Pre-Summer Sale Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

FIDIC CCM Dumps

Page: 1 / 14
Total 140 questions

Certified Contract Manager Questions and Answers

Question 1

(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)

Options:

A.

The Employer and the Contractor have identified an issue and disagreement, and have agreed between themselves that they want the DAAB to provide assistance and/or informally discuss and attempt to resolve that issue/disagreement.

B.

The Engineer has made a non-objection letter, in which it is stated that the issue/disagreement does not concern the matter that is being dealt with by the Engineer.

C.

The Employer and the Contractor have made a " joint request " in writing before the DAAB gives the requested assistance.

D.

Both Parties should be present at the meeting in which the DAAB provides assistance.

Question 2

Under the FIDIC Red Book, which one of the following statements is correct for a claim by the Contractor?

Options:

A.

The Employer has the authority to accept a claim by the Contractor, even in the case of the Contractor ' s failure to comply with the notice requirements.

B.

If the Engineer does not make a determination, the Employer and the Contractor are unable to agree to settle an issue that gave rise to a claim.

C.

The Engineer ' s response to the Contractor ' s submission of detailed particulars that are required by the procedure for claims by the Contractor must include the Engineer ' s final decision on the quantum.

D.

It is the Employer ' s Representative who must first respond to the claim by the Contractor.

E.

The Engineer ' s response to a claim by the Contractor is final and binding upon the Employer.

Question 3

The amount of an advance payment guarantee provided for pursuant to FIDIC Red and Yellow Books (both editions) may be reduced as of:

Options:

A.

The Commencement Date

B.

The date of the Taking Over Certificate

C.

The date on which the entire advance payment is repaid as stated in the Payment Certificate

D.

The date on which an amount is repaid by the Contractor as stated in the Payment Certificates

Question 4

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.

Options:

A.

True

B.

False

Question 5

(You are the Contract Manager of the Employer ' s Representative for a project using FIDIC Silver Book (edition 1999). The Contract Agreement does not define the Commencement Date. The Contract has been legally effective for 4 weeks. You are writing a letter urging the Employer to issue a Notice of Commencement Date. Why is this important? (2 correct answers apply))

Options:

A.

If no notified Commencement Date were more than 8 weeks since the Contract became legally effective, the Contractor will be entitled to financial compensation.

B.

The Employer’s failure to notify the Commencement Date within 6 weeks after the date on which the Contract comes into full force and effect would constitute a breach of the Contract.

C.

If no notified Commencement Date were more than 8 weeks since the Contract was legally effective, the Contractor will be entitled to extension of time.

D.

The Contractor shall be entitled to give notice of termination if the Contractor does not receive a Notice of Commencement Date within 12 weeks after both Parties signed the Contract Agreement.

Question 6

Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?

Options:

A.

True

B.

False

Question 7

(Sub-Clause 12.3(a) of FIDIC Red Book (edition 1999) specifies four criteria which are applicable without reference to Clause 13. A new rate shall only be appropriate if all four criteria are satisfied. Is this statement true or false?)

Options:

A.

True

B.

False

Question 8

Before applying the procurement process of any FIDIC Book, the Employer should always check if there are local procurement rules that also apply. Which one of these responses is correct?

Options:

A.

No, because the FIDIC procurement process is universal.

B.

No, because Employers never have specific procurement rules.

C.

Yes, based on the law system, internal governance or type of Employer additional procurement rules can apply.

D.

Yes, but this is only applicable for public entities like governments. If the Employer is a private organisation (like a company), they are free to procure how they want.

Question 9

Under the FIDIC Red Book (edition 1999), as part of the Contractor submission of Statement, any amount to be deducted for retention, will be calculated by applying the percentage of retention stated in the Appendix to Tender to the total of: (two correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The estimated contract value of the Works executed.

B.

Any amounts to be added and/or deducted for the advance payment and repayments under Sub-Clause 14.2.

C.

Any amounts to be added and deducted for changes in legislation and changes in cost.

D.

Any amounts to be added and deducted for Plant and Materials in accordance with Sub-Clause 14.5.

Question 10

Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer ' s prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer ' s prior approval or not. Is this statement true or false?

Options:

A.

True

B.

False

Question 11

Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer ' s Requirements. Which statement is correct?

Options:

A.

Scrutinising in FIDIC Yellow Book 1999 and Silver Book 1999 means that the Contractor must ask the Employer to check the Employer ' s Requirements very well to see if the Works can be built on that location according to the Employer ' s Requirements.

B.

Scrutinising in FIDIC Silver Book 1999 means that the Contractor should read the Employer ' s Requirements very thoroughly after the contract closes and see if the Employer ' s Requirements is complete or if something is missing.

C.

Scrutinising in FIDIC Yellow Book 1999 means the same as in FIDIC Silver Book 1999. In both models it means that after the contract closes and before starting the actual making of the design, the Contractor has to read the Employer ' s Requirements very thoroughly and check on any errors, omissions or conflicts.

D.

Scrutinising in FIDIC Yellow Book 1999 means that the Contractor has the opportunity after contract close to report on any errors, mistakes or conflicts in the Employer ' s Requirements. In the FIDIC Silver Book 1999 scrutinising provides that obligation during the tender period; Contractor has the opportunity to report on any errors, mistakes or conflicts in the Employer ' s Requirements and for Employer to change it; for after contract cl

Question 12

(Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)? Choose all correct answers.)

Options:

A.

If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.

B.

The dayworks related Sub-Clause is also applicable to other types of works.

C.

The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.

D.

The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that a Variation shall be executed on a daywork basis.

Question 13

In a construction project using the FIDIC Silver Book (edition 1999), if the Parties prefer the dispute board to be appointed on an " ad-hoc " basis instead of as a standing Dispute Avoidance and Adjudication Board (DAAB), what is it called? (1 correct answer applies)

Options:

A.

Ad-hoc DAAB

B.

DAB

C.

Ad-hoc DB

D.

Ad-hoc arbitration

Question 14

What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Notice is a defined term, while other communications are not defined as a term in the General Conditions.

B.

Contractually there is no difference between a notice and other communications.

C.

Both ' Notice ' and ' Other Communications ' are defined terms under the Conditions of Contract.

D.

The Parties and Engineer shall be given original or copy of any Notice, Notice of Dissatisfaction (NOD) and Certificates, which is not always the case for other communications.

Question 15

(Under FIDIC Red Book (edition 1999) a notice may be delivered to which two addresses?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The address stated in the Contract Data.

B.

The address provided for by the recipient of the notice.

C.

The address of the Site.

D.

The address of the Contractor ' s Representative.

Question 16

Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?

Choose all of the correct answers (multiple possibilities)

Options:

A.

The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.

B.

The Engineer cannot sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.

C.

The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor ' s items on the Site.

D.

The Employer cannot reinstate and clear the Site and dispose the remaining Contractor ' s items on the Site if the Contractor fails, as this is the Contractor ' s obligation.

Question 17

Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?

Choose all of the correct answers (multiple possibilities)

Options:

A.

All internationally recognized holiday periods.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

Only the delivery dates of Plant and Materials which have not been delivered on Site yet.

Question 18

Which of the following statements are relevant to continuing effect claims? [FIDIC 2017 Edition]

(2 correct answers apply)

Options:

A.

Continuing effect claims shall be noticed in the same way as " normal " claims, within 28 days after the Claiming Party became aware of the event or circumstance.

B.

In case the Employer is the Claiming Party, then he/she is not obliged to submit interim claims.

C.

In case the Contractor is the Claiming Party, when he/she misses to submit even just a single interim claim, then his/her entitlement is lost.

D.

In general, a fully detailed Claim has to be submitted within 84 days after becoming aware of the event giving rise to the claim.

Question 19

(Under the FIDIC Red Book, which of the following statements are correct? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).)

Options:

A.

An attempt to reach an amicable settlement is a mandatory requirement before an Engineer ' s ruling can be referred to a DAAB.

B.

A decision by a DAAB is not final and binding on the Parties until it is confirmed by an arbitration award.

C.

The FIDIC Red Book ' s General Conditions specify a standing DAAB.

D.

A DAAB member nominated by one of the Parties must be agreed by the other Party.

E.

If the Employer or the Contractor fails to notify its dissatisfaction with an Engineer ' s ruling within the specified time, the DAAB ' s decision is final and binding.

Question 20

If the Engineer is required to obtain the Employer ' s prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Remain silent and not do anything in the subject.

B.

The Engineer should refer the matter in subject to the DAB.

C.

Issuing the determination to the Contractor in the form and with the content agreeable to the Employer, with a remark, that it is the Employer ' s determination and not the Engineer ' s determination.

D.

Informing the Contractor of their inability of issuing the determination, in lack of the Employer ' s necessary approval.

Question 21

Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?

Options:

A.

A description of the varied work.

B.

A description of the proposed design.

C.

Details of the resources and methods to be adopted by the Contractor.

D.

A Programme for execution of the varied work.

Question 22

(Which two answers show characteristics of Test on Completion or Test After Completion under the FIDIC Silver Book (edition 1999)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

In case of failure of the Test on Completion, the Employer may accept the Works, thereby reducing the Contract Price.

B.

The Employer can either opt for Tests on Completion or Tests after Completion, but not both.

C.

Tests after Completion are carried out by the Employer.

D.

Although Tests after Completion fail, it may be considered as passed when performance damages specified in the contract are paid by the Contractor.

Question 23

(Which two of the following items are new features introduced in FIDIC Red and Yellow Books (edition 2017) in respect to the procedures relating to the Programme?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The requirement to submit a revised programme by the Contractor whenever the previous programme is inconsistent with actual progress.

B.

Specifying the programming software that shall be used by the Contractor in preparation of the Programme.

C.

The requirement that any revised programmes to be submitted by the Contractor is to reflect accurately the actual progress of the works.

D.

Submission by the Contractor of a detailed time Programme to the Engineer within 28 days after receiving the notice under Sub-Clause 8.1.

Question 24

You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?

Options:

A.

The Contractor submits a Value Engineering proposal, in which it proposed to change the colour of the outdoor paint. The Engineer approved the proposal.

B.

The Engineer instructs a change in slopes of stairs to the parking lot with an Instruction in accordance with Sub-Clause 3.3.

C.

The Engineer requests a proposal regarding a change in type of windows and doors of the business centre.

D.

The Employer verbally instructs a change in the layout of the rooftop restaurant. The Engineer issued an Instruction describing the required change with revised design drawings.

Question 25

(Under the FIDIC Red, Yellow, and Silver Books (edition 1999), which of the following entitlements of the Employer can result in a deduction of the Contract Price and Payment Certificates subject to Sub-Clause 2.5? (2 correct answers apply))

Options:

A.

Paying the Nominated Subcontractor directly.

B.

Compensation for the costs of the initial review of the Contractor ' s Documents.

C.

Delay Damages.

D.

Cost of using the Employer ' s materials.

Question 26

During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers on the excavator shouts out to the supervisor of the Contractor it has discovered something on the Site. The supervisor inspects the finding and concludes this is possibly an ancient treasure in a wooden box. The supervisor sees some golden coins through the cracked lid of the box. The supervisor immediately stops the execution of the Works, sends the workers away and blocks access to the Site for all persons. Given the sensitive nature of the findings, the supervisor informs you as Engineer. How do you react?

Options:

A.

You compliment the supervisor for their swift and decisive action. However, the Works should advance as soon as possible. You ask the supervisor to excavate the box further, and place it in the back of your truck. You promise the supervisor you will drive the box yourself to the University in the city nearby, because it is very important to preserve found treasures like this. The Contractor is not entitled to an extension of time, as no del

B.

You thank the supervisor for their action. You make sure the Site is secured and ask the Contractor to make an improvised barrier around the Site. You ask the Contractor to appoint its most trustworthy guards to set a perimeter. You inform the Employer and local authorities and you ask the Contractor to send you a notice in writing whereby it requests for a Variation (as this is needed for you to instruct the Contractor), thereby already in

C.

You inform the supervisor that given the sensitive nature of the findings, you need a formal and written notice as mentioned in Sub-Clause 4.24 second paragraph, otherwise you cannot give further instructions. You ask them to send it to you as soon as possible, because otherwise you are not able to entitle the Contractor to any extension of time and payment of costs.

D.

You immediately take action and give the instruction to the supervisor to make sure to cover this finding and till the excavation with material. You then redesign and make a determination (Sub-Clause 3.5) on a change of the Works — if needed — to make sure the execution can restart within days because of the need to finish this project.

Question 27

Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer ' s Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?

Options:

A.

True

B.

False

Question 28

When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition 1999)?

Options:

A.

Without undue delay after the issuance of the Taking-Over Certificate.

B.

Without undue delay after the issuance of the Performance Certificate.

C.

Within 21 days after the issuance of the Taking-Over Certificate.

D.

Within 21 days after the issuance of the Performance Certificate.

Question 29

(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the Contractor allowed to start the design of the Works before the Commencement Date? (1 correct answer applies))

Options:

A.

Yes, but Contractor will do so on its own risk.

B.

Yes, Contractor can start design and execution of the Works to make sure it won ' t lose any time.

C.

No, because any design or execution before the Commencement Date is prohibited in Clause 8.

D.

Yes, but Contractor will do so on Employer ' s risk.

Question 30

FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

Options:

A.

True

B.

False

Question 31

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?

Options:

A.

After issuance of the Taking-Over Certificate.

B.

After issuance of the Performance Certificate.

C.

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.

Until all outstanding works as stated in the Taking-Over Certificate are completed.

Question 32

(In a FIDIC Red Book, the Employer shall have prepared (or have prepared by a design consultant) all the design for the Works. Which of the listed documents form the basis for this design (2 correct answers apply))

Options:

A.

The Bill of Quantities

B.

The Specifications

C.

The Breakdown of Lump-Sum

D.

Schedule of Subcontractors

E.

The form of Contract Agreement

Question 33

You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer ' s financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?

Options:

A.

A prolonged suspension for more than 1 year has affected the whole of the Works.

B.

The Contractor does not receive the amount due under the latest Payment Certificate for more than 4 months after the due date.

C.

The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.

D.

The Employer failed to comply with a final and binding determination issued by the Engineer, and such failure constitutes a material breach of the Employer ' s obligations under the Contract.

Question 34

(Which one of the following statements is correct regarding the Employer ' s Representative under the FIDIC Silver Book (edition 1999)?)

Options:

A.

The Representatives of both the Employer and the Engineer have no authority to amend the Contract at all.

B.

The Employer may appoint an Employer ' s Representative to act on his behalf under the Contract.

C.

The Employer must always appoint an Employer ' s Representative to act on his behalf under the Contract.

D.

The Employer may appoint an Employer ' s Representative to act on his behalf under the Contract but has to consult the Contractor to agree to this Representative.

Question 35

Which of the following statements are not correct? [2017 Edition]

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor or the Engineer can request a meeting.

B.

Only the Engineer can call for a meeting

C.

Subcontractors cannot attend management or progress meetings unless the Engineer ' s approval is obtained.

D.

Only the Employer can call for a meeting.

E.

The Engineer shall keep records of the Progress Meetings.

Question 36

Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

FIDIC Conditions of Contract for Construction ( " Red Book " ).

B.

FIDIC Conditions of Contract for Plant and Design Build ( " Yellow Book " ).

C.

FIDIC Conditions of Contract for EPC/Turnkey Projects ( " Silver Book " ).

Question 37

If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?

Options:

A.

If the defects do not affect the use of the Works for their intended purpose, the Engineer can issue the Taking-Over Certificate.

B.

By giving reasons, the Engineer can refuse to accept the Works until repeated tests have been successfully performed.

C.

The Employer can request to take over the Works.

D.

The Party which is not liable for the cost of rectifying defects can expect the other Party to pay the cost of performing the repeated tests.

Question 38

In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to Sub-Clause 3.5:

" In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry out any determination regardless of a possible notice of dissatisfaction. "

What GP(s) is/are breached?

Options:

A.

GP1 only

B.

GP3 only

C.

GP1 and GP3

D.

GP1, GP2 and GP3

Question 39

Which one of the following statements best describes the requirements of Time for Completion?

Options:

A.

This is the Contractor ' s fundamental time-related obligation, namely completion the whole of the Works within the Time for Completion calculated from the Commencement Date.

B.

This is the Contractor ' s fundamental time-related obligation, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

C.

This is one of the Contractor ' s obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

D.

This is one of the Contractor ' s obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Effective Date.

Question 40

(In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer’s Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)

Options:

A.

This is an Employer’s Risk under Sub-Clause 17.3 (a)/(b), and the Contractor is entitled to EOT and Cost. The Engineer will assess actual entitlement after the event; no further notices are required.

B.

Violence is an Employer’s Risk; however, the Contractor can only claim after the situation ends. The Engineer cannot determine EOT or Cost yet, and the Contractor must submit a fully detailed claim later.

C.

The Contractor should have foreseen such risks due to the region’s history; therefore, Clause 19 is not applicable.

D.

The Employer is in breach of its obligation to provide safe working conditions under Sub-Clause 2.1; therefore, the Contractor can claim on that basis.

Question 41

Which of the following situations form legally binding contracts? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities)

Options:

A.

The Employer received the Contractor ' s Letter of Tender and issued a Letter of Intent.

B.

The Employer and the Contractor signed the Contract Agreement.

C.

The Employer received the Contractor ' s Letter of Tender and issued a conditional Letter of Acceptance.

D.

The Employer received the Contractor ' s Letter of Tender and issued Letter of Acceptance.

Question 42

Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?

(Choose all correct answers — multiple possibilities)

Options:

A.

The Employer is bound by the Certificate issued by the Engineer, and must make payment in full, except for any compensation arising from any claim which the Employer may have against the Contractor.

B.

The Employer is not bound by the Certificate issued by the Engineer.

C.

The Employer is bound by the Certificate issued by the Engineer and must make payment in full, irrespective of any entitlement to compensation arising from any claim which the Employer may have against the Contractor.

D.

If the Employer considers itself entitled to claim against the Contractor, notice and particulars must first be submitted under Sub-Clause 2.5. The Employer ' s entitlement is then to be agreed or determined by the Engineer, and then, incorporated as a deduction in a Payment Certificate.

Page: 1 / 14
Total 140 questions