PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers
A software project is being implemented by a small, colocated team. What should the project manager do to keep the team focused and engaged with the high level of requirements?
An agile project was underway for two months and delivered the expected value to the stakeholders. However, during a sprint review, a team member complained that the product owner constantly changes requirements and the member feels that this is blocking the team’s performance.
How can the scrum master handle this situation?
The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.
What must the agile practitioner do?
What should be done with this story?
What can an agile team use to prioritize stories?
A customer has given a project team several requests for new features on a product. The customer is upset that the requests have been placed in the backlog and are not currently being worked on by the team.
What should the team do next?
What should the Scrum Master do next?
A team is building a product in three-week iterations. During the last retrospective, it was identified that there was a 20% increase from previous iterations in the number of reported defects and change requests.
Since this is causing the product's value to decrease, what should the team do?
What is a specific development practice that has been effective in implementing disciplined DevOps?
What could help eliminate misunderstandings?
Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.
Which of the following activities should be performed next?
During a current sprint, a team member asks permission from the Scrum Master to investigate an alternative design approach.
What should the Scrum Master do?
The agile lead is told by executive leadership that the team needs to work faster because the release date has been moved up three months. The agile lead communicates the updated timeline to the team. One of the junior team members objects and feels the timeline is unrealistic.
What should the junior team member do?
A key stakeholder feels they do not understand the project at a comprehensive level.
What should the Agile practitioner do?
A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?
What should the team do?
An agile team is planning the next iteration for a product release that has accumulated technical debt. What should the team do?
What should the product owner do to resolve this?
During product development, changes in technology and regulations require the team to reassess product architecture.
How should this technical debt be captured?
A scrum master is overseeing the launch of a chatbot for the service desk. Complaints come up post-release about edge case responses to queries. After analyzing the issues, the business decision was made to take the chatbot offline, resulting in workflow disruptions and risking the reputation.
How could this situation have been avoided? (Refer to Testing Protocol Table)
A project team realizes that an important task on the iteration backlog will take more time than originally estimated.
What should the project team do?
DRAG DROP
All the developers on a project team are working offshore in a different time zone, resulting in many issues. Match the issues to the agile practitioner's recommendations for resolutions below. (Drag the Problems/Issues on the left to the box in the center, corresponding to the correct Recommendations for Resolution on the right)
What should the team do?
An organization is undergoing an agile transformation to improve its market position. Management wants minimal overhead in connection with the agile initiative and wants the agile teams to control the work in process (WIP) and ensure that iterations do not result in waste.
Which approach should be used in this scenario?
What should the team do?
During agile training, an aspiring scrum master with experience in predictive projects asks about the differences between the Kanban approach and the agile approach.
How should the agile trainer respond?
What is the proper agile approach to handle this?
Who should the Scrum Master invite to the meeting?
An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?
What should the team do?
How should the team resolve this?
Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?
Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release.
What should the team do?
In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?
An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased. What should the agile practitioner do to get the team back on track?
The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.
What should the team do next?
During sprint planning, the product owner wants the team to prioritize and deliver a number of features that have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.
What should the project leader do?
What is the project leader trying to create?
What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?
What should the Scrum Master do?
Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date.
What should the agile practitioner do?
Which option describes how risk should be managed in an agile project?
As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met.
How should the project management plan be adjusted?
An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.
What should the agile team do?
What should the agile practitioner do?
A newly formed team is struggling to work together and agree on how to complete tasks in the upcoming sprint. What should the scrum master do to support the team?
A project manager is working on a database migration project to cloud services (Refer to Migration Strategy to Cloud Services table). The project team has accumulated significant technical debt over several sprints due to pressure to deliver features quickly. This debt is now impacting their ability to deliver new features, leading to a notable decline in product performance and customer satisfaction.
Identify the actions the team should take to effectively manage technical debt while consistently delivering high-value features that align with stakeholder expectations.
An agile team has started to worry because lately they have seen an increase in the number of issues. There seems to be a large variance in the quality of the work items delivered. The team now realizes that a shared understanding of quality may not exist among team members.
What should the team do?
Unable to meet a sprint's committed velocity, an agile team approaches the agile coach to define the next sprint's velocity. What should the agile coach advise?
A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?
A member of the development team displays disrespectful behavior and continuously argues with colleagues. This is negatively impacting team morale.
Which action should the scrum master take to resolve this situation?
How could the project leader have avoided this?
What should the Scrum Master do first?
A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.
How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?
A new agile project manager accepts an assignment to manage a well-established team. Many team members have worked together on this product for several years. During a meeting, the project manager notices that team members offer little vocal interaction, yet all required tasks are completed on time.
What type of behavior does this describe?
In a Scrum team, who should be responsible for the budget and release plans?
Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched.
How should this situation be handled?
A Product Owner new to the role is very enthusiastic about an agile project with an energetic team.
What should be done first to ensure successful delivery of the product?
When a team member encounters an issue in an agile environment, what should they do?
Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?
During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.
What should the scrum master do?
A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.
Which two actions should the scrum master take as priorities? (Choose two.)
A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.
Which two actions should the scrum master take as priorities? (Choose two.)
An agile coach is facing a dilemma: On one hand, there is a requirement that is vital and will consume all capacity of the team. On the other hand, there are some chore-related tasks that will improve the team's ability to produce results. The team insists on implementing these tasks since they will increase efficiency.
What should the agile coach do?
Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item.
What should the agile project manager do?
A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?
The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.
What should the coach do to help the team?
When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?
What should the product owner do?
What should the agile team lead do?
How should the agile team address this?
A product owner is working on a special agile project for the automobile industry. The project team is responsible for all of the issues related to vehicle electronic control units. The team has observed a significant backlog of items in the “In progress' column (Refer to the kanban board). This accumulation is causing delays in task completion and impacting overall project timelines. The team operates in a dynamic environment where requirements frequently change, and stakeholders demand quick turnarounds.
What should the project team adopt to address this issue and improve task flow, considering all the demands?
A new stakeholder has recently joined a project. During a meeting with the Scrum Master, the new stakeholder tries to understand the status of the project and the remaining tasks for completion.
How should the Scrum Master inform the new stakeholder?
What should the agile coach do to develop members into a high-performance team?
A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.
What should the product owner do?
What should the agile coach do?
An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.
Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)
An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.
What should the Scrum Master do?
Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?
A project team identifies a number of technical challenges with features in the next sprint.
What should they do?
After conducting the second retrospective with project stakeholders, the customer expresses frustration. The customer wants a more predictable roadmap for the delivery of features and functionalities.
How should the project manager respond to the customer?
The product owner is very concerned about work not being completed and tested before a hard release date.
What can the agile team do to mitigate this risk?
Which agile practice would most significantly increase a team's velocity?
Several team members have complained to senior management about their Scrum Master's processes. What should the Scrum Master do to address the team's process concerns?
The Scrum Master for a large project must provide an estimate of what can be delivered in six months.
What should the Scrum Master do?
How should this be handled?
What should the team do to improve the accuracy of their estimates?
A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?
What should the agile coach do?
An executive notices a Kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do?
In companies where decision-making is driven by data analytics and unknown variables are addressed, what advantages does agile project execution offer over a predictive approach?
During its first sprint, a new Scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories.
What should the team do?
Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.
What should the agile leader do next?
An agile team had unexpected technical problems in a project and was not able to complete the deliverables on time. During the retrospective meeting, the team openly discussed the causes for these issues and what can be done to avoid similar situations in the future.
What agile values and principles did the team demonstrate?
A development team and product owner disagree on a user story in the product backlog. What should the agile practitioner do?
An agile project manager has noticed their teams declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?
A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.
What strategy should be used to deliver it successfully?
What should a team do when they complete all sprint goals earlier than expected?
The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration planning session, the team determines that the next highest priority item will take longer than expected to complete in the current sprint.
What should the agile practitioner do next?
An agile team is working on refining project requirements. Due to new dependencies uncovered in every working session, the team is unable to complete the detailed solution requirements. Instead of trying to complete requirements, what should the team do to work collaboratively to identify and prioritize the most important requirements and adapt to changes as needed?
During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks needed to implement the user stories?
What should the agile practitioner do next?
A scrum master is part of a team that has just agreed on the project scope and deliverables for a global, multilingual manufacturing company that has many staff members moving between locations. The team consists of 20 people and the budget is US$5 million. The kickoff meeting is scheduled for the following month.
What should the scrum master do as a first step?
An agile team is continuously interrupted by stakeholders wanting to ask product backlog questions. Distractions can have a negative impact on value delivery and quality.
Who is responsible for protecting against distractions?
An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager.
What should the Scrum Master do?
A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.
What should the agile team lead do?
During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.
How can the project team achieve this?
A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.
What should the team do?
A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.
Should the team add the feature's story points to their burndown chart?
A global organization is migrating its IT infrastructure from traditional, physical assets to cloud-based assets. Agile concepts are new to the organization because it currently uses a predictive approach.
What should an Agile Coach do to facilitate a culture change to an Agile approach?
After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.
If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?
What should the project leader suggest?
An organization is using a predictive approach to managing projects. The executives like to see more deliverables in a short time and require that the milestones be achieved on time.
What value can the organization gain by moving to an iterative approach?
During planning, a project team and sponsor created a visual representation of the high-level specifications of the features and user stories to be implemented in a product. Consensus was achieved on this high-level depiction of the product characteristics, but the sponsor is having difficulty understanding what to develop and when.
How should the project manager explain this to the customer and save time in the meeting?
An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?
What should the agile team do?
During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance.
How should the agile practitioner handle the recommendation?
The product owner working on an agile software development project has brought all the Scrum team members together for the first sprint planning meeting. The team has read the user stories and has provided estimates to complete these user stories. The product owner plans to empower the team to get the work done.
What is this an example of?
What should the agile team do?
The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.
What is the estimated project conclusion?
In a project to develop a supply-and-demand scenario planning tool, the team aims to streamline development and rapidly deliver features. Which approach best supports quick feature delivery while maintaining quality? (Refer to An Excerpt from the Quality Management Plan)
A product owner adds user stories to the backlog on a daily basis. The stories are vague requests, and the product owner expects the details to be clarified once the team works on the prioritization list.
How should the team members address this challenge so that the prioritization meeting does not become a brainstorming session?
A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).
What should the team tell the sponsor at this point in the planning process?
A project manager is managing a large complex project with cross-functional teams using an adaptive approach. Frequent communication among the team leads of these cross-functional teams is crucial for the project to stay on track and deliver value according to the project plan.
Which agile communication practice should the project manager implement to ensure the cross-functional teams interact frequently?
A newly formed Scrum team wants to foster an environment of transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments. Emphasis is placed on how issues are resolved and the strategies for preventing them in the future. Over time, what will be the result of this approach?
A scrum team is working on an important project with a short deadline. To save time and reduce overhead, the product owner proposes that the regular sprint reviews should be cancelled and replaced with a review of each release according to the release plan.
What should the scrum master do?
A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.
What should the Scrum Master do?
What should the agile practitioner do?
What should the agile project manager do?
A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.
What should the project lead do to help the team?
Part way through a project, several team members are in conflict over whether or not a deliverable has been properly completed.
How should the agile leader reduce this conflict?
An executive sponsor of a new Scrum team actively attends Scrum ceremonies.
How does this benefit the team?
An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.
What should the agile lead recommend?
An agile practitioner notices that a project is increasing open defect counts after every subsequent iteration.
What should the agile practitioner do?
At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.
How should this situation have been prevented?
An Agile Project Manager observes that the Scrum team is falling behind on the completion of a particular sprint.
What should the Agile Project Manager do?
What should the agile coach do in this situation?
A team member is stressed due to a heavy workload, while other team members have some slack in their schedules.
How should the team lead address this?
What should the agile practitioner do?
After completing the release plan, the team realizes that the project is very likely to have a negative ROI.
What should the team do?