Question 1

A global company is subject to differing regulations regarding hazardous materials in a product. Version 1 of the product can be sold in North America and Europe. Version 2 of the product can only be sold in Europe.

Which sequence of setups could help a planner ensure that supply is available in a timely fashion per these constraints?

Options:

A.

Create an attribute-based netting rule using region and version; map the rule to collectible attributes; associate the rule to a supply plan; run the plan.

B.

Define region and version as planning attributes; map them to collectible attributes; create an attribute-based netting rule using region and version; associate the rule to a supply plan; run the plan.

C.

Define region and version as planning attributes; create an attribute-based netting rule using region and version; associate the rule to a supply plan; run the plan.

D.

Define segment groups based on region and version; execute segmentation; map the segmentation results to an attribute-based netting rule; associate the rule to a supply plan; run the plan.

Question 2

Which option outlines changes you can make a simulation plan when evaluating demand and supply?

Options:

A.

Add demands, cancel demands, reschedule demands, add new planned orders, reschedule supplies

B.

Change item specification values, change item lead times, create mass changes for items

C.

Change item specification values, change item lead times, create mass changes for items all at once, change item-organization specification values

D.

Add demands, cancel demands, reschedule demands, and supply, cancel supply, reschedule supplies

E.

Change item specification values, change item lead times, change item-organization specification values

Question 3

During an implementation, customer is in the process of planning supply requirements. Customer also needs to generate forecast and safety stock levels. Which plan type on the plan options should the customer be running?

Options:

A.

Demand and Supply Plan

B.

Safety Stock and Forecast Plan

C.

Demand Plan

D.

Supply Plan

E.

Integrated Plan

Question 4

You are in Implementation project and your customer is a global company with a complex supply chain network. Planners work across different geographies and different line of products. Each planner works with their own set of data and analysis and dashboards.

How do you configure the application so each planner can have their own custom dashboard view-able only to themselves?

Options:

A.

Create public page layouts that are tailored to specific business needs.

B.

You cannot create custom dashboards by user.

C.

Enable layout security checkbox in the Administer Planning Security.

D.

Create private page layouts that are tailored to specific business needs.

Question 5

As a new planner, you want to test simulation set functionality. You have created a simulation set named 'Test Simulation Set.' In this simulation set, you have already added Item 98573. You would like to change the item specification 'Fixed Order Quantity' to 10 within this simulation set.

Which sequence will allow you to accomplish this task?

Options:

A.

Select and open 'Test Simulation Set' > Search and select Item 98573 > Highlight item > Select 'Action' > Select 'Edit' > Find Fixed Order Quantity specification> under the 'Action' column select 'set value as' > under the 'Value' column enter 10

B.

Select and open 'Test Simulation Set' > Search and select Item 98573 > Highlight item > Select 'View' > Select 'Columns' > Check box next to Fixed Order Quantity specification> the 'Fixed Order Quantity' will now show on the Item 98573 line > Highlight line for Item 98573 and scroll right until you find 'Fixed Order Quantity' > Change value to 10

C.

Select and open 'Test Simulation Set' > Search and select Item 98573 > Highlight item > Select 'Action' > Select 'Edit' > Find Fixed Order Quantity specification> under the 'Action' column select 'reset to original' > under the 'Value' column enter 10

D.

Select and open 'Test Simulation Set' > Search and select Item 98573 > Highlight line for Item 98573 and scroll right until you find 'Fixed Order Quantity' > Change value to 10

Question 6

Your current shipments forecast for Jan 2018 is 1000 and the demand planner determines that the forecast should be 1500. Describe how the demand planner can override shipments forecast. Also, what happens to the final shipments forecast measure when the demand plan is run again and the shipments forecast value changes to 1250?

Options:

A.

Open a table with the Adjusted Shipments Forecast measure and enter 1500. The Final Shipments Forecast measure will change to 1500 and the value will persist during subsequent demand plan runs.

B.

Open a table with the Shipments Forecast measure and override it to 1500. The Final Shipments Forecast measure will change to 1500 and the value will persist during subsequent demand plan runs.

C.

Open a table with the Shipments Forecast measure and override it to 1500. The Final Shipments Forecast measure will change to 1500. During the subsequent demand plan run, the Final Shipments Forecast value will change to 1250.

D.

Open a table with the Adjusted Shipments Forecast measure and enter 1500. The Final Shipments Forecast measure will change to 1500. During the subsequent demand plan run, the Final Shipments Forecast value will change to 1250.

Question 7

A customer has created a supply plan based on current requirement. Due to changes in third party forecast, the plan must be rerun with these recent updates. However, while this new information became available, existing supply like on-hand inventory and work order completions have also been updated.

Which data refresh option should be used to reflect all these changes in the plan?

Options:

A.

Do not refresh with current data

B.

Refresh with quick refresh option

C.

Refresh with forecast data

D.

Refresh with selected current data

E.

Refresh with current data

Question 8

Which four actions does Demand Management enable you to do? (Choose four.)

Options:

A.

Run an unlimited number of forecast simulations to see impacts of changes in the price, running a marketing campaign, shift in weather, demand upside request, and so on.

B.

Simulate changes to the dependent options forecast for build to stock items.

C.

Perform side-by-side analysis on a multiple number of scenarios, and see the impact on operational and financial objectives.

D.

Simulate how changes to forecasting models and parameters have an immediate impact on the statistical forecast.

E.

Simulate the impact of introducing new products in particular geographic areas.

Question 9

When creating a new replenishment plan, what are the required plan options?

Options:

A.

Segment Group. Segments. Policy Assignment Set

B.

Segment Group. Inventory Policies. Policy Assignment Set

C.

Segment Group. Segments. Inventory Policies

D.

Segment Group. Segments. Inventory Policies. Policy Assignment Set

Question 10

Which two statements are true about the seeded (predefined) Contract Manufacturing roles? (Choose two.)

Options:

A.

Users with the Supply Chain Operations Manager role can access the Supply Chain Collaboration work area.

B.

Users with the Contract Manufacturer role can access the Supplier Portal to upload their production updates.

C.

Users with the Supplier Inventory Manager role don't need access to the Supplier Portal because they already have access to the Supply Chain Collaboration work area.

D.

Users with the Supply Chain Operations Manager role need access to the Supplier Portal to see their updates and what's in progress.

E.

Users with the Supplier Inventory Manager role can access the Supplier Portal.

Question 11

You are a demand planner and you want to generate forecast for all laptop and desktop products in the US business unit. You are using standard enterprise and product hierarchy. You have created a demand plan and now you must define plan scope.

Identify three valid steps. (Choose three.)

Options:

A.

For plan parameters, select forecasting calendar as Gregorian and time level as week.

B.

For forecasting items, select hierarchy as product, level as category level 1, and laptop and desktop categories as level members.

C.

For plan parameters, select forecasting calendar as Gregorian and time level as month.

D.

For plan organizations, select hierarchy as enterprise, level as country, and US as level member.

E.

For forecasting items, select hierarchy as product, level as product, and all laptop and desktop products as level members.

F.

For plan organizations, select hierarchy as enterprise, level as business unit, and US and level member.

Question 12

In which situation would Bills of Distribution be more effective than Sourcing Rules?

Options:

A.

When Organization A, Organization B, and Organization C make their own products

B.

When Organization A buys from a Supplier; Organization B transfers from Organization A, and Organization C transfers from Organization B

C.

When all organizations transfer 50% of the material from Organization B, and 50% from Organization C

D.

When all organizations are buying from a single outside supplier

E.

When Organization A, Organization B, and Organization C transfer from Organization C

Question 13

Which KPIs are available to measure forecasting accuracy and specify how these measures aggregated from item-organization level to higher levels.

Options:

A.

MAPE, MAD, and Bias are used to measure forecast accuracy. MAD and Bias are aggregated using sum. MAPE is aggregated using weighted average.

B.

MAPE, MAD, and Bias are used to measure forecast accuracy. MAPE and Bias are aggregated using weighted average. MAD is aggregated using sum.

C.

MAPE, MFE, and Bias are used to measure forecast accuracy. MAPE and Bias are aggregated using weighted average. MFE is aggregated using sum.

D.

MAPE, MFE, and Bias are used to measure forecast accuracy. MAPE and MFE are aggregated using weighted average. Bias is aggregated using sum.

Question 14

During implementation, the customer would like to use safety stock planning parameters. However, they would like to uncheck "Safety stock change interval to all items." What will the results be if they choose to uncheck this parameter?

Options:

A.

Safety stock will not be calculated at all for this plan.

B.

This option will require a min/max quantity for this parameter even though it will not be used.

C.

Safety stock will use a smoothing method to calculate the safety stock within change interval to determine the level of safety stock needed without this parameter.

D.

Safety stock change interval will only apply to items with Days of Cover safety stock method.

Question 15

What happens when a demand planner approves a demand plan and then adjusts shipment history and runs demand plan again?

Options:

A.

The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. After a forecast is approved, the approved values remain unchanged until the forecast is approved again.

B.

The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures "not editable." After a forecast is approved, the Final Shipments Forecast and Final Bookings Forecast measures remain unchanged until the forecast is approved again.

C.

The approve action makes the Adjusted Shipments Forecast and Adjusted Bookings Forecast measures "not editable." But any subsequent demand plan run can change Final Shipments Forecast and Final Bookings Forecast values.

D.

The approve action takes the data from the two final forecast measures and copies to Approved Final Shipments Forecast and Approved Final Bookings Forecast, respectively. Any subsequent demand plan run can change final shipments or bookings forecast values that will automatically update the approved forecast measures.

Question 16

You have executed Planning Data Collection and want to confirm that data has successfully been collected. Identify the three data combinations that can be viewed using the Maintain Supply Network Model Page. (Choose three.)

Options:

A.

Customer Location and Carriers

B.

Safety Stock and Subinventories

C.

Sales Channel and Demand Class

D.

Calendar and Master Organization

E.

Supplier Site and Service Level

Question 17

You ran a demand plan and you are reviewing the shipments forecast value measure. It is always zero for a particular item. Identify the root cause of this problem.

Options:

A.

In planning measures catalog, shipment forecast value measure is not enabled at item and organization level.

B.

In plan parameters, Item List Price marked as primary does not have price defined for the particular item.

C.

In plan parameters, shipment forecast value measure expression is not defined.

D.

In planning measures catalog, shipment forecast measure is not enabled at item and organization level.

Question 18

You are defining material planners for your organization. However, when you go to Manage Material Planners, your organization does not appear in the list of values. Why?

Options:

A.

The organization was not enabled for collection under Manage Planning Source Systems.

B.

The organization must be enabled in Manage Planning Parameters.

C.

The organization is an Item Organization.

D.

The organization must be enabled in Manage Planning Profile Options.

E.

You do not have data access to the organization.

Question 19

The marketing department of a company needs to analyze the forecast based on type of demand (large retailer versus specialty store) and item cost (low versus high).

After creating a segment group with demand class and product for segment granularity, what additional sequence of actions must they also perform to satisfy marketing?

Options:

A.

Define four segments based on demand type and item cost, define each segment's criteria, execute segmentation, and use the selector tool to create a new table or graph.

B.

Define four segmentation based on demand type and item cost, define each segment's criteria, execute segmentation, configure planning analytics to update the dimension catalog, and use the selector tool to create a new table or graph.

C.

Define four segments based on demand type and item cost, execute segmentation, and use the selector tool to create a new table or graph.

D.

Define two segments based on demand type and item cost, execute segmentation, and use the selector tool to create a new table or graph.

Question 20

Cost accounting captures costed transactions that are picked up by the cost processor. Which is not picked up by the cost processor?

Options:

A.

invoices and revenue interfaced from Cloud Receivables

B.

supplier invoices interfaced from Cloud Payables

C.

shipping, receiving, and inventory transactions from manufacturing

D.

period close adjusting journal entries for Payroll

Question 21

Which set of transaction types data are uploaded in Contract Manufacturing Collaboration?

Options:

A.

Work-order Completions

B.

Component Material Issues, Work-order Completions

C.

Component Material Issues, Work-order Completions, Shipment Confirmations

D.

Planned orders, Planned Order Commits

Question 22

Your client has a requirement to restrict Supply Plan data access. Identify three Data Access Set detail entities that can be used to restrict plan data access. (Choose three.)

Options:

A.

Supplier

B.

Item

C.

Transaction Type

D.

Customer

E.

Material Planner

F.

Demand Class

Question 23

Which two statements are true when using Measure catalogs? (Choose two.)

Options:

A.

The predefined measure catalog is not the system default.

B.

The measure catalog has a collection of measures that you can enable for use in a single plan in the Planning Central work area.

C.

You can restrict access to Measure Catalogs using Administer Data Security.

D.

You can add or remove measures from a measure catalog.

E.

Measure catalogs are defined in the system to improve the performance of the plan.

F.

You navigate to Configure Measure Catalogs to edit the Catalog.

Question 24

Your clients want to simulate how canceling demand may impact a plan. Which two steps must be done to simulate this change? (Choose two.)

Options:

A.

Run plan with 'Do not refresh with current data'

B.

Manage Plans > Edit Plan Options > Add simulation set

C.

Open plan > View Supplies and Demands > Firm the demand and set firm quantity to 0 > Save changes

D.

Open plan > View Supplies and Demands > Remove the sales order from the plan and firm demand > Save changes

E.

Run plan with 'Refresh with current data'

Question 25

Which statement applies only to the planning of back-to-back items and not standard items?

Options:

A.

Planning analyzes supply shortages and capacity overloads using any of the standard planning tools.

B.

Must use Global Order Promising and Supply Chain Orchestration to release and create new supplies

C.

Must have added sourcing rules to the Global Order Promising assignment set.

D.

Planning pegs reserved supplies to sales orders.

E.

Planning collects bookings or shipments history to forecast items.

Question 26

Which release recommendation parameter can you utilize to govern the behavior of the auto-release process?

Options:

A.

Release Only by User

B.

Auto-Release Interval in Days

C.

Auto-Release Planned Order Time Fence

D.

Quick Release Time Fence

E.

Compression Days Tolerance for Automatic Release

Question 27

Which two statements regarding the Decomposition scheduled process are incorrect? (Choose two.)

Options:

A.

It does not recognize forecast exceptions.

B.

It reads published planning data from interface tables.

C.

It received supplier commits.

D.

It creates or updates an order forecast, used by Supply Chain Collaboration to publish to suppliers.

Question 28

Your client manufactures consumer electronics and has all facilities live on Oracle Cloud. Their latest product has a very complicated manufacturing process and therefore can only be made at one facility (Organization ABC). However, it is ordered all over the world.

How should the Sourcing Rule be set up to accomplish this?

Options:

A.

A global sourcing rule for 50% make at ABC and 50% buy from ABC

B.

A local sourcing rule for 100% make at ABC; a global sourcing rule for 100% transfer from ABC

C.

A local sourcing rule for 100% make at ABC; a global sourcing rule for 100% buy from ABC

D.

A local sourcing rule for 100% buy from ABC; a global sourcing rule for 100% transfer from ABC

E.

A global sourcing rule for 100% make at ABC; a local sourcing rule for 100% transfer from ABC

Question 29

Which three statements are true regarding exceptions? (Choose three.)

Options:

A.

The conditions under which exceptions are generated can be modified.

B.

You can act on an exception by selecting it and clicking 'Resolve exception'. A list of ways to resolve will be generated.

C.

The calculation logic for exceptions can be modified.

D.

You can drill down into Supplies and Demand from an exception line.

E.

You can export exception tables to Excel.

F.

You can create custom exceptions.

Question 30

Which feature is NOT available for Sales and Operations Planning plans?

Options:

A.

View Segmentation Summary

B.

Configure Exceptions

C.

Collect Planning Data

D.

Load Planning Data from Files

Question 31

Which is the proper fulfillment strategy to plan for supply using the appropriate lead times required for processing material at a third party, based on the manufacturing work definition?

Options:

A.

outside processing operations

B.

expense destination transfers

C.

contract manufacturing

D.

back-to-back orders

E.

drop shipments

Question 32

Which Statement is NOT correct regarding demand schedules when planning supply?

Options:

A.

A demand schedule can be another Demand Plan, a Sales & Operations Plan, or a Production Plan.

B.

A demand schedule's "End Item Demand" measure must be one of: Final Shipments Forecast, Final Bookings Forecast. Approved Final Shipments Forecast, or Approved Final Bookings Forecast.

C.

An integrated demand and supply plan can have more than one demand schedule.

D.

External forecast loaded from flat files can be a demand schedule.