiple users to edit a project plan in real time?

Options:

A.

Send the file through email as an attachment

B.

Share access to the file on a wiki knowledge base.

C.

Access the file through an online application.

D.

Schedule an in-person meeting to review the plan

Question 131

The PMO wants to streamline the routing and approval of project activities to provide up-to-date visibility of the status. Which of the following collaboration tools would be most appropriate to use?

Options:

A.

Real-time, multi-authoring tool

B.

Wiki knowledge base and search engine

C.

Workflow and e-signature platform

D.

File-sharing platform and storage system

Question 132

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

Options:

A.

Reviewing project blockers

B.

Defining roles and responsibilities

C.

Establishing a project schedule

D.

Determining a project budget

Question 133

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

Options:

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Question 134

Which of the following should be considered first when determining the privacy management for project data?

Options:

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Question 135

A company is starting a new implementation project The stakeholders are reviewing RFP responses to help make a decision about which project management consulting firm to hire. Given the following information:

as

Which of the following is the best consulting firm for the company to hire?

Options:

A.

Consulting firm 1

B.

Consulting firm 2

C.

Consulting firm 3

D.

Consulting firm 4

Question 136

A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

Options:

A.

Consult with the legal department.

B.

Update the issue log.

C.

Start a new RFP immediately.

D.

Perform a PERT analysis.

Question 137

During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?

Options:

A.

Gantt chart

B.

Milestone chart

C.

Velocity chart

D.

PERT chart

Question 138

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Options:

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Page: 1 / 46
Total 460 questions