New Year Sale Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

Construction Specifications Institute CDT Dumps

Page: 1 / 12
Total 120 questions

Construction Documents Technologist Questions and Answers

Question 1

In the AIA A201 General Conditions of the Contract for Construction, whom is responsible for property insurance for a project?

Options:

A.

Surety, on contractor's behalf.

B.

Owner, unless assigned to contractor.

C.

Owner and contractor, jointly.

D.

Contractor, unless assigned to owner.

Question 2

What can value analysis be used for?

Options:

A.

To provide the owner with the lowest construction cost.

B.

To enhance project value or reduce initial or long-term cost.

C.

A phase for future work to allow higher quality items up front.

D.

To change the perceived value by owner and stakeholder.

Question 3

What is a fundamental principle required to provide fairness in a competitive bidding process?

Options:

A.

Bid securities provide protection to all bidders for unfair practices of others.

B.

The bid shopping process provides the most beneficial pricing to the owner.

C.

All bids are prepared based on identical conditions, information, and time constraints.

D.

A minimum of three bids are required to assure sufficient competition.

Question 4

The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?

Options:

A.

Sheet index

B.

Cover sheet

C.

General notes

D.

Building code summary

Question 5

When developing an operation and maintenance (O&M) budget for a facility, what should form the basis for budget decisions?

Options:

A.

The architect/engineer’s projected operating costs

B.

The construction manager’s life cycle analysis

C.

The estimator’s preliminary project description

D.

The facility manager’s historical record of actual costs

Question 6

Which documents are commonly included as procurement documents?

Options:

A.

Project record documents

B.

Contract documents

C.

Consensus documents

D.

Bidding documents

Question 7

When is the owner entitled to stop the work?

Options:

A.

If the architect/engineer fails to represent owner properly

B.

If the contractor fails to correct work that is not compliant with the contract documents

C.

If the contractor is presumed to be bankrupt

D.

If there is a safety problem on the site

Question 8

During procurement activities, what is the process of notifying prospective or qualified bidders requesting proposals for a specific project or issuing an invitation to bid?

Options:

A.

Solicitation

B.

Instructions for Procurement

C.

Instructions to Bidders

D.

Request for Scope of Work

Question 9

Under the design-bid-build project delivery, what is the next step after the procurement phase has ended to award the contract for construction?

Options:

A.

The contractor begins negotiating agreements with subcontractors.

B.

The owner forwards construction contract agreements to subcontractors.

C.

The contractor and owner issue an amendment indicating the project is in the construction phase.

D.

The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.

Question 10

What could a reference standard specification be based upon?

Options:

A.

Project manual for similar project

B.

Design intent

C.

Trade association standard

D.

Manufacturer's specification section

Question 11

During the bid period, what does the architect issue if it is necessary to modify the procurement documents?

Options:

A.

Addenda

B.

Construction change directives

C.

Change order

D.

RFI response

Question 12

What is Leadership in Energy and Environmental Design® (LEED®)?

Options:

A.

A set of sustainable standards with measurable recognized categories for a project

B.

A formula for determining a sustainable classification

C.

A system of prioritizing sustainable projects

D.

Standardized structure for organizing sustainable information

Question 13

During the schematic design phase, a contingency line item in the estimate would be included to cover which of the following?

Options:

A.

Allowances

B.

Unit prices

C.

Unknown factors

D.

Alternates

Question 14

Cost classification, data organization, and specifications use which written formats?

Options:

A.

OmniClass and UniFormat

B.

UniFormat and MasterFormat

C.

OmniClass and MasterFormat

D.

SectionFormat® and MasterFormat

Question 15

Which of the following participants is involved in the Integrated Project Delivery (IPD) method?

Options:

A.

Authority having jurisdiction

B.

Commissioning agent

C.

Contractor

D.

Inspector

Question 16

When preparing their bid, a contractor organizes their costs into different categories. The following items are examples of which type of cost?

    Permits and inspections

    Mobilization and startup

    Jobsite safety and security procedures, including personnel

    Administrative costs attributable to the work

Options:

A.

Construction

B.

Contingency

C.

Overhead

D.

Insurance

Question 17

A facility manager needs to replace a broken insulated glazing unit in an existing facility. Which source would be most appropriate for determining where and how to order the new unit?

Options:

A.

Record drawings

B.

Manufacturer's representative

C.

Project manual

D.

Record submittals

Question 18

There are over 3,500 different grades of steel. The amount of carbon, level of impurities, and additional elements all contribute to what grade steel is classified as in building projects. Therefore, which of the following is the method of specification writing used to limit lengthy descriptions of materials?

Options:

A.

American National Standards Institute (ANSI)

B.

Descriptive

C.

Performance

D.

Reference standard

Question 19

An architect/engineer wants to schedule monthly meetings with a contractor and owner to discuss matters pertinent to timely and successful completion of the work. Which type of meeting should they schedule?

Options:

A.

Workflow meeting

B.

Preinstallation meeting

C.

Progress meeting

D.

Schedule monitoring meeting

Question 20

How do private bidding practices compare or contrast with public bidding practices?

Options:

A.

A private owner may waive any informality in the bidding, except for the performance bond.

B.

Private bids may be opened in private, but the results must be published in a reasonable time.

C.

The laws and regulations for private bidding are the same as for public bidding.

D.

The private owner may award a contract to a responsive and responsible bidder other than the lowest.

Question 21

In what project stage does the architect/engineer obtain and document the owner's decisions about specific products and systems?

Options:

A.

Construction documentation

B.

Design

C.

Project conception

D.

Programming

Question 22

A drawing set arranged in the following order is an example of what type of drawing organization?

Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection

Options:

A.

Traditional drawing set organization

B.

Uniform Drawing System

C.

AIA CAD Layer Guidelines

D.

BIM Implementation

Question 23

In the MasterFormat® specification system, which subgroup contains requirements of MEP, fire protection, and telecom systems?

Options:

A.

Site and Infrastructure Subgroup (Divisions 30–39)

B.

Facility Services Subgroup (Divisions 20–29)

C.

Facility Construction Subgroup (Divisions 02–19)

D.

Part 2 – Products

Question 24

Which team member is actively involved and interested in all phases of the project?

Options:

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

Question 25

What is the compositional format for standardizing the presentation of specification information on a printed page in a way that is meant to be easy to read and quick to navigate?

Options:

A.

UniFormat®

B.

PPDFormat®

C.

PageFormat®

D.

SectionFormat®

Question 26

What is MasterFormat® keyword index used for?

Options:

A.

Identifying Level 4 sections

B.

Identifying specification format

C.

Locating subject titles and numbers

D.

Specifying correct word usage

Question 27

What does Divisions 02-49 of the construction project manual address?

Options:

A.

Procurement instructions

B.

Distinct work results areas

C.

Temporary facilities and controls

D.

Life cycle activities

Question 28

Which of these is NOT a graphical format used to establish order and organization of construction drawings?

Options:

A.

United States National CAD Standard

B.

American Institute of Architects (AIA) CAD Layer Guidelines

C.

Construction Specifications Institute (CSI) Uniform Drawing System

D.

MasterFormat®

Question 29

Procedural requirements for alternates, project meetings, and submittals belong where?

Options:

A.

Divisions 02-49

B.

The general conditions

C.

The supplementary conditions

D.

Division 01

Question 30

What does the Integrated Project Delivery (IPD) process involve?

Options:

A.

A collaborative, integrated, and productive team composed of key project participants

B.

Traditional delivery methods and team relationships for improving project performance by understanding the qualifications and attributes of team members

C.

Responsibility silos for greater efficiencies, leading to project success

D.

Segregat knowledge gathered as needed with paper-based communications to team members

Question 31

Which of the following is an example of preconstruction submittals?

Options:

A.

Product data

B.

Shop drawings

C.

Schedule of values

D.

Warranty documentations

Question 32

In construction documents, what does the agreement refer to?

Options:

A.

The agreement between the owner and the architect/engineer

B.

The general conditions of the contract for construction

C.

The agreement between the owner and the contractor

D.

The agreement between the contractor and the subcontractor

Question 33

Where are the limits of the work of each alternate defined?

Options:

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02–49

Question 34

During design, in a design-build delivery method, what is the design-builder responsible for delivering to the owner?

Options:

A.

Submittals

B.

Record documents

C.

Geotechnical reports

D.

Construction documents

Question 35

Which party has the ultimate authority to approve a change order?

Options:

A.

Architect/engineer

B.

Contractor

C.

Owner

D.

Construction manager

Question 36

What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?

Options:

A.

Building code

B.

Quality control standard

C.

Reference standard

D.

Specification master

Page: 1 / 12
Total 120 questions