Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 Questions and Answers

Question 1

Which of the following statements is true regarding documentation standards? [2]

Options:

A.

Documentation standards are a lower priority than testing standards.

B.

Documentation standards can vary depending on the test level.

C.

Agile projects consistently use level test plans and documentation standards.

D.

Documentation standards are determined by the Project Manager.

Question 2

Which of the following is a generic good practice when evaluating and selecting a test tool?

Options:

A.

Define the ownership of the tool

B.

Run a pilot project to validate the selection criteria

C.

Identify internal requirements for coaching, mentoring or training in its use

D.

Plan a proof-of-concept to be performed by the first project that uses the tool

Question 3

Assume that you are working for a company that has maintained and tested a car parking permit system for many years. The system holds the name and address of permit holders and automatically writes to the permit holder with a form to renew or cancel their permit each year.

The test plan states the following:

"since the system is considered a stable system. Boundary Value Analysis is the only test case design technique that needs to be applied during testing"

Consider the following change that was detailed in the Requirements Specification for a replacement to an existing parameter held within the system;

• The specified renewal date for each permit must be not be after 31 st January 2020. Which one of the following is a valid test condition that satisfies both the requirement and the test plan?

SELECT ONE OPTION

Options:

A.

Input the dates either side of and including 31/01/2020, and select tests from the regression pack relating to the renewal date and printing only.

B.

Input the date 31/01 /20 in the wrong field to see what happens, and run the whole of the regression test pack.

C.

Input the date 01/02/2020 and confirm this is not accepted. and select tests from the regression test back relating to the renewal date only

D.

Input a date in an invalid format e.g. 31 FEB 2020, and select tests from the regression pack relating to renewal date, policy holder's name, address and printing.

E.

Input the date 01/02/2020 and confirm this is not accepted. and select tests from the regression testback relating to the renewal date only

Question 4

Which of the following is the MOST relevant factor to consider when selecting an open source tool? SELECT ONE OPTION

Options:

A.

The number of testers that will use the tool.

B.

The initial cost of the tool and ongoing annual costs.

C.

The number of user screens in the tool.

D.

The formal user support available for the tool.

Question 5

Which testing metric identifies defect density? [1]

Options:

A.

Project

B.

Product

C.

Process

D.

People

Question 6

Your last project was released three months ago and used a risk-based approach. In production, a number of serious failures in low risk areas have occurred.

What is the most important lesson to be learned from this information? [2]

Options:

A.

The "lessons learned" session should have been conducted prior to deployment.

B.

A broader cross-functional team should contribute to the risk analysis.

C.

The project manager should have set stakeholder expectations for serious failures.

D.

Future projects should test the lower risk areas first.

Question 7

Which of the following are primary activities in conducting product risk analysis? [1]

Options:

A.

Risk testing, risk management

B.

Risk identification, risk assessment

C.

Risk identification, risk testing

D.

Risk management, risk assessment

Question 8

Assume that you are part of a team conducting test design for a new university system that will allow students to update their own personal information. The Test

Strategy states that positive and negative testing should be carried out. along with performance, security and interoperability testing against all new requirements.

The following requirements have been identified by stakeholders:

1. Students must be able to make changes to the following information:

a Name (due to marital status)

b Marital status

c. Home address

d. Home telephone number

e. Email address

f. Mobile telephone number

g. Contact details in case of emergency

2 Only Reception staff must have access to the information held.

3 The system must support 2000 concurrent users and details updated on the system within 20 seconds.

4. Interoperability of the new system with the other systems maintained by the University for student Registrations.

Test analysis for functional and non-functional testing has iust bequn and the following test conditions have been identified:

as

Which one of the following is a valid test condition that is missing from the table of test conditions and has clear traceability back to the test strategy and requirements?

SELECT ONE OPTION

Options:

A.

Time taken to update student information is 20 seconds or less when sup-plied correctly, or an error message is returned

B.

System is compatible with market leading accessibility tools for blind or partially sighted users.

C.

Correct input of home telephone numbers using a string of alpha characters only.

D.

Correct input of student's date of birth details, using the format dd/mm/yyyy

Question 9

Your company specialises in the manufacture of luxury garden furniture to the UK market and it is starting a project that will deliver a major update to its payment processing component, addressing improvements to functional suitability and performance efficiency.

A decision has been made to transfer responsibility for functional system test procedure creation and execution to a software house, located offshore. System test analysis and design will be performed onshore, at the company's UK headquarters. As the senior test manager for your company, you want to employ another experienced test manager to oversee the daily operations of the software house to ensure that their work meets required quality standards and adheres to the agreed organisational test strategy and project test plan.

Which option presents the skills that are of MOST relevance for the new test manager role?

Options:

A.

Professional competence - knowledge of test implementation and execution. Methodological competence - application of black- and white-box test techniques.

B.

Professional competence - project management skills. Social competence - communication, conflict resolution and assertiveness.

C.

Professional competence - knowledge of performance test design and execution. Social competence - awareness of cultural differences and challenges.

D.

Professional competence - ability to develop a test strategy. Social competence - ability to develop the skills of the third-party testers.

Question 10

Which of the following is an advantage of specifying test conditions at a detailed level? [1]

Options:

A.

Can be used to identify test coverage gaps

B.

Saves time

C.

Can be used to leverage use cases for acceptance testing

D.

Improves maintainability and reduces ownership costs for the testware

Question 11

You are Test Manager working on a project which is improving the user interface for its call centre staff handling customer enquiries. The project has completed UAT for the first iteration; however a large number of defects were raised by call centre staff seconded to help with the User Acceptance testing.

The defects described the user interface as not being intuitive enough with a poor 'help' facility. A user representative spent a week working with developers and system testers to explain the issues, which were subsequently agreed to have resulted from poorly specified usability requirements.

The requirements were defined separately for each iteration and have been formally reviewed by business analysts, developers and the IT director.

The user representative was also able to answer a number of other questions that the system test team had regarding call centre workflows, which improved their domain knowledge.

You have been asked to conduct a project retrospective and recommend improvements for the next iteration which introduces further user interface changes. Which of the following would be the MOST effective improvement for the next iteration?

Options:

A.

System test analysts to attend external training on usability testing techniques.

B.

System test cases to incorporate usability testing and be reviewed by a call centre user representative.

C.

Call centre representatives to participate in reviews of the user interface requirements.

D.

A call centre user representative to be seconded to the system test team to help improve test design.

Question 12

Which of the following aspects should test progress metrics be mapped to? [1]

Options:

A.

Lines of code

B.

Exit criteria

C.

Post-implementation defect discovery rate

D.

Defect resolution rate

Question 13

You are performing a risk assessment for a financial application using quantitative risk analysis. The following is a table describing the analysis undertaken so far:

as

Which of the following statements correctly describes the outcome of the risk assessment using the "Cost of Exposure" technique in this scenario? SELECT ONE OPTION

Options:

A.

Testing for failures associated to PR4 should happen first.

B.

PR3 and PR4 should be tested while PR! and PR2 should not be tested.

C.

PR2 should be tested while PR1. PR3 and PR4 should not be tested

D.

PR1, PR3 and PR4 should be tested while PR2 should not be tested

Question 14

Assuming that 'In progress' means that somebody is working on a fix and that 'Resolved' means that the fix passed the confirmation test; which option provides a defect workflow that flows in a sensible way from an initial state to a terminal state?

Options:

A.

New, Under Investigation, Rejected, Re-test, Resolved, Closed

B.

New, Under Investigation, In progress, Re-test, Resolved, Closed, Deferred

C.

In progress, Under Investigation, Deferred, Retest, Resolved, Closed

D.

New, under investigation, Deferred, In progress, Re-test, Resolved, Closed

Question 15

The previous release of an in-house invoicing application was live for 6 months before beingreplaced by a later release.

• Before it went live, €1,500 had been spent on defect prevention and a further €4,500 had been spent on writing and running tests; these tests found 80 defects and the average cost of dealing with these was €50 each.

• By the time that it was replaced, defect reports from live running showed that pre-release testing had found only 80% of the defects that were present; the average cost of dealing with the defects that went live was 12 times that of the internal failures.

Which statement is TRUE?

Options:

A.

Neither external failure costs nor total Cost of Quality can be calculated from the available data

B.

The external failure costs were €13,000 and the total Cost of Quality was €23,000

C.

Each defect found before release saved an average of €600

D.

The external failure costs were €12,000 and the total Cost of Quality was €22,000

Question 16

Which of the following is likely to occur if reviewers do not have an adequate level of technicalknowledge? [1]

Options:

A.

There will be no impact as long as they have sufficient business knowledge.

B.

There will be no impact as long as they have sufficient process knowledge.

C.

The review is likely to be less efficient.

D.

The review will be shorter because any technical aspect can be skipped.

Question 17

You are a new Test Manager on a maintenance release for an existing mature product that is expected to be retired in the not too distant

future. The previous release had utilized a performance regression test suite written in an in-house custom tool using the same

programming language as the product itself. This suite will most likely require tweaking to ensure it works with the new version of the

product. While there are several members in the performance testing team, the original author of the performance testing tool has moved on

to another company, and none of the remaining staff have a great deal of familiarity with the performance test scripts used to test this

product.

How would you recommend this scenario be addressed? [3]

Options:

A.

Retire the in-house tool and switch to a vendor supported tool for performance testing.

B.

Reduce the scope of the product testing to exclude performance testing.

C.

Make the in-house tool available to the open source community.

D.

Leverage the development team to fill any knowledge gaps in the in-house tool.

Question 18

The diagram shows a defect workflow in which two states do not have appropriate names.

Which option could correctly provide the missing state names?

Options:

A.

State X = Open, State Y = Clarification

B.

State X = Confirmation, State Y = Resolved

C.

State X = Terminated, State Y = Archived

D.

State X = Duplicate, State Y = Postponed

Question 19

You have been promoted to Test Manager within your company. Your new manager states that your test team utilized a risk-based test approach for the last release but in production, a number of

serious failures in lightly tested areas have occurred.

What would be your first action prior to the start of the next test phase for the next release? [3]

Options:

A.

Ensure you have the correct stakeholders' participation during the risk assessment process

B.

Review the test cases executed from the previous release.

C.

Request functional requirements be prioritized in order of importance to the stakeholder.

D.

Review the production defects and determine if they are valid.

Question 20

Most managers in your company consider the efforts of your test team valuable, while others seecomprehensive testing as an unnecessary cost overhead to the SDLC.

What action could the Test Manager take to quantify the value of testing to the organization? [3]

Options:

A.

Develop metrics that illustrate planned and actual testing hours.

B.

Review the Test Plan with the management team.

C.

Determine the cost of external failures.

D.

Demonstrate the role QA has in similar size organizations.

Question 21

Which of statement about defect management is TRUE?

Options:

A.

A good defect management committee reduces the importance of a defect management tool

B.

A defect management committee should consider the benefits, risks and costs associated with fixing a defect

C.

All projects should have a full-time defect manager to follow up decisions made about defects

D.

Cross-functional defect management is important, but only for defects at the higher severity levels

Question 22

Which one of the following is NOT a determining factor when considering the optimal time to conduct a document review? SELECT ONE OPTION

Options:

A.

Management procedures have been reviewed

B.

Review time is built into the schedule.

C.

The document is in a reviewable state.

D.

Suitably skilled reviewers are available.

Question 23

While mining the defect database for patterns of problems in the last release, a Test Manager notices that many of the most damaging failures were caused by defects

injected during the low-level design phase.

Which of the following actions will likely give this project the most effective solution to this problem? [3]

Options:

A.

Increased static analysis during the implementation phase

B.

Mandatory reviews of all important design work products

C.

Formal inspections of the code modules affected by the last release

D.

Increased white-box coverage during system testing

Question 24

Which one of the following metrics would be MOST suitable for helping to determine whether test analysis and design is complete? SELECT ONE OPTION

Options:

A.

Percentage of requirements linked to passed test cases.

B.

Number of testability defects found in the requirements.

C.

Number of test cases automated versus planned.

D.

Number of product risks covered by test conditions.

Question 25

You are Test Manager of a project delivering a workflow system for complex business processes It has been decided a tool is required to increase the efficiency of test execution. What would be a valid issue to consider when deciding whether to build a custom made tool?

SELECT ONE OPTION

Options:

A.

The tool may only be useable for this project and have no long term benefits

B.

The tool may be dependent on the person creating the tool if it is not adequately documented.

C.

It may not be possible to integrate the tool with existing tools used in the organisation.

D.

The tool may not meet the specific requirements for testing this project.

Question 26

Referring to SCENARIO 2 It has been agreed that Project 1 will be delivered using an Agile approach, with user stories delivered across three sprints, each lasting 4 weeks. The programme manager is concerned about RISK 3 and wants the Master Test Plan to specify an effective test process improvement approach.

Which of the following is the best test process improvement approach for Project 1 ? SELECT ONE OPTION

Options:

A.

Test process improvement is not possible for this project as the Agile approach does not allow time to make improvements.

B.

A TMMi assessment should be run at the end of each sprint to identify improvements for the next sprint.

C.

Short post-sprint review sessions should be conducted to identify areas of improvement for the next sprint.

D.

A CTP assessment should be run after each sprint to identify critical test processes that need improving.

Question 27

Refer to SCENARIO 2 Project 2 is to be delivered using a RAD software development model. There will be two increments, the first will deliver a simple prototype user interface to facilitatetesting of the sound system delivered by 'Silver Sound Ltd', the second will deliver the full user interface required for the production system.

Development of the business requirements and project plan are underway, detailed system analysis will follow for each increment.

You have studied the test policy and risk register and must plan the next set of test activities. Which one of the following is the MOST effective approach for this project?

SELECT ONE OPTION

Options:

A.

Develop a master lest plan for each increment as soon as systems analysis is complete, then proceed with test analysis.

B.

Conduct exploratory testing only for the first increment as it is a prototype solution, commence test charter planning for increment 2

C.

Conduct high-level test planning and test analysis now, followed by more detailed test planning and test analysis for each increment considering use of automation where appropriate.

D.

Finalize detailed test planning now for both increments, conduct exploratory testing for the first increment, then use automated tests only for increment 2.

Question 28

Which TWO of the following metrics will be MOST useful in helping the stakeholders to decide whether to allow the system into acceptance testing?

    Breakdown of all risks by status (closed / not fully tested / one or more tests failed)

    Breakdown by test priority of test execution status (passed / failed / not run)

    Breakdown of outstanding risks by risk level and status (not fully tested / one or more tests failed / both)

    Breakdown of unresolved defects by severity and status

    Breakdown of unresolved defects by Risk Id/s that is/are affected by them

Options:

A.

3&4

B.

2&5

C.

1 &4

D.

1 &2

Question 29

You are the Test Manager of a four-person test team working for a small distribution company with a single warehouse. Your team has been working with a third party development team on a new

inventory management system. The company expects this system to generate approximately one million dollars per annum in profits for the company. Early in the project, various risks were

identified, and steps taken to mitigate those risks.

For example, you sent your test team for training on the new system, and upgraded the test environment. There are still some lingering risks that have not been addressed, but they have been

determined to have a low chance of occurring, with minimal impact if they do occur.

What would be the best option to mitigate these remaining risks? [3]

Options:

A.

Note the risks, and ignore them for now.

B.

Redo the project test plan to add additional testing for these risk items.

C.

Contract with the Risk Protection Insurance company to assume these risks at a cost of $500,000 per annum.

D.

Create a cross-functional team to work to reduce the impact and likelihood of these risks coming to fruition.

Question 30

Which option correctly presents the main characteristics of test estimation?

Options:

A.

Time - Effort - Quality

B.

Time - Cost - Effort

C.

Quality - Cost - Effort

D.

Time - Cost - Quality

Question 31

You are testing a new product that will turn on the windshield wipers of a car when the sensors detect there is moisture on the windshield. Depending on the information

returned from the sensors, the wipers will be turned on at one of the following speeds: slow intermittent, medium intermittent, fast intermittent, slow constant, medium

constant, fast constant. Your team has identified the following test condition:

Test Condition 1.1.1 - Verify that the windshield wipers can go from slow constant to fast constant speed when the amount of moisture increases appropriately.

Your team has defined the following steps for a test case for this test condition:

1. Set the moisture sensor to request slow constant

2. Increase the moisture to set the sensor to request fast constant

3. Verify that the wipers respond with fast constant speed

Given this information, which of the following statements is correct? [2]

Options:

A.

This test case is traceable to the test condition and provides 100% requirements coverage of the defined test condition.

B.

There is not enough information in the test condition to define a test case.

C.

This test case is not traceable to the test condition.

D.

The test case is traceable to the test condition and provides 100% statement coverage of the defined test condition.

Question 32

SCENARIO 1

DreamPartner dating agency are redesigning their dating application following a major security breach in which sensitive customer data was made publically available. The redesign includes stronger security encryption and performance tuning.

The product risk register for the redesign project, which was produced after all requirements had been agreed, includes the following:

as

The organisational Test Strategy contains the following objectives:

1. A Risk-based lest approach must be adopted for all projects

2. Functional regression testing should start as soon as functional testing is complete

3. Automated tests may be run before or in parallel with manual tests

The project Test Plan has allocated 6 weeks to complete all test execution, with functional testing taking 3 weeks to execute, performance and security testing 2 weeks each and regression testing 1 week.

Which of the following options places the test suites (TS1 to TS5) in the correct order for test execution?

SELECT ONE OPTION

Options:

A.

TS3, TS1, TS2, TS5, TS4.

B.

TS1, TS2, TS5, TS3, TS4.

C.

TS3, TS4, TS1, TS2, TS5.

D.

TS5, TR1, TS3 TSA, TS2

Question 33

A car rental company offers discounts to its customers based on a number of factors, including booking history, length of membership and type of car being booked. An update to the rental application is under test, with test cases written that specifically address a documented product risk covering discount calculation. Although the risk impact was analysed as high, the likelihood was given as low, as there had been no known changes to the calculation rules. However, during test execution some discount calculations were incorrect and investigation showed that code changes had been made that impacted the discount algorithms. As a result, the likelihood was increased to high by the risk management team.

Which would be the BEST measure to take to respond to the current situation?

Options:

A.

Monitor the risk and adjust the risk register to reflect the changed risk level and any new risksdiscovered

B.

Update the test case coverage of the discount calculation risk to reflect the increased risk level

C.

Review the composition of the risk management team to ensure a better diversity of stakeholders

D.

Adopt a risk-based testing strategy to help mitigate failures in the rental application

Question 34

As test manager, you need to determine if there are likely to be new security risks arising from proposed changes to an in-house purchasing application. You invite a security testing consultant, who is external to the organisation, to assess the changes and provide you with their written report of perceived security risks.

Which risk identification technique are you using?

Options:

A.

Expert interview

B.

Risk workshop

C.

Brainstorming

D.

Independent assessment

Question 35

You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.

as

Given this information what should you conclude?

Options:

A.

More testing was needed before the production release because the defect detection percentage (DDP) was below 90%

B.

The cost of testing is high and could probably be lowered by spending more money on defect prevention

C.

The cost of testing is just right and is justified by the numbers

D.

More effort should be put on appraisal to help lower the cost of quality

Question 36

Which test process improvement model consists of five maturity levels?

Options:

A.

TMMi®

B.

TPI® NEXT

C.

GQM

D.

CMMi®

Question 37

You are a new lest manager in an organization You have been asked to assess the defect process to determine if there are any efficiency improvements that could be made that would reduce the cost of quality You have started digging through the defect Information What information would be most helpful for this investigation?

Options:

A.

Defect priorities and seventies as related to time from reporting to closure

B.

Areas of the software producing the most defects

C.

Risk areas m which defects have been detected and the

D.

relationship between the risk rating of the software and the seventy of the defect

E.

The phase in which a defect was introduced versus the phase in which it was found

Question 38

When Is the metric for the percentage of requirements coverage defined?

Options:

A.

Test planning

B.

Test monitoring

C.

Test execution

D.

Test completion

Question 39

There is a debate in your organization about who can close a defect report The developers think they should be able to reject and close defects without any further steps The testers are not happy with this approach as they are afraid the rejections may go undetected and the developers may close something without understanding the real problem

How can this problem be rectified7

Options:

A.

Only testers should be allowed to close defect reports

B.

Only management should be allowed to close defect reports

C.

No one should close a defect report until the release is completed and the product is successfully deployed to production

D.

Closure should only occur when a defect is fixed and tested

Question 40

What is the purpose of the defect management committee?

Options:

A.

To control the flow of defect reports into the system

B.

To validate defect reports and determine fix plans

C.

To implement strict guidelines for defect report creation

D.

To ensure the developers fix all defects

Question 41

You are managing the test team that is testing a new mobile application that provides a "step-by-step' hiking guide Your risk assessment resulted in the following table:

as

Your team has clone the depth and breadth testing for the GPS accuracy and usability features but when the product was given to beta testers there were some issues Despite the users reporting the app was easy to use at least one user walked off the edge of a cliff and another one ended up in a river. Your team has confirmed that the functionality is working correctly. and the GPS information is accurate.

What other area of testing should you now prioritize?

Options:

A.

Usability

B.

Functionality

C.

Performance

D.

Security

Question 42

You are working for an outsource testing company You have a client that will only consider candidates that are highly skilled with Salesforce. regardless of the number of years they have spent testing similar products You have looked through your skills matrix and you have no one with the right type of experience for this project.

What competence area is your team lacking?

Options:

A.

Social competence because they are lacking the ability to work with the rest of the team

B.

Personal competence because they are not confident enough to pass the interviews with the clientand they are not willing to learn Salesforce

C.

Methodical competence because they lack the ability to create test cases from a Salesforce requirements document

D.

Professional competence because they do not have the required domain knowledge in Salesforce

Question 43

At what testing level do the test management activities Include coordinating with end users7

Options:

A.

Component testing

B.

Component Integration testing

C.

System testing

D.

Acceptance testing

Question 44

Which of the following Is the common set of information to be produced in a test estimate''

Options:

A.

Number of people number of systems lines of code, cost

B.

Time per person budget end date start date

C.

Test effort test duration time to complete, cost

D.

Effort time cost, test activities

Question 45

In what environment are you most likely to see multiple defect management systems used in one project?

Options:

A.

Sequential

B.

Agile

C.

Hybrid

D.

Multi-tenant

Question 46

Which of the Mowing Is commonly used by a test manager to identity risks'

Options:

A.

Lines of code in the system under test

B.

Function points within the software

C.

Experience with similar projects

D.

Record/playback test automation tools

Question 47

You have been looking at the actual vs expected defects in one high risk area of the software The actual is much higher than the expected value What should you do?

Options:

A.

Reassess the risk with a higher likelihood number

B.

Reassess the risk with a higher impact number

C.

Concentrate more testing in the area because the risk is clearly higher

D.

Concentrate less testing in the area because the defects are already found

Question 48

Which of the following defect statistics will provide input to be used for improvement in the defect reporting process?

Options:

A.

Number of defect reports re-opened

B.

Number of defects in a particular area of the code

C.

Number of defect reports rejected by the developers

D.

Number of defects found in a phase later than they were introduced

Question 49

Which of the following Is a way in which risk analysis drives test analysis?

Options:

A.

It determines which tests should be executed first

B.

It guides the selection of test conditions that must be covered by testing

C.

It influences the type of reporting that will be used during execution

D.

it drives root cause analysis for any defects found

Question 50

Your team has been assigned to a new project You have a mix of manual testers and automation engineers but everyone is currently doing manual testing. The development learn has alreadydecided to use DevOps as its approach but they have never used it before and are happy to take your input Unfortunately, about 50% of the development is completed already In the testing your team is doing they are finding that about 40% of the defects they catch are actually regressions caused by other changes

Given this information what should you do to help mitigate risk'?

Options:

A.

Review the policies regarding defect reporting and ensure your team is adding all the necessary information to each defect report

B.

Pivot part of the team from manual testing to test automation development to address the regression risk and implement better quality gates to reduce regressions

C.

Optimize the test environment to provide faster testing with more accurate test data and better testing tools to provide wider coverage

D.

Implement code reviews for the development team and require tester signoff before code can be released into the pipeline

Question 51

You have decided to help your team improve their skills. One of their assignments is to mentor a junior member of the team Which competency should you expect the mentor to develop during this exercise?

Options:

A.

Social

B.

Professional

C.

Methodological

D.

Biological

Question 52

Which of the following is the proper order for the stages of a tool lifecycle?

Options:

A.

Acquisition Support Evolution Retirement

B.

Acquisition Evolution Support Retirement

C.

Evolution Acquisition Retirement Support

D.

Evolution Support Acquisition Retirement

Question 53

Your team has been given the following test objective Ensure that the users are happier with this version than they were with the last version?

What is wrong with the way this is defined?

Options:

A.

It is unlikely that just a version change will make users happier so this is not achievable

B.

It cannot be measured because happier' is subjective

C.

It does not define a timeframe

D.

It is not aligned with the organization's objectives

Question 54

Your team has been working on an Agile project for two months. There is a retrospective at the endof each sprint One of the data items reviewed is how many defects are being caught by users rather than by testers. The test team is being blamed for these escapes

What do you need to do to make these sessions more productive?

Options:

A.

You should attend the retrospective instead of the individual testers

B.

You should do root cause analysis to prove the developers are responsible

C.

You should gather metrics to present to the team regarding all the hours spent testing

D.

You should help the team brainstorm ideas on how to improve the testing to eliminate the escapes

Question 55

You have been assigned t o a project that has a very tight schedule. In fact, given your first analysis you do not think the planned test execution can be completed within the schedule There is no time allowed for defect fixing or for repeating tests. Regression testing has been left out of the planning entirely There is no time to develop test automation. The team has agreed that this Is not the way to run a project, yet they are stuck with the current schedule

Given this information what is the best way to proceed with the testing to try to meet the deadline with the best outcome1?

Options:

A.

Review the personnel plan and get more resources onto the test team

B.

Continue with the current plan but highlight to the project manager that either the deadline will be missed or the testing will not be done

C.

Develop a test automation plan so that automation can be started now

D.

Conduct a quality risk analysis and prioritize the testing based on risk so the highest risk items are tested first

Question 56

You are looking to Improve the efficiency of testing. The developers have been claiming that the majority of defect reports they receive are invalid either due to the test environment or because the tester did not follow the right steps In a standard defect management process where should you look for more information about these invalid defects?

Options:

A.

In the ones that are stuck in the In Progress state

B.

In the ones that are Resolved but not Closed

C.

In the ones that are in the status Rejected or Closed without a fix

D.

In the ones with the status of Re-Opened

Question 57

You have been asked to make a recommendation on deployment readiness on the software your team has been testing.You have the following metrics:

as

Given this information what is a critical metric you are missing?

Options:

A.

Number of tests passed

B.

Number of defects outstanding

C.

Residual risk

D.

Planned vs actual cost of testing

Question 58

Which of the following is required to apply an experience-based testing approach''

Options:

A.

Detailed requirements

B.

Usage models

C.

Tester knowledge of the system and its usage

D.

A full risk-assessment to support risk prioritization

Question 59

Your manager has decided that your team of manual testers should all become test automation engineers Your team is much stronger in analysis than In technical testing so you are concerned about their ability to adapt. What tool capabilities could help with this transition?

Options:

A.

Low license costs

B.

Remote storage of the test automation scripts

C.

High usability with Al-assisted object capture

D.

Good reporting

Question 60

Your team has been assigned to test a loyalty card program for a supermarket chain. Because this is a highly competitive market significant investment has been made to determine the shortcomings of the products offered by competitors While the feature sets are mostly the same, there is a wide variance In usability and performance and the users perceptions of these quality characteristics

Given only this information what test approach would be most appropriate?

Options:

A.

Model-based

B.

Experience-based

C.

Risk-based

D.

Requirements-based

Question 61

In what way is the operations team usually Involved In testing7

Options:

A.

To conduct operational acceptance testing

B.

To conduct user acceptance testing

C.

To conduct security testing

D.

To conduct end-to-end transactional testing

Question 62

You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?

Options:

A.

Wideband defphi

B.

Planning poker

C.

Three-point estimation

D.

Extrapolation

Question 63

You are working on a project where the business part of the organization works traditionally with defined requirements, but the development team follows an Agile model Neither team plans to change their approach What is the proper name for this type of project approach''

Options:

A.

Sequential

B.

Hybrid as a transition to Agile

C.

Agile

D.

Hybrid as fit for purpose

Question 64

Which of the following best describes the appraisal costs in the cost of quality'

Options:

A.

The cost spent preventing defects from occurring in the first place

B.

The cost for performing dynamic testing

C.

The cost for fixing defects

D.

The cost for lawyers to deal with a lawsuit over a defect

Question 65

Your organization has decided to augment your testing team with an offshore team. The offshore team members are experienced testers who are experts in the domain of the system under test Your team is worried about the offshore team taking their jobs and they are resistant to the change You need to pick three of your team members to be the ambassadors for the new team

Which competences will be most important for your ambassadors to possess?

Options:

A.

Professional competence and methodological competence

B.

Methodological competence and social competence

C.

Social competence and personal competence

D.

Personal competence and professional competence

Question 66

You are working In an environment that is continually pushing process improvements down to the lest team You are skeptical that any of these have actually accomplished any improvement In fact you know that some of the changes have actually impaired progress

Given this information what step of the IDEAL model is missing?

Options:

A.

Diagnosing

B.

Establishing

C.

Acting

D.

Learning

Question 67

In an Agile project, when Is it acceptable lo not write a formal defect report when a defect is found''

Options:

A.

Never

B.

If the defect can be fixed in the same iteration in which it was found

C.

the defect can be fixed in a later hardening sprint

D.

If the defect must be fixed by another team

Question 68

Which of the following Is considered a heavyweight risk-based testing technique'

Options:

A.

Systematic software testing

B.

Pragmatic risk analysts

C.

Brainstorming

D.

Hazard analysis