Certified Associate in Project Management (CAPM) Questions and Answers
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
Which of the following is an input to the Perform Qualitative Risk Analysis process?
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
Which of the following is an example of schedule compression?
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
Monte Carlo is which type of risk analysis technique?
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
Which of the following correctly explains the term "progressive elaboration'?
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
When sequencing activities, what does the common acronym FF stand for?
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:
A tool or technique in Perform Quality Control that a project manager would use is:
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
Lessons learned documentation is gathered during which of the following Project Management Process Groups?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
Which process determines the risks that might affect the project?
In which process is a project manager identified and given the authority to apply resources to project activities?
Labor, materials, equipment, and supplies are examples of:
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?
The process of identifying the stakeholders' information needs is completed during:
Which cost estimate technique includes contingencies to account for cost uncertainty?
What is the primary benefit of meeting quality requirements?
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
Which is used to solicit proposals from prospective sellers?
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
Which of the following factors is lowest at the start of the project?
Which tool and technique is used in Conduct Procurements?
The key benefit of the Monitoring and Controlling Process Group is the ability to:
Analogous cost estimating relies on which of the following techniques?
Project contracts generally fall into which of the following three broad categories?
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
Tools and techniques used for Plan Communications include the communication:
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
Which of the following is an information gathering technique in Identify Risks?
Which is the correct formula for calculating expected activity cost for three-point estimating?
During which process would stakeholders provide formal acceptance of the completed project scope?
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
A method to manage stakeholder expectations in the scope statement is to clearly:
What is the most accurate rough order of magnitude (ROM)?
In which process might a project manager use risk reassessment as a tool and technique?
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?
Which of the following tools and techniques is used in the Verify Scope process?
Types of internal failure costs include:
Which technique helps to determine the risks that have the most potential impact on a project?
Which standard has interrelationships to other project management disciplines such as program management and portfolio management?
Which of the following reduces the probability of potential consequences of project risk events?
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
Which of the following is an input to the Direct and Manage Project Execution process?
A tool and technique used during the Perform Qualitative Risk Analysis process is:
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
In a project using agile methodology, who may perform the quality control activities?
The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.
What are these elements called?
Which set of activities should a project manager use as part of the Develop Team process?
In which of the Risk Management processes is the project charter used as an input?
Which role does the project manager resemble best?
Which of the following are processes associated with Project Cost Management?
Which are the main objectives of Project Risk Management?
The primary purpose of the stakeholder register is to:
Which tools and techniques will a project manager use to develop a project charter?
What does expert judgment provide as an input to the resource management plan?
The features and functions that characterize a result, product, or service can refer to:
A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
Responsible, accountable, consult and inform (RACI) is an example of which of the following?
Which tasks should a project manager accomplish in order to manage project scope correctly?
What is the purpose of the project schedule management.
Which are examples of processes that may be used once or at predefined points in the project life cycle?
A project manager is identifying the risks of a project. Which technique should the project manager use?
What tool or technique can improve a products final characteristics?
Which action should the project manager take after the team finishes executing the scope?
Which of the following describes the similarities of the process groups and project life cycle?
Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?
In an agile and adaptive project, which scope management entity invokes stakeholder engagement?
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?
Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?
A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?
What should a project manager use to determine how much money is needed to complete a project?
An important project stakeholder has low risk tolerance. Which type ot communication should a project manager use to provide this stakeholder with a difficult update?
During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project's components. What should be included in the WBS?
Project reporting is a tool that is most closely associated with which process?
What is a tailoring consideration in Project Integration Management?
Which of the following set of elements is part of an effective communications management plan?
Which of the following is used as an input to prepare a cost management plan?
Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?
What type of meeting is held to discuss prioritized product backlog items?
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.
Which process is the project manager executing?
In which organizational structure would the project manager have most authority?
The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?
Howls program success measured?
What is the difference between quality metrics and quality measurements?
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?
Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?
What is a tool or technique used in the Control Quality process?
What are the key tools for managing project knowledge?
Which tool should a project manager consider to deal with multiple sources of risk?
In which Project Cost Management process is work performance data included?
How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
What does an S-curve from a Monte Carlo analysis show?
A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?
A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?
During which process of Project Cost Management does a project manager produce the cost baseline?
Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?
When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.
What is main purpose of Project Quantity Management?
Which tool should a project manager use to calculate cost variance for a project?
Match the praxes manager's sphere of influence with the associated primary role:
What is the purpose of the Manage Quality process?
What important qualities should project managers possess for strategic and business management?
Which kind of communication should the project manager use when creating reports for government bodies?
Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?
What is the Project Schedule Management practice used to deliver incremental value to the customer'?
What specific quality considerations should be examined while completing Quality Management plan?
At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?
What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?
To ensure stakeholder satisfaction; identified stakeholder needs should all be
A practitioner organized a requirements workshop with the client's frontline application users. The users explained that one of the challenges of the current application is that they must click on each input before entering data, which happens thousands of times a day.
Which technique did the practitioner use to identify this pain point?
Which additional considerations should the project manager make when managing risks in an agile/adaptive project?
Which can be used to convert a verified deliverable to an accepted deliverable?
A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements. What should the business analyst do?
A project team is reviewing project performance. During the execution phase, the project team discovers that there is an off-the-shelf (OTS) product, which could reduce the timeline for development.
What should the project manager do next?
A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.
What should the project manager do to address this issue?
A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence. What should the project manager do first?
What do top project managers do to maximize their sphere of influence within a project team?
An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float. What is the likelihood the team will complete all 20 story points in the upcoming sprint?
What organizational process asset (OPA) might impact a project's outcome?
A project manager should consider the impact of project..............manager following
A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?
What is the main purpose of Project Quality Management?
A newly developed project team is working together, building trust and adjusting its work habits to support the team What stage of the Tuckman ladder does this describe?
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?
Two resources are performing a peer review of an artifact. What should be the outcome of the peer review?
An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning. Which two of the following items should be included in the planning? (Choose two)
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?
A business case is being assembled. Which two elements are necessary to complete this process? (Choose two)
Which of the following is used as input to prepare a cost management plan?
Which is the appropriate tool to identify the possible correlation two elements in aprocess?
A project manager is reviewing a past project with similar.... team choosing for tailoring?
A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?
What is a key benefit of using virtual project teams?
A project manager engages a highly specialized resource who is in a different location and cannot join the regular team meetings. This is leading to delays in productivity. How can the project manager assist the team to resolve the issue?
Select three processes that are associated with Project Schedule Management.
A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?
What internal enterprise environmental factor (EEF) can impact a project?
Two members of the team are having a conflict..............or partially resolve the problem
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.
Which technique should the project manager use?
What behavior refers to leadership style?
A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?
In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?
During the project life cycle for a major product, a stakeholder asked to add a new feature. Which document should they consult for guidance?
A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?
What type of stakeholder is part of a project manager 's sphere of influence on a project?
The project manager released a report A few stakeholders express the view that report should
have been directed to them
Which of the 5Cs of written communications does the project manager need to address?
A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?
Which of the following projects is a quality candidate for adaptive approaches?
Which three techniques can be estimate costs?
A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.
Which method should be used in this situation?
A project team is evaluating criteria to determine project viability. Which of these activities will provide insight into making a go/no-go decision to start the project?
A project manager is responsible for delivering new software for their company. Based on previous experiences, the project manager decides to use the dynamic systems development method (DSDM). The project manager will use this method to prioritize the scope to meet project constraints.
Which elements are included in the DSDM framework?
For what project management process is work performance information an output?
Match the process with its corresponding process group.
A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?
An adaptive team's velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project. How should the project manager calculate the anticipated velocity for future sprints?
During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis.
What is this an example of?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
Which quality control technique illustrates the 80/20 principle?
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
When cost variance is negative and schedule variance is positive, the project is:
Which of the following is an output of Close Procurements?
Which is one of the determining factors used to calculate CPI?
During project selection, which factor is most important?
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
Which statement is true about the project management body of knowledge?
Risk exists the moment that a project is:
Which technique is utilized in the Control Schedule process?
One of the objectives of a quality audit is to:
Projects are separated into phases or subprojects; these phases include:
The cost benefit analysis tool is used for creating:
After Define Activities and Sequence Activities, the next process is:
Which of the following is an output of Define Scope?
Who is responsible for initiating a project?
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
The initial development of a Project Scope Management plan uses which technique?
Which activity may occur at project or phase closure?
Which of the following is a project constraint?
Which of the following is a tool and technique used to monitor risk?
Which of the following is an input to the Develop Project Charter process?
Which of the following change requests can bring expected future performance of the project work in line with the project management plan?
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
In the basic communication model, which term refers to the method that is used to convey the message?
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
Inputs to the Plan Risk Management process include the:
The process for performing variance analysis may vary, depending on:
Exhibit A is an example of which of the following types of Sequence Activities?
Which baselines make up the performance measurement baseline?
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
Which of the following is an input to Direct and Manage Project Execution?
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
An input to the Estimate Activity Resources process is:
Which risk response strategy is common for both positive and negative risks?
Which of the following is a strategy to deal with positive risks or opportunities?
Administer Procurements is part of which Process Group?
Which of the following response strategies are appropriate for negative risks or threats?
The correct equation for schedule variance (SV) is earned value:
Which statement correctly describes the value of a business case?
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
The three processes of Project Cost Management are:
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
Activity cost estimates are quantitative assessments of the probable costs required to:
Which is an output of the Collect Requirements process?
Which input will be used when tasked with developing the human resource plan?
A tool and technique used during the Define Scope process is:
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
Which process requires implementation of approved changes?
What happens to a stakeholder's project influence over time?
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
Which type of managers do composite organizations involve?
Which tool is used to develop technical details within the project management plan?
Assigned risk ratings are based upon:
Which of the following statements correctly characterizes pull communication?
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
During which process group is the quality policy determined?
Cost baseline is an output of which of the following processes?
Outputs of the Control Communications process include:
The individual or group that provides resources and support for a project and is accountable for success is the:
Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
Which is an example of Administer Procurements?
Portfolio Management is management of:
Which tools or techniques will a project manager use for Develop Project Team?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
Which action should a project manager take to ensure that the project management plan is effective and current?
Which of the following investigates the likelihood that each specific risk will occur?
When can pre-assignment of project team members occur?
An input required in Define Scope is an organizational:
Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?
To which process is work performance information an input?
The stakeholder register is an output of:
Information collected on the status of project activities being performed to accomplish the project work is known as what?
The project management processes presented in the PMBOK Guide® should:
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
Which of the following techniques is used during Control Scope?
What is the number of stakeholders, if the project has 28 potential communication channels?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
Which process is included in the Project Integration Management Knowledge Area?
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
Who selects the appropriate processes for a project?
An input of the Control Schedule process is the:
Taking out insurance in relation to risk management is called what?
Which technique is used in Perform Quantitative Risk Analysis?
In an organization with a projectized organizational structure, who controls the project budget?
Which of the following is an input to Direct and Manage Project Execution?
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
What cost control technique is used to compare actual project performance to planned or expected performance?
The process of formalizing acceptance of the completed project deliverables is known as:
What type of project structure is a hierarchically organized depiction of the resources by type?
When is a Salience Model used?
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
Which of the following involves making information available to project stakeholders in a timely manner?
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
Which schedule network analysis technique modifies the project schedule to account for limited resources?
Most experienced project managers know that:
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?
What is the total float of the critical path?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
An input used in developing the communications management plan is:
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
In which Knowledge Area is the project charter developed?
An output of the Manage Stakeholder Engagement process is:
A tool or technique used in the Control Procurements process is:
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
Market conditions and published commercial information are examples of which input to the Estimate Costs process?
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
Lessons learned are created and project resources are released in which Process Group?
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
In the Plan Stakeholder Management process, expert judgment is used to:
The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:
Which Knowledge Areas include processes from the Closing Process Group?
Scope, schedule, and cost parameters are integrated in the:
Which tool or technique is used to manage change requests and the resulting decisions?
An input to the Plan Procurement Management process is:
Which tools or techniques are used in the Plan Schedule Management process?
Which input to the Plan Risk Management process provides information on high-level risks?
Which item is an example of personnel assessment?
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
Which grid shows which resources are tied to work packages?
The Monitoring and Controlling Process Group includes processes that:
Sensitivity analysis is typically displayed as a/an:
The number of potential communication channels for a project with 5 stakeholders is:
In a project, total float measures the:
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?
Which item is an input to the Define Activities process?
Which item is a formal proposal to modify any document, deliverable, or baseline?
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
Organizational theory is a tool used in which Project Human Resource Management process?
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
When should quality planning be performed?
Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
An output of the Create WBS process is:
Identify Risks is part of which Process Group?
Which cost is associated with nonconformance?
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Reserve analysis is a tool and technique used in which process?
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
When does the project team determine which dependencies are discretionary?
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
Which tool or technique is used in the Perform Integrated Change Control process?
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
The process of prioritizing risks for further analysis or action is known as:
Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
Risk categorization is a tool or technique used in which process?
Which tool or technique is used in the Develop Project Management Plan process?
An input to the Identify Stakeholders process is:
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
A disadvantage associated with virtual teams is that they:
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
The following is a network diagram for a project.
The shortest non-critical path for the project is how many days in duration?
The following is a network diagram for a project.
The free float for Activity E is how many days?
An output of the Perform Integrated Change Control process is:
A tool and technique used in the Develop Project Charter process is:
A graphic display of project team members and their reporting relationships is known as a:
The purpose of developing a project scope management plan is to:
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
The zero duration of milestones in project planning occurs because milestones:
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
The purpose of the Project Communications Management Knowledge Area is to:
The following is a network diagram for a project.
The free float for Activity H is how many days?
Which is an enterprise environmental factor?
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
The component of the risk management plan that documents how risk activities will be recorded is called:
Which Manage Communications tool or technique focuses on identifying and managing barriers?
Outputs of the Control Communications process include:
Analytical techniques are a tool and technique of which process in Project Procurement Management?
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?
Which items are an output of the Perform Integrated Change Control process?
An intentional activity to modify a nonconforming product or product component is called:
The process of defining how the project scope will be validated and controlled is known as:
Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?
In complex projects/ initiating processes should be completed:
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
Progressively elaborating high-level information into detailed plans is performed by the:
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
For a stakeholder with low interest and high power, the project manager should:
Which term describes an assessment of correctness?
The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
Requirements documentation will typically contain at least:
A project manager should communicate to stakeholders about resolved project issues by updating the:
When closing a project or phase, part of the process may require the use of which type of analysis?
Project Stakeholder Management focuses on:
Which type of organizational structure is displayed in the diagram provided?
Whose approval may be required for change requests after change control board (CCB) approval?
High-level project risks are included in which document?
Which item is a cost of conformance?
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
The scope management plan and scope baseline are contained in:
In the Define Activities process, the schedule management plan is used to:
The following is a network diagram for a project.
What is the critical path for the project?
The following is a network diagram for a project.
The critical path for the project is how many days in duration?
A risk that arises as a direct result of implementing a risk response is called a:
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Specification of both the deliverables and the processes is the focus of: