Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dumps65

Construction Specifications Institute CDT Dumps

Page: 1 / 12
Total 120 questions

Construction Documents Technologist Questions and Answers

Question 1

Under SectionFormat®, where would the Article "Manufacturers" be found?

Options:

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Question 2

Which of the following statements best describes stakeholder and participant interest in a project?

Options:

A.

Participants have direct interest in the project while stakeholders have indirect interest

B.

Stakeholders have direct interest in the project while participants have indirect interest

C.

Both stakeholders and participants have direct interest in the project

D.

Both stakeholders and participants have indirect interest in the project

Question 3

What is a primary disadvantage in using the design-bid-build method?

Options:

A.

It attracts too many bidders

B.

All of the bids may exceed the owner's budget

C.

It requires a higher level of bid document quality

D.

It reduces the owner's control over the project during the construction phase

Question 4

Which member of the project team initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding?

Options:

A.

Contractor

B.

Designer

C.

Supplier

D.

Owner

Question 5

When does a project reach substantial completion?

Options:

A.

When the project is sufficiently complete to allow its intended use

B.

When the project receives final inspections from the authorities having jurisdiction

C.

When the contractor's final application for payment is approved

D.

When all of the close-out documents have been reviewed and approved

Question 6

What does the Integrated Project Delivery (IPD) process involve?

Options:

A.

A collaborative, integrated, and productive team composed of key project participants

B.

Traditional delivery methods and team relationships for improving project performance by understanding the qualifications and attributes of team members

C.

Responsibility silos for greater efficiencies, leading to project success

D.

Segregated knowledge gathered as needed with paper-based communications to team members

Question 7

There are over 3,500 different grades of steel. The amount of carbon, level of impurities, and additional elements all contribute to what grade steel is classified as in building projects. Therefore, which of the following is the method of specification writing used to limit lengthy descriptions of materials?

Options:

A.

American National Standards Institute (ANSI)

B.

Descriptive

C.

Performance

D.

Reference standard

Question 8

The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?

Options:

A.

Cash allowance

B.

Quantity allowance

C.

Unit pricing

D.

Alternates

Question 9

What governs Division 01 specifications and general requirements?

Options:

A.

Part I general

B.

Divisions 02-49

C.

The general conditions of the construction contract

D.

The construction drawings

Question 10

Which of the following is a component of the contract documents?

Options:

A.

Procurement requirements

B.

Resource drawings

C.

Shop drawings

D.

Addenda

Question 11

Which party has the ultimate authority to approve a change order?

Options:

A.

Architect/engineer

B.

Contractor

C.

Owner

D.

Construction manager

Question 12

What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?

Options:

A.

Stipulated sum

B.

Unit price

C.

Cost-plus-fee

D.

Cost-plus-fee with guaranteed maximum price

Question 13

In construction documents, what does the agreement refer to?

Options:

A.

The agreement between the owner and the architect/engineer

B.

The general conditions of the contract for construction

C.

The agreement between the owner and the contractor

D.

The agreement between the contractor and the subcontractor

Question 14

What four considerations are included in site selection programming?

Options:

A.

Use, space, funds, date

B.

Function, form, economy, time

C.

Purpose, shape, cost, schedule

D.

Goal, condition, budget, calendar

Question 15

A facility manager needs to replace a broken insulated glazing unit in an existing facility. Which source would be most appropriate for determining where and how to order the new unit?

Options:

A.

Record drawings

B.

Manufacturer's representative

C.

Project manual

D.

Record submittals

Question 16

A drawing set arranged in the following order is an example of what type of drawing organization?

Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection

Options:

A.

Traditional drawing set organization

B.

Uniform Drawing System

C.

AIA CAD Layer Guidelines

D.

BIM Implementation

Question 17

Who is responsible for accepting and inspecting for damage of the owner-furnished products delivered to the project site?

Options:

A.

Contractor

B.

Installer

C.

Owner

D.

Subcontractor

Question 18

Who has the right to stop the work if hazardous materials are encountered during the construction?

Options:

A.

Architect/engineer

B.

Contractor

C.

Stakeholders

D.

Facility manager

Question 19

Standards for sustainable facilities, products, and fundamental approaches emphasize the needs of what?

Options:

A.

Architect, supplier, and contractor

B.

Owner, stakeholders, and participants

C.

Public, private, and environmental health

D.

Owner team, contractor team, and design team

Question 20

What is the primary purpose of MasterFormat®?

Options:

A.

To create a master list of Level 3 and Level 4 section titles

B.

To organize cost estimates by major project element

C.

To establish an order of information within specification sections

D.

To provide a uniform system for the organization of information in project manuals

Question 21

Which project phase would outline specifications be created in order to be used as a checklist for further development of the project documents?

Options:

A.

Project Conception phase

B.

Schematic Design phase

C.

Design Development phase

D.

Construction Document phase

Question 22

When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?

Options:

A.

The architect/engineer/owner team can consider bid listing and bid depository provisions.

B.

Require bidders to provide a list of their intended subcontractors along with their bid.

C.

The subcontractor can withhold their prices from the bidder until the final moments before the deadline.

D.

The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.

Question 23

When is the owner entitled to stop the work?

Options:

A.

If the architect/engineer fails to represent owner properly

B.

If the contractor fails to correct work that is not compliant with the contract documents

C.

If the contractor is presumed to be bankrupt

D.

If there is a safety problem on the site

Question 24

What is Leadership in Energy and Environmental Design® (LEED®)?

Options:

A.

A set of sustainable standards with measurable recognized categories for a project

B.

A formula for determining a sustainable classification

C.

A system of prioritizing sustainable projects

D.

Standardized structure for organizing sustainable information

Question 25

Cost classification, data organization, and specifications use which written formats?

Options:

A.

OmniClass and UniFormat

B.

UniFormat and MasterFormat

C.

OmniClass and MasterFormat

D.

SectionFormat® and MasterFormat

Question 26

Which of the following is LEAST important to log when documenting the decision-making process?

Options:

A.

Date, time, and location of the meeting

B.

List of attendees and who they represent

C.

Length of time each attendee spent speaking

D.

Action items with responsibilities assigned and date to accomplish

Question 27

During procurement activities, what is the process of notifying prospective or qualified bidders requesting proposals for a specific project or an invitation to bid?

Options:

A.

Solicitation

B.

Instruction for procurement

C.

Instruction to bidders

D.

Request for scope of work

Question 28

The names of the project, owner, architect/engineer and consultants, and the general project data such as location map are normally included in which of the following?

Options:

A.

Sheet index

B.

Cover sheet

C.

General notes

D.

Building code summary

Question 29

In the AIA A201 General Conditions of the Contract of Construction, whom is responsible for property insurance for a project?

Options:

A.

Surety, on contractor's behalf.

B.

Owner, unless assigned to contractor.

C.

Owner and contractor, jointly.

D.

Contractor, unless assigned to owner.

Question 30

According to standard general conditions, which of the following is true about shop drawings?

Options:

A.

They are contract documents.

B.

They illustrate some portion of the work.

C.

They are reviewed only by the architect/engineer.

D.

They include performance charts, instructions, and brochures.

Question 31

Which of these is NOT a graphical format used to establish order and organization of construction drawings?

Options:

A.

United States National CAD Standard

B.

American Institute of Architects (AIA) CAD Layer Guidelines

C.

Construction Specifications Institute (CSI) Uniform Drawing System

D.

MasterFormat®

Question 32

Where can you typically find requirements for temporary toilet facilities?

Options:

A.

Supplementary General Conditions

B.

Division 22 – Plumbing

C.

The Owner–Contractor Agreement

D.

Division 01 – General Requirements

Question 33

Which team member is actively involved and interested in all phases of the project?

Options:

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

Question 34

When innovative or unusual design techniques are proposed, it is advised to have what type of review?

Options:

A.

Sustainability

B.

Budget

C.

Constructability

D.

Design

Question 35

Why should project closeout meetings be held?

Options:

A.

To set substantial completion

B.

To resolve subcontractor disputes

C.

To commission the project for occupancy

D.

To review handover procedures and activities

Question 36

What can value analysis be used for?

Options:

A.

To provide the owner with the lowest construction cost.

B.

To enhance project value or reduce initial or long-term cost.

C.

A phase for future work to allow higher quality items up front.

D.

To change the perceived value by owner and stakeholder.

Page: 1 / 12
Total 120 questions