iSQI CTAL-TM_Syll2012 Dumps

ISTQB® Certified Tester Advanced Level - Test Manager [Syllabus 2012] Questions and Answers

Question 1

Test Management

You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The project will follow a V-Model software development life cycle and it will have four formal levels of testing: component, integration, system and acceptance testing.

You must produce the test plan documentation for this project by providing an adequate coordination across the four levels of testing in order to assure auditability.

Which of the following answers would you expect to best describe how to organize the test plan?

Number of correct responses: 1

K32 credits

Options:

A.

Produce a single master test plan that covers in detail all four levels, describing the particular activities for all test levels

B.

Produce a master test plan that covers three levels (component, integration, system test) and a separate acceptance test plan

C.

Produce a master test plan describing the relationship between the four levels, and four separate detailed level test plans, one for each level

D.

Produce four separate detailed level test plans, one for each level, without a master test plan

Question 2

Test Management

You are managing the system testing for a SOA based system. The integrated system consists of several subsystems:

- a SOA middleware

- a CRM (Customer Relationship Management) system

- a BRM (Billing and Revenue Management) system

- a SMS (Subscriber Management System) system

and you performed a risk analysis based on these subsystems.

At the end of the scheduled period for test execution you produce a first classical report based on the traditional metrics of testing. Test pass/fail status and bug status (open/resolved) That table provides you a distorted picture of the quality risk, because there is no indication of the risk level of the failed tests, the tests not run, or the open bugs. Thus, you produce the following table to solve this distortion issue:

as

In the table above, where you have introduced the concept of risk weighting, the highest risk test or bug report has a score of 1, while the lowest risk test or bug report has a score of 0.04.

Which of the following subsystems, based on the risk scores of the table, is most risky?

Number of correct responses: 1

K43 credits

Options:

A.

SOA

B.

CRM

C.

BRM

D.

SMS

Question 3

After the presentation, you are asked to explain the chart.

Assume you have applied a full risk-based testing strategy.

as

Which of the following answers would you expect to best describe the pie chart?

Number of correct responses: 1

K43 credits

Options:

A.

All the risk items have been covered with tests. No more risk items remain to test

B.

According to the full risk-based testing strategy applied, it is very likely that the highest-risk items, tests and bugs remain in the blue and red areas. Therefore, it is very risky to release the application

C.

Only the lowest-risk items, tests and bugs should remain in the blue and red areas. Therefore the application can be released at any time subject to management of the items identified in those areas

D.

97 percent of the risk items has been tested. No open bugs or test failures remain. Only 3 percent of risk items remains to be covered by the remaining test

Question 4

Test Management

Which of the following statements about management of product quality risks in mature organizations with respect to the lifecycle, is true?

Number of correct responses: 1

K21 credit

Options:

A.

Mature organizations address product quality risks associated to non-functional characteristics only during the system test phase

B.

Mature organizations are aware that the contribution of testing to analysis of product quality risks is very important. The analysis should occur throughout the entire lifecycle

C.

Mature organizations don’t waste time identifying the sources of risks. They only focus on identifying product quality risks

D.

Mature organizations are aware that risk management of product quality risks only occurs during testing

Question 5

Test Management

Assume you are currently working on a project developing a system where functional requirements are very well specified. Unfortunately non-functional requirements do almost not exist.

You are the Test Manager. You have to choose a technique for test selection that allows testing of non-functional characteristics, especially reliability.

Which of the following techniques for test selection do you expect being most useful in this scenario?

Number of correct responses: 1

K21 credit

Options:

A.

A model-based technique based on the creation of operational profiles

B.

Ambiguity reviews

C.

Test condition analysis

D.

Cause-effect graphing

Question 6

People Skills – Team Composition

Which of the following would you expect to be most likely an example of a motivating factor for testers?

Number of correct responses: 1

K21 credit

Options:

A.

The resources allocated for the testing activities are not sufficient and don’t allow the testers to contribute to the quality of the product

B.

The testers contribution to the quality of the software products developed from an organization is recognized with increased responsibilities

C.

The same regressions tests are executed manually by the same testers, for every product release, without any progression in content

D.

The testers are asked to perform, in parallel with their testing tasks, other tasks unrelated to their testing responsibilities

Question 7

People Skills – Team Composition

Assume you are managing the system testing execution phase of a project.

The system test execution period for that project is scheduled for eighteen weeks and the release date is scheduled at the end of system testing.

During the sixth week of system test execution, at the staff meeting, the project manager informs you that the project deadlines are changed and the release date that is only three weeks ahead.

This new release will not allow the completion of the system tests. Suppose also that you have followed a risk-driven test approach for this project.

Which of the following statements represents the worst way to lead your test team in the next three weeks?

Number of correct responses: 1

K21 credit

Options:

A.

Neglect your management activities and work side-by-side with your test team executing tests

B.

Considering the executed tests, you should reduce the test coverage back on the risk analysis and adjust downward the priority of the associated risk items

C.

Convince all the people of your test team that each of them is an important and needed member, and that their contribution is fundamental to the success of the team

D.

Favor and encourage a proactive attitude where people ask for new tasks as soon as they finish their current tasks

Question 8

People Skills – Team Composition

Which of the following would you expect to be most likely an example of a demotivating factor for testers?

Number of correct responses: 2

K21 credit

Options:

A.

The management asks the testers to be kept informed about the intensity, quality and results of testing

B.

The testers’ recommendations to improve the system or its testability are adopted by the development team

C.

The same regressions tests are manually executed by the same testers, for every product release, without regression test tools

D.

The testers are assessed on whether and how often they detect important and critical failures

E.

Test quality is measured by counting the number of customer/user reported problems.

Question 9

People Skills – Team Composition

Your test team consists of four members (Mary, Bob, Mark, Dave) with different interpersonal skills.

The following skills assessment spreadsheet shows the characteristics of the team members with respect to a list of interpersonal-skills (for each characteristic only the member with the highest level of that characteristic is indicated and marked with ‘X’):

as

On the next project a member of your test team will have to perform some routine tasks requiring collaboration with other teams.

Who in your test team would you expect to be most suitable at doing these tasks?

Number of correct responses: 1

K43 credits

Options:

A.

Mary

B.

Bob

C.

Mark

D.

Dave

Question 10

People Skills – Team Composition

Consider the following analysis of testing skills performed on four people: Alex, Robert, John and Mark (all the skills have been rated on an ascending scale: The higher the score, the better the skill):

as

Which of these people, based on this analysis, would you expect to be most suitable to work specifically as test designer?

Number of correct responses: 1

K43 credits

Options:

A.

Alex

B.

Roberta

C.

John

D.

Mark

Question 11

Testing Process

Consider an information system of a Pay-Tv company based on a SOA architecture.

The integrated system currently consists of three core systems:

- a CRM (Customer Relationship Management) system

- a BRM (Billing and Revenue Management) system

- a CAS (Conditional Access System) system

all of them communicating with SOA Middleware.

You have been asked to manage the testing activities for the integration of two additional off-the-shelf systems from two different vendors: a SMS (Short Message Service) server and an IVR (Interactive Voice Response) system.

Assume that there is a high likelihood that the two off-the-shelf systems will be low-quality and that you have a clear proof that the testing performed by the two vendors on their systems has been unsystematic and unprofessional. This obviously leads to higher quality risk for the overall integrated system.

You are the Test Manager of this project. Your main goal is to plan for testing activities to mitigate this risk.

Which of the following answers best describes the test activities (assuming it is possible to perform all of them) you should plan for?

Number of correct responses: 1

K43 credits

Options:

A.

You should plan for an informal and minimal acceptance test of the two off-the-shelf systems and then a single end-to-end test of the overall integrated system

B.

You should directly plan for a single end-to-end test focused on end-to-end tests of the overall integrated system without an acceptance test of the two off-the-shelf systems

C.

  You should plan for two levels: a system integration test and an end-to-end test of the overall integrated system

D.

You should plan for adequate re-testing of both the systems followed by a system integration test and an end-to-end test of the overall integrated system

Question 12

The following is the unique “critical” quality risk item that has been identified:

CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user

Test analysis for system testing has just begun and the following test conditions have been identified:

TC-SEL-2. Test the selection of the package sizes

TC-SEL-4. Test wrong numbers of bottles for an order

TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user

Assume that you have used traceability to determine the logical test cases that cover all the requirements and the single risk item identified in that scenario.

Which of the following is a positive logical test that is complete and correct, and covers the REQ-SEL-4 requirement?

Number of correct responses: 1

K32 credits

Options:

A.

Select a 6-bottles package, then try to insert 5 bottles; verify that no error messages are displayed

B.

Select a 6-bottles package, then try to insert 7 bottles; verify that no error messages are displayed

C.

Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of bottles" message is displayed

D.

Select a 6-bottles package, then try to insert 7 bottles

Question 13

The following are the requirements identified as “critical”:

REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to define an item to purchase

REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart

REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit voucher

REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the available credit already charged on the smartcard

REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the accepted credit cards (Visa, MasterCard and Great Wall Card)

REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the “select” and “purchase” pages going back to the “browse” page (anonymous navigation)

Moreover the following quality risk item has been identified as “critical”:

QR-P1. The web customer portal might not be able to provide the expected response time (less than 10 sec) for the purchase transactions under a load of up-to 1000 concurrent users

Test analysis for system testing has just begun and the following test conditions have been identified:

TC-SEL-01. Test the combinations of products and durations to define an item to purchase

TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart

TC-PUR-01. Test the purchase of an item

TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard

Assume that you have used traceability to determine the logical test cases that cover all the requirements and the single risk item identified in that scenario.

Which of the following is a positive logical test that is complete, is correct, and covers the REG-LOGO-001 requirement?

Number of correct responses: 1

K32 credits

Options:

A.

On the purchase page (“purchase state”), click the logout button; verify that the browse page (“browse state”) is displayed

B.

On the select page (“select state”), click the logout button

C.

On the purchase page (“purchase state”), click the logout button; verify that the “Impossible to logout – complete or cancel the current transaction” message is displayed

D.

On the browse page (“browse state”), click the logout button

Question 14

A chart showing the trend in the lag time from defect reporting to resolution during system testing is also available. The chart shows that the daily closure period is consistently and significantly above the rolling closure period for a long period of the system testing phase.

Almost all defects found during system testing have been related to the system as a whole, not related to single units or integrations issues. Almost all quality risks have been addressed during the unit and integration testing phase and no residual quality risks were present in the integrated system. This has been confirmed by exploratory testing sessions performed during system testing, targeted at finding defects in these quality risk areas.

Based on the given information only, which one of the following areas would you expect to be considered more in the retrospective meeting in order to be improved?

Number of correct responses: 1

K33 credits

Options:

A.

The requirements review

B.

The defect management process

C.

The quality risk analysis process

D.

The system design and architecture design reviews

Question 15

The following is the unique “critical” quality risk item that has been identified:

CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user

Test analysis for system testing has just begun and the following test conditions have been identified:

TC-SEL-2. Test the selection of the package sizes

TC-SEL-4. Test wrong numbers of bottles for an order

TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user

What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and EXCR2 exit criteria?

Number of correct responses: 1

K32 credits

Options:

A.

4

B.

3

C.

2

D.

1

Question 16

Defect Management

Which of the following information would you expect to be the most useful to perform a defect clustering analysis?

Number of correct responses: 1

K21 credit

Options:

A.

The trend in the lag time from defect reporting to resolution

B.

The defect component information

C.

The lifecycle phase in which the defect has been introduced

D.

The defect removal efficiency information

Question 17

Defect Management

During the system testing phase a tester from your test team observes a failure in the system under test and he/she decides to create an incident report. The incident report is currently in a “new” state, indicating it needs to be investigated.

Which THREE of the following information items can’t yet be present in the incident report?

Number of correct responses: 3

K32 credits (2 credits out of 3 credits correct, 1 credit point)

Options:

A.

The type of defect that caused the failure

B.

The actual and the expected result highlighting the failure

C.

The lifecycle phase in which the defect has been introduced

D.

What really caused the failure (actual cause)

E.

Steps to reproduce the failure, including screenshots, database dumps and logs where applicable

Question 18

Defect Management

Consider a defect report and assume that a part of its lifecycle includes the following states:

New: Is the initial state

Working: Means that the developers are addressing the defect in order to produce a fix for the defect

Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers

Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect

Closed: is the final state

Which of the following answers represents an invalid sequence of states that can’t lead the bug report to the “Closed” state?

Number of correct responses: 1

K21 credit

Options:

A.

New, Working, Verification, Working, Clarification, Working, Verification, Closed

B.

New, Working, Clarification, Working, Verification, Closed

C.

New, Working, Verification, Working, Clarification, Working, Closed

D.

New, Working, Verification, Closed

Question 19

Defect Management

Assume you are working on a defect management process to be used by a software organization to track the current status of the defects reports for several projects.

When a defect is found for investigation a defect report is created in “Opened” state that is the unique initial state. The defect report status has also a unique finale state that is the “Closed” state.

The following state transition diagram describes the states of this defect management process:

as

where only the initial (“Opened”) and final (“Closed”) states are indicated while the remaining states (V, W, X, Y, Z) have yet to be named.

Which of the following assignments would you expect to best complete the defect management process?

Number of correct responses: 1

K32 credits

Options:

A.

V=Rejected , W=Corrected , X=Validated, Y=Re-Opened, Z=Assigned

B.

V=Assigned, W=Validated , X=Corrected, Y=Re-Opened, Z=Rejected

C.

V=Assigned, W=Corrected , X=Validated, Y=Re-Opened, Z=Rejected

D.

V= Corrected, W=Assigned, X=Validated, Y=Corrected, Z=Rejected

Question 20

Your test team is in the process of completing final regression testing one week before the release date. One of your staff has just uncovered a critical defect that causes

data corruption.

What should you do? [2]

Options:

A.

Update the risks in your test plan to cover data corruption issues and update your test cases to be sure you test for this in the future

B.

Write a high priority defect and follow the escalation communication plan as defined in your test plan

C.

Write a high priority defect and call the business stakeholders to warn them about it

D.

Update the weekly status charts and change the project status to red

Question 21

During the follow-up phase the following conditions are checked:

X1. The code has been completely reviewed

X2. All the identified defects have been correctly fixed and the modified code has been compiled successfully and run through all the static analyzers used by the project without warnings and errors

X3. The modified code is available under the configuration management system with a new version number for the specified CI

If these conditions are fulfilled then the review process terminates.

Which of the following characteristics of a formal review is missing in this description?

Number of correct responses: 1

K21 credit

Options:

A.

Defined entry and exit criteria

B.

Checklists to be used by the reviewers

C.

Deliverables such as reports, evaluation sheets or other review summary sheets

D.

Metrics for reporting on the review effectiveness, efficiency, and progress

Question 22

Reviews

You are a Test Manager working for a software organization where reviews have never been applied. After a meeting with your managers examining a business case for reviews, (including their costs, benefits, and potential issues), the management finally decides to adopt formal reviews for future projects.

You have been given a budget that you have spent to provide training in the review process and to introduce the review process on a pilot project.

On that pilot project the introduction of reviews has been very positive in terms of positive involvement from all the participants. All the reviews applied to different documents have been very effective for their purposes (especially at revealing defects).

Which of the following answers describes an important success factor for the introduction of formal reviews which is missing in this scenario?

Number of correct responses: 1

K43 credits

Options:

A.

Management support

B.

Participant support

C.

Definition and use of metrics to measure the ROI (Return On Investment)

D.

Training in the review process

Question 23

Reviews

Consider the following list of statements about audits and management reviews:

I. Audits are usually more effective than management reviews at finding defects

II. Audits and management reviews have the same main goals, the only difference is related to the roles and level of formality

III. A typical outcome of an audit includes observations and recommendations, corrective actions and a pass/fail assessment

IV. An audit is not the appropriate mechanism to use at the code review in order to detect defects prior to dynamic testing

Which of the following statements is true?

Number of correct responses: 1

K21 credit

Options:

A.

I. and III. are true; II. and IV. are false;

B.

II. and III are true; I. and IV. are false;

C.

III. and IV. are true; I and II are false;

D.

I, III and IV are true; II. is false;

Question 24

The main objectives the senior management team wants to achieve are:

- to reduce the costs associated with dynamic testing

- to use reviews to ensure that the project is on course for success and following the plan

- to use reviews as a well-documented and effective bug-removal activity following a formal process with well-defined roles

- to determine the effectiveness of reviews in terms of phase containment

- to improve phase containment effectiveness

Which of the following answers would you expect to describe the best way to achieve these objectives?

Number of correct responses: 1

K43 credits

Options:

A.

You should plan for lightweight exit-phase reviews at the end of each development and testing phase, and plan for a process of gathering information from testing to perform an analysis aimed at identifying the larger cluster of defects

B.

You should plan for formal exit-phase reviews at the end of each development and testing phase, and plan for a process of gathering information from testing to perform an analysis aimed at identifying the larger cluster of defects

C.

You should plan for formal exit-phase reviews at the end of each development phase and testing phase, and plan for a process of gathering information from testing to perform an analysis of the bugs found during testing to determine the people responsible for those bugs

D.

You should plan for formal exit-phase reviews at the end of each development and testing phase, and plan for a process of gathering information from testing to perform an analysis of the bugs found during testing to determine the phase in which they have been introduced

Question 25

Reviews

Which of the following factors could negatively influence a review?

Number of correct responses: 1

K21 credit

Options:

A.

Include people with the adequate level of knowledge, both technical and procedural

B.

Include people who are detail-oriented and scrupulous at finding issues

C.

Include as many people as possible in order to have more viewpoints about possible problems on the item under review

D.

Include people able to contribute to a clear, thoughtful, constructive and objective discussion

Question 26

Test Tools and Automation

Assume you are a Test Manager involved in system testing of a CRM application for a Pay-TV company. Currently the application is able to support a proper number of users assuring the required responsiveness. Since the business is expected to grow, you have been asked to evaluate the ability of the application to grow to support more users while maintaining the same responsiveness.

Which of the following tools would you expect to be the most useful at performing this evaluation?

Number of correct responses: 1

K21 credit

Options:

A.

Coverage tools

B.

Test management tools

C.

Static analysis tools

D.

Performance tools

Question 27

Test Tools and Automation

After a selection process you have selected a test management tool that is going be introduced in your organization and used by your test team in a pilot project.

You have already identified the member of your test team who will be the administrator of the tool, since he/she has a significant experience with the administration of test management tools and so he/she is able to make effective and efficient up-front decisions about "how" the tool will be used. You have also developed a training plan for the other members of your test team.

In collaboration with the administrator of the tool you have also devised standard ways of managing, storing and maintaining the tool and its assets including backup/restore procedures.

You have also analyzed standard formats supported by the tool (CSV, XLS, XML, etc.) to export, import and archive all the information managed by the tool itself (requirements, test case specifications, test plans etc.) for compliance with the most important test management tools, in order to minimize the impacts of migrating this information to a new tool that could replace the existing one in the future.

Which of the following phases in the lifecycle of the new tool has NOT been adequately considered in this description?

Number of correct responses: 1

K21 credit

Options:

A.

Acquisition

B.

Support and maintenance

C.

Evolution

D.

Retirement

Question 28

Test Tools and Automation

Assume you are managing a test automation project for a mission-critical system.

Because vendor provided tools and open source solutions don't meet the needs of this project, you ask your test team to develop a custom automation framework.

Which of the following management issues associated to the development of this custom automation framework is least likely to manage?

Number of correct responses: 1

K21 credit

Options:

A.

Proper testing for the custom automation framework must be performed

B.

The custom automation framework will require an adequate documentation

C.

The changes to the custom automation framework should be communicated to all external users of this tool under the GNU license

D.

The custom automation framework will need proper maintenance

Question 29

Test Tools and Automation

Assume you are the Test Manager in charge of independent testing for avionics applications.

You are in charge of testing for a project to implement three different CSCI (Computer Software Configuration Item):

- a BOOT-X CSCI that must be certified at level B of the DO-178B standard

- a DIAG-X CSCI that must be certified at level C of the DO-178B standard

- a DRIV-X CSCI that must be certified at level A of the DO-178B standard

These are three different software modules written in C language to run on a specific hardware platform.

You have been asked to select a single code coverage tool to perform the mandatory code coverage measurements, in order to meet the structural coverage criteria prescribed by the DO-178B standard. This tool must be qualified as a verification tool under DO-178B.

Since there are significant budget constraints to purchase this tool, you are evaluating an open-source tool that is able to provide different types of code coverage. This tool meets perfectly your technical needs in terms of the programming language and the specific hardware platform (it supports also the specific C-compiler).

The source code of the tool is available.

Your team could easily customize the tool to meet the project needs. This tool is not qualified as a verification tool under the DO-178B.

Which of the following are the three main concerns related to that open-source tool selection?

Number of correct responses: 3

K43 credits (2 credits out of 3 credits correct, 1 credit point)

Options:

A.

Does the tool support all the types of code coverage required from the three levels A, B, C of the DO-178B standard?

B.

Does the tool have a good general usability?

C.

What are the costs to qualify the tool as a verification tool under the DO-178B?

D.

Is the installation procedure of the tool easy?

E.

Does the tool require a system with more than 4GB of RAM memory?

F.

Is the licensing scheme of the tool compatible with the confidentiality needs of the avionics company?

Question 30

Test Tools and Automation

In your organization the following tools of the same vendor are currently in use: a requirements management tool, a test management tool and a bug tracking tool.

You are the Test Manager.

You are currently evaluating a test automation tool of the same vendor (to complete the vendor's tool suite) against an interesting open-source test automation tool under the GNU GPL (General Public License).

There are no initial costs associated to that open-source tool.

Which of the following statements associated to the selection of the open-source tool is correct in this scenario?

Number of correct responses: 1

K21 credit

Options:

A.

The open-source tool can be modified but only if the community of developers of that tool gives you the formal permission to modify it

B.

There are no initial costs for the open-source tool but you should carefully consider the costs associated to the integration with the existing tools and also evaluate the recurring costs

C.

There are no initial costs for the open-source tool because open-source tools are usually low-quality, while vendor tools have always a better quality than the corresponding open-source tools

D.

The open-source tool can be modified but it can’t be distributed further in any way

Question 31

Improving the Testing Process

Which of the following statements about the STEP test process improvement model is true?

Number of correct responses: 1

K21 credit

Options:

A.

In the STEP model, tests validate the requirements and use cases when they are developed

B.

The STEP model stresses defect detection and demonstration of capability, whereas the defect prevention is a secondary potential goal of testing

C.

The STEP model assures that the system requirements specification and the test design specification processes don't overlap

D.

In the STEP model, testware design occurs after coding

Question 32

Improving the Testing Process

Which of the following statements about the TMMi test process improvement model is true?

Number of correct responses: 1

K21 credit

Options:

A.

In TMMi all the process areas at lower levels must be 75% complete by achieving specific and generic goals in order to claim the higher level

B.

TMMi provides an approach for test process improvement such as the IDEAL (Initiating, Diagnosing, Establishing, Acting and Learning) model

C.

TMMi has a staged architecture for process improvement with seven maturity levels

D.

At TMMi level 1 testing is chaotic without a defined process, and it is often seen as the same as debugging

Question 33

Improving the Testing Process

Consider the following statements describing the importance of improving the test process:

I. Test process improvement is important because being focused only on the test process it can provide recommendations to improve the test process itself, but it can’t indicate or suggest improvement to areas of the development process

II. Test process improvement is important because it is much more effective than software process improvement to improve the quality of a software system

III. Test process improvement is important because several process improvement models (STEP, TPI Next, TMMi) have been developed over the years

IV. Test process improvement is important because every organization, regardless of the context, should always achieve the maximum level of maturity of testing described in the test improvement models such as TMMi

Which of the following answers is correct?

Number of correct responses: 1

K21 credit

Options:

A.

I. and IV. are true; II. and III. are false

B.

I., II., III. and IV are false

C.

I., II. and III are true; IV. is false

D.

I., II. and III. are false; IV. is true

Page: 1 / 13
Total 130 questions