Question 1

Which two statements are true about the borrowed and lent cross charge method? (Choose two.)

Options:

A.

Internal Invoice is not generated with this method.

B.

This method allows you to process cross charge transactions across legal entities.

C.

This method creates accounting entries that move an amount equal to the transfer price between the provider and receiver organizations

D.

You must set up a contract business unit to use this method.

Question 2

Your company creates a separate project for infrastructure services, so as to track these costs separately and then allocate to various projects that use the services of the infrastructure team. You want to allocate these costs by first attributing a fixed percentage of the source amount to each project and then spread it across tasks based on the actual labor hours charged to each task.

Which allocation basis method would you use to meet this requirement? (Choose the best answer.)

Options:

A.

spread evenly

B.

target percentage and prorate

C.

target percentage and spread evenly

D.

prorate

Question 3

Which five steps are required for the File-Based Data Import Integration option?

Options:

A.

Run Process to transfer data to interface tables.

B.

Install an Excel add-in.

C.

Upload the file to the server.

D.

Download an Excel template.

E.

Populate the spreadsheet with data and generate a CSV file.

F.

Import data into various applications.

G.

Validate the sheet using the Validate option.

Question 4

In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)

Options:

A.

common costs on the project/task

B.

expenditure type exclusions on the Capitalized Interest rate name

C.

expenditure type exclusions on the Capitalized Interest rate schedules

D.

expenditure items whose cost spreads across multiple assets that are capitalized

E.

expenditure items whose costs are applied to a single asset or multiple assets

Question 5

Identify three purposes for which the project resource search index is used. (Choose three.)

Options:

A.

Display resource details

B.

Filter counts while you search for resources

C.

Calculate Resource Qualification Scores

D.

Provide absence details for resources

E.

Calculate Resources Availability Scores

Question 6

Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

Options:

A.

Effort

B.

Cost

C.

Manual Entry

D.

Remaining Plan

Question 7

Which three are part of using the Rapid Implementation for Project Financial Management Applications macro-enabled Microsoft Excel spreadsheet to enter setup data?

Options:

A.

Prepare setup data.

B.

Import Projects.

C.

Generate CSV files.

D.

Upload setup data.

E.

File Import and Export.

Question 8

Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.

Identify the correct statement about the RBS and new resources. (Choose the best answer.)

Options:

A.

If the “Allow resource changes at project level” option is set to No, the new resources and resource formats that are added to a Planning Resource Breakdown Structure for one project are not available for other projects.

B.

If the “Allow resource changes at project level” option is set to No for the RBS, then the resources added to the Planning Resource Breakdown Structure are automatically available for use on the projects.

C.

If the “Allow resource changes at project level” option is set to Yes for the RBS, the new resources are available automatically at project level.

D.

If the “Allow resource changes at project level” option is enabled for the RBS, the new resources added at project level are automatically reflected in the RBS.

Question 9

Which two statements describe how the Resource Qualification Score is calculated?

Options:

A.

An individual's score is 100% if the resource request has a qualification with a specified proficiency and the resource does not have the qualification.

B.

An individual's score is 100% if the resource request has a qualification, but no proficiency is specified, and the resource has the qualification.

C.

An individual's score is 100% if the resource request has a qualification with a specified proficiency and the resource has the qualification that meets the specified proficiency.

D.

An individual's score is 100% if the resource request has a qualification with a specified proficiency and the resource has the qualification with a proficiency that is lower or higher than specified.

Question 10

Select two correct statements about project classifications on a template. (Choose two.)

Options:

A.

Set Code is not required for a project class category in a project classification.

B.

Project Classification is a mandatory field on a project template.

C.

When a project is created from a template, the required project classifications must be entered.

D.

Project class category in a project classification must be associated with a Set Code.

Question 11

You are now the project manager of a newly created implementation project. Which two items are not part of managing an implementation project?

Options:

A.

Assign tasks to various users who are responsible for managing setup data.

B.

Monitor the progress of completing setup tasks.

C.

Select the offering you want to implement.

D.

Generate a list of setup tasks.

E.

Enable optional functional areas and features by opting in.

Question 12

Using Oracle Time and Labor, your client wants to put in a validation process that allows only a certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week.

What feature would you use to meet this requirement? (Choose the best answer.)

Options:

A.

project time validation rules

B.

time calculation rules

C.

time entry rules

D.

time audit rules

Question 13

Which three are valid password complexity criteria while setting up password policies? (Choose three.)

Options:

A.

Complex: At least 8 characters, 1 uppercase, and 1 number

B.

Very Complex: At least 8 characters, 1 uppercase, 1 number, and 2 special characters

C.

Very Complex: At least 6 characters, 1 uppercase, 1 number, and 1 special character

D.

Very Complex: At least 8 characters, 1 uppercase, 1 number, and 1 special character

E.

Simple: At least 8 characters and 1 number

Question 14

Your customer has a requirement to allow adjustment and reversals for transactions imported from an external expense entry system.

Which section on the Manage Project Transaction Sources page will allow you to enable these options?

Options:

A.

Documents

B.

Transaction Source

C.

Document Entries

D.

Transaction Entries

Question 15

You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project: Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)

Options:

A.

A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.

B.

The association of a deliverable with a task is dependent on associating a requirement with a task.

C.

A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.

D.

You associate a deliverable with a task, independent of associating a requirement with a task.

Question 16

Which two statements are true about the cross-charge method, Borrowed and Lent?

Options:

A.

This method creates accounting entries that move an amount equal to the transfer price between the provider and receiver organizations within a legal entity.

B.

Costs or revenue are shared based on transfer price rules with this method.

C.

You must set up the contract business unit to use this method.

D.

This method creates a formal internal invoice.

Question 17

Green House Corporation has decided to enable the budgetary control feature for their projects. At which two levels will they be able to enter the amounts in the budget versions for these projects?

(Choose two.)

Options:

A.

Expenditure Type

B.

Task

C.

Top resource

D.

Expenditure Category

E.

Project

Question 18

Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)

Options:

A.

Cascade change to the start date.

B.

Do not cascade date changes.

C.

Cascade change to the finish date.

D.

Cascade change to the start date and the finish date.

Page: 1 / 13