Summer Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: wrap60

PMI PMP Dumps

Page: 1 / 35
Total 354 questions

Project Management Professional (2024 Version) Questions and Answers

Question 1

After 35 years of service, a company's CEO has retired. The new CEO is planning to digitally transform the company and has assigned a new project manager to assist in this endeavor. The initial backlog has been created and agreed upon, and the team members have been assigned.

What should the project manager do before the project kick-off meeting?

Options:

A.

Conduct a backlog refinement and identify the key activity to start with.

B.

Compare the team's expertise against the project requirements.

C.

Perform integration management activities to consolidate the plans.

D.

Review the project's environment to understand the organizational culture.

Question 2

As part of a company’s planning effort for team capacity building, the project manager was asked to provide management with a list ofrequired trainings for the project team. What should the project manager do?

Options:

A.

Review the project pipeline, identify gaps in competencies for execution, and decide on the needed trainings.

B.

Review the team members’ latest performance, identify gaps in competencies, and decide on the needed trainings.

C.

Review the project schedule and the team members’ performance, and decide on soft skills and related trainings needed for the team.

D.

Review the gaps found during project execution, prepare a list of recommended trainings, and discuss it during a team meeting.

Question 3

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path,

and any delay would impact project completion.

What should the project manager do?

Options:

A.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.

B.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.

C.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.

D.

Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.

Question 4

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

Options:

A.

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

B.

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

D.

Work with the team to understand their views and add the appropriate dependencies and risks.

Question 5

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a

timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

Options:

A.

Delegate certain authorities and share information to allow fair decision-making.

B.

Delegate most authorities and control the authority by withholding important information.

C.

Delegate most authorities and share information to allow fair decision-making.

D.

Delegate certain authorities and control the authority by withholding important information.

Question 6

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch. There is a risk of a partner's system being unavailable which could impact the project negatively.

What key activity is needed to ensure the project's success?

Options:

A.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue.

B.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

C.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution.

D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities.

Question 7

A client has requested that a product be implemented in 4 months and is ready to increase their budget to do this quickly. The project manager cannot comply with the request with the current resources or

even additional resources. The project manager estimates that 8 to 12 months are needed for the product to go live.

What should the project manager do to address this situation?

Options:

A.

Call a meeting with the client so they will understand that 4 months is not enough time to deliver the product.

B.

Motivate the team to work more efficiently and approve overtime in order to meet the client's goal in 4 months.

C.

Discuss with the client alternative approaches to deliver the minimal viable product (MVP) in 4 months and the rest later.

D.

Seek additional resources from the subcontractors and other sources to parallelize the necessary work.

Question 8

A project team consists of eight resources working on a complex project. The chief technical designer prefers to work alone and seldom talks in meetings, but produces good designs. The technical lead is always energetic, has lots of opinions about the project, and constantly clarifies their thoughts in discussions.

What should the project manager do to improve overall team performance?

Options:

A.

Ask the chief technical designer to provide their feedback by email.

B.

Let the team dynamics continue as is since the current team mix works well.

C.

Encourage the chief technical designer to engage more with the team.

D.

Ask the technical lead to drive the project's technical discussions.

Question 9

A project manager is newly assigned to the second phase ofan ongoing project. During theimplementation, a defect occurred and no oneknows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.

What should the project manager do first?

Options:

A.

Acquire knowledgeable resources.

B.

Check the organizational process assets (OPAs).

C.

Update the risk management plan.

D.

Extend the timeline of the project.

Question 10

A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard.

What should the project manager do?

Options:

A.

Review the configuration management plan.

B.

Update the stakeholder engagement plan.

C.

Review the project management plan.

D.

Update the communications management plan.

Question 11

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1.25. The project manager must provide the first project status review soon and wants to emphasize that the project is under control.

How should the project manager report the project status to key stakeholders?

Options:

A.

Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.

B.

Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.

C.

Prepare a detailed presentation for stakeholders on earned value, including how it is calculated and the project's current earned value results.

D.

Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away.

Question 12

A project manager noticed that a team member has been struggling with some tasks, which may ultimately impact the completion date.

Team morale is low because they will not get the expected bonus if they do not finish on time.

What should the project manager do next?

Options:

A.

Update the project schedule and budget estimates.

B.

Ask the human resources (HR) department to replace the team member and add an additional resource.

C.

Ask the client to approve a delay in the project schedule.

D.

Acknowledge the team for their accomplishments, encourage them, and offer assistance to avoid future delays.

Question 13

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the

senior managers claim not to know about the deliverable.

What should the project manager do next?

Options:

A.

Check if these stakeholders attend regular project meetings.

B.

Meet with these stakeholders to review the project charter.

C.

Review the project charter to validate this claim.

D.

Validate if the project charter changed from the original one.

Question 14

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain. When attempting to gain an understanding of the risks for this agile project, what is the primary tool the project manager should employ?

Options:

A.

Probability assessments

B.

Workshops for risk avoidance

C.

Interview with the project champion

D.

Collaborative discussion

Question 15

A project manager is working on a project for a startup company. The company launched cloud-based agile project management and DevOps training modules via the learning platform to support multiple self-paced and virtual learning formats. In a recent sprint, the quality assurance team failed to thoroughly inspect the modules before deployment, resulting in a poor customer experience.

Which of the following issues is the project manager facing?

Options:

A.

Nonconformance issue

B.

Unmet planned-to-done ratio

C.

Undetected error

D.

Escaped defect

Question 16

A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to allstakeholders; however, the last department to migrate indicated that they have not received the notification.

What should the project manager do?

Options:

A.

Report the issue during the next status meeting at the end of the week.

B.

Escalate the issue to the project sponsor and upper management.

C.

Close out the project and tell the manager to open a service desk ticket.

D.

Log the issue and assign it to the project team member(s).

Question 17

A project manager is part of a cross-functional agile team. Throughout the project, it has become obvious that team members from different functional units have different perspectives of what the outcomeshould be.

What should the project manager do to resolve this?

Options:

A.

Schedule a meeting with the stakeholders to determine a consensus regarding the outcome.

B.

Invite the project sponsor to the sprint review to provide clarity on the sprint outcome.

C.

Ask the product owner to address the concerns about the project outcome during the sprint retrospective.

Check to ensure the project outcome aligns with the project charter and statement of work (SOW).

Question 18

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee.

+ Actual progress = 2 units

+ Planned progress = 3 units

+ Actual cost (AC) = 2 units

+ Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

Options:

A.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

Question 19

A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know

how frequently the risks are being reviewed.

Which document project manager should check first?

Options:

A.

Risk management plan

B.

Risk register

C.

Issue log

D.

Risk report

Question 20

Due to a recent company merger, a project manager from company B has been assigned to a team that is comprised of team members from company A. At the start of the project, conflicts arise due to a lack

of clarity on processes and the project manager's relationship with company B.

What should the project manager do to resolve this conflict?

Options:

A.

Work with the team to analyze which processes are suitable to use and define them in the ground rules.

B.

Ask the team to use company B's processes since they are more familiar with these processes.

C.

Avoid the conflict as the customer feels comfortable with using processes from company A.

D.

Review the historical information and make the decision based on the return on investment (ROI).

Question 21

A project manager for an application development firm is meeting with stakeholders prior to the launch of the latest release of the company's most profitable application. The stakeholder mentions the following key points:

• A major corporate rebrand was scheduled to occur with this launch, but the rebrand has been delayed by 3 weeks.

• Development processing improvements will be ready in 4 weeks.

• The company is preselling the updated product with a release date of next week.

Which action should the project manager recommend to the sponsor?

Options:

A.

Have the sales team reach out to customers to communicate that the product release is being delayed.

B.

Suspend the release of the product until the marketing delay has been resolved.

C.

Delay the rebranding and release the product now to address the realized improvements and meet the sales commitments

D.

Postpone the product release until the processing improvement delay has been resolved

Question 22

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the processes and procedures, the

project manager notices similarities to a previous project that experienced similar roadblocks. The project manager reviews the task schedule and finds that certain tasks are

well behind expectations. In speaking with the project team, the project manager confirms that the team is following the processes exactly.

What should the project manager do?

Options:

A.

Review the resources allocated to the project and change accordingly.

B.

Review and amend the processes to ensure only value-adding activities are present.

C.

Update the variation register to account for the extended project time.

D.

Update the schedule to account for the unexpected delays in the project tasks.

Question 23

An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.

What should the project manager do?

Options:

A.

Establish a project schedule.

B.

Assign a team leader.

C.

Recognize the team's contributions.

D.

Establish a team charter.

Question 24

During the daily standup meeting that is assessing progress against the current sprint, ateam member reports some delayscomponent managed by an external vendor. How should the project manager address the team member's concern?

Options:

A.

Implement fast tracking to reduce the impact of the delay on the sprint.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Update the communications management plan to prevent future reoccurrence.

D.

Ask the team member to resolve the issue independently to minimize further delays.

Question 25

The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.

What should the project manager do?

Options:

A.

Inform stakeholders about the delay during project updates.

B.

Determine cross-dependencies and plan a spike in the next sprint.

C.

Discover the gaps in the communications management plan and address them accordingly.

D.

Determine the risks and identify a resolution during the retrospective meeting.

Question 26

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

Options:

A.

Reject the changes as the lead time is too short.

B.

Determine whether the project team is capable of making the changes.

C.

Review the additional changes and perform integrated change control.

D.

Check if the changes are covered in the statement of work (SOW).

Question 27

A project manager is preparing the business case for a project in a not for profit organization. The project manager justifies the cost of the project to a group of sponsors.

Which benefits realization metric should the project manager use?

Options:

A.

Total value of ownership

B.

Budget at Completion (BAC)

C.

Payback period

D.

Return of investment (ROI)

Question 28

A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new capability

to perform a what-if analysis in the tool based on the customer demand and forecast.

What should the project manager do next?

Options:

A.

Include the new capability to the product backlog and continue activities based on the current plan.

B.

Perform an impact analysis on the schedule and budget based on the additional scope.

C.

Analyze and negotiate with the executive steering committee regarding this new request.

D.

Revise the project schedule and budget based on the additional scope, and review with the team.

Question 29

A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.

What should the project manager do?

Options:

A.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

B.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

C.

Suggest the team member postpone their enrollment in the master's program until the project is completed.

D.

Assess the team member's commitment to the master's program and its impact on project performance.

Question 30

A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customerdetailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent theproject from being completed in the number of iterations initially planned.

What should the project manager do next?

Options:

A.

Create a contingency plan in case the project deviates from the initial plan.

B.

Create an assumption log and map assumptions to impediments based on the impact to the project value.

C.

Create an issue log template that will be used to identify and track impediments.

D.

Create a schedule management plan to ensure the project meets the delivery date.

Question 31

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.

How should the project manager address this situation?

Options:

A.

Ensure the feature's tasks are included in the iteration backlog, explain to the sponsor the consequences of the request, and ask the team to deliver the feature in the current iteration.

B.

Ensure the feature has been included in the product backlog, then hold a meeting with the team and sponsor to determine how to deliver the feature within the current iteration.

C.

Ensure the feature is included in the iteration backlog, ask the team to work on the current tasks first, and include the new tasks after those tasks are completed.

D.

Ensure the feature has been included in the product backlog, explain to the sponsor the consequences of the request, and ask the team to include the features tasks in the next iteration.

Question 32

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project.How should the project manageradjust their responsibilities accordingly?

Options:

A.

Introduce new communication tools to the project team members.

B.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination.

C.

Become a servant leader by supporting team collaboration and removing impediments.

D.

Delegate coordination activities to the product owner so the project manager can focus on managing collaboration.

Question 33

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.

What should the project manager do?

Options:

A.

Ask the team member to develop a dashboard to fulfill the request.

B.

Tell the team member to route the request through the project manager.

C.

Update the communications management plan to include informal requests.

D.

Update the stakeholder engagement assessment matrix.

Question 34

An agile project is approaching its first release date, and the product will be supported by the operations team. To ensure proper support for the product, what should the project manager do?

Options:

A.

Engage an external consultancy to assemble supporting documents and coordinate the knowledge transfer.

B.

Create and prioritize a support manual on the product backlog to ensure adequate knowledge transfer.

C.

Ensure the operations team has representation in the planning and review meetings and that there are support requirements in the backlog.

D.

Propose a workshop with the operations team to outline all requirements of the new software and how to properly support it.

Question 35

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeksdue to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

Options:

A.

Convince the team member not to leave until the project is completed.

B.

Reach out to the procurement team to hire a substitute for the team member.

C.

Allow senior management to decide how to proceed with the project.

D.

Reach an agreement with the team on how to handle the situation.

Question 36

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects. The project manager would like to minimize the impact of the

stakeholder's behavior on the development team.

What training should the project manager choose for their team to help with this situation?

Options:

A.

Agile training

B.

Emotional intelligence training

C.

Communication training

D.

Negotiation training

Question 37

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition.

However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of contract to sign with the vendor responsible

for migrating the systems. The project manager is concerned about controlling finances while delivering results.

How should the project manager address this situation?

Options:

A.

Sign a single agreement for the whole project.

B.

Negotiate payment after all project migration is completed.

C.

Use fixed-price increments as user stories are completed.

D.

Confirm payment after each project retrospective.

Question 38

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

Options:

A.

Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product.

B.

Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.

C.

Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work.

D.

Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.

Question 39

A project manager is transitioning from a predictive life cycle project to a new agile project. How should the project manager manage and control the scope for the new project?

Options:

A.

Create a scope baseline and put the rest as backlog activities.

B.

Estimate the work the team can complete and define story sizes to keep the project under control.

C.

Develop a plan to complete more work in less time.

D.

Spend a short amount of time defining the scope and building prototypes to refine the requirements.

Question 40

A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the

system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.

B.

include knowledge transfer sessions between the project and operations team at every stage

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure

Question 41

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used

to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project's health?

Options:

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast. O

B.

Explore reporting the eamed value (EV) key performance indicators (KPIs) usingagile progress as an input.

C.

Ask the project managers to report on their projects using a Kanban board format.

D.

Request the program managers to be more accurate when presenting status reports.

Question 42

Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing

manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.

What should the project manager do?

Options:

A.

Cancel the meeting series until the marketing team provides a solution.

B.

Consult the project team and discuss the key team members’ availability.

C.

Shift those key members and assign them to another project.

D.

Consult the resource management plan and escalate to the sponsor.

Question 43

A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on theproject due to a lack of resources. What should the project manager do next?

Options:

A.

Escalate the issue to the sponsor and debrief them about the situation.

B.

Review the risk management plan to identify the response strategy.

C.

Review the milestone list to determine which tasks can be fast-tracked.

D.

Organize a team meeting to discuss the next course of action.

Question 44

Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two

members are tense around each other and are taking everything personally.

What should the project manager do?

Options:

A.

Send both team members to the human resources (HR) department for an acceptable resolution.

B.

Understand each team member's argument and select the one that results in less risk to the project.

C.

Help the team members to resolve the conflict in a way that results in the best team performance.

D.

Offer a compromise that is acceptable to both team members, even if it may not be the best solution.

Question 45

A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?

Options:

A.

Reject the changes as the project is in the final stages.

B.

Perform a detailed assessment to analyze the impact.

C.

Use schedule compression methods to alter the critical path.

D.

Initiate a risk response strategy from the risk register.

Question 46

A project manager has been assigned to a corporate project management office (PMO). They are responsible for leading the development and rollout of updated project management procedures and templates

that would include both predictive and agile approaches,

What should the project manager do after the documents are completed?

Options:

A.

Hire an external consultant to monitor the execution of the new procedures.

B.

Upload the files to the corporate website to be available for internal use.

C.

Meet with the department managers to help them roll out the new procedures.

D.

Develop a training plan for all of the stakeholders to learn about the updates.

Question 47

A project presently in the testing stage is nearing the closing phase, which will transition the completed project to the company’s operations support team. However, many new members have just been added

to the operations support team who are not familiar with the project and the project's acceptance is now at risk.

What should the project manager do to mitigate this transition risk?

Options:

A.

Request the steering committee to authorize an early project deployment (i.e., a “beta” transition release) and engage the operations support team in the early release.

B.

Request the steering committee to reevaluate the feasibility of transitioning and closing the project given the personnel changes on the operations support team.

C.

Request the steering committee to train only the selected operations team members who are familiar with the project and then train the new team members separately.

D.

Request the steering committee to exclude the new team members during the transition and train the new members after the planned transition is completed.

Question 48

One of the team members is always late to the daily standup meeting. What should the project manager do?

Options:

A.

Reinforce the ground rules for standup meetings with the entire team.

B.

Schedule the meeting at the end of the day to accommodate everyone.

C.

Speak with the team member directly to reinforce the ground rules.

D.

Ignore the situation since the team member is accomplishing their deliverables.

Question 49

A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner.

Which activity should the project manager undertake?

Options:

A.

Change the delivery project approach.

B.

Perform a cost-benefit analysis.

C.

Review the risk analysis.

D.

Review the definition for the minimum viable product (MVP).

Question 50

A local company is developing a new product and, for the first time, using a remote team for the programming tasks of features. The design for the product comes from the

local team. During the third sprint review, the product owner has concerns about the project's outcomes. The remote development team is complaining that they do not

clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

Options:

A.

Review lessons learned from previous projects and organizational process assets (OPAs).

B.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

C.

Determine the communication needs, environment, and tools to get the message across.

D.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

Question 51

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project managerrealizes that a significant regulatory feature is missing in the project backlog.

What should the project manager do?

Options:

A.

Estimate the related cost and ask for a project extension.

B.

Ask the product owner to add the missing feature in the backlog.

C.

Increase the capacity of the team to include the missed feature.

D.

Invite stakeholders to discuss the impact of adding the regulatory feature.

Question 52

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design andexecution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitanttoprovide support for the project.

What should the project manager do?

Options:

A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.

B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.

C.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

D.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed.

Question 53

Team members are having a discussion with the project manager. In the last retrospective meeting, the team realized that the obsolete equipment could affect the next

iteration of the project. The team recommends buying new equipment because it is critical to the success of the final deliverable.

What should the project manager do next?

Options:

A.

Check the project budget to verify if there is enough contingency reserve.

B.

Tell the team members that more equipment is not part of the project's scope.

C.

Submit a change request to increase the budget and buy new equipment.

D.

Review the cost management plan to determine how to address this issue.

Question 54

A large project is affecting the neighborhood in which it is located. The neighbors are not satisfied with the project, and their resistance to the project may affect the project

deadline.

What two actions should the project manager take? (Choose two.)

Options:

A.

Analyze the situation and find out what is causing the neighborhood's negative attitude.

B.

Ask the customer to extend the project deadline to allow time for conflict resolution.

C.

Ask the mayor of the city to use their authority to stop neighborhood resistance.

D.

Set up a meeting with neighborhood representatives to win their cooperation.

E.

Send letters to the neighbors and ask them kindly not to disturb the project.

Question 55

A project team is working to deliver a solution to manage nationwide crisis relief operations. The project team is spending most of its time in

meetings with end users. The meetings have been slowing down project progress.

What should the project manager do to keep the deployment on track while obtaining stakeholder approval?

Options:

A.

Put all of the requirements, priorities, and progress on a visible board, share it with all entities, and decrease the number of meetings.

B.

Ask the project sponsor to attend the meetings on behalf of the team while the team is working on the development.

C.

Inform the stakeholders that a daily meeting will take place at a specific time and ask them to share their feedback during this time.

D.

Stop attending meetings, start development with what was collected so far, and define a date for the first delivery of the solution.

Question 56

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined.

The actual invoice payments received have also been late and were outside of the contracted payment schedule. Recent invoices have only been partially paid.

What should the project manager do?

Options:

A.

Review past projects for payment-related lessons learned.

B.

Conduct a meeting with the project team to update the procurement management plan.

C.

Add nonpayment to the issue log and keep tracking payments.

D.

Hold a meeting with the client to address the issue.

Question 57

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do toimprove project performance?

Options:

A.

Empower the team members to remove obstacles and blockers.

B.

Address and remove obstacles and blockers for the team.

C.

Ask stakeholders to communicate with the team directly.

D.

Add blockers to the issue log and risk management plan.

Question 58

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand

for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?

Options:

A.

Hire a third party who is an expert on the industry's regulations to work out the details.

B.

Escalate the issue to the company's CEO who has experience with the regulations.

C.

Communicate with the industry's regulatory authority to grant the company an exception.

D.

Comply with the regulatory requirements and work to compress the project schedule.

Question 59

A team has been working on a project for several months, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some

deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?

Options:

A.

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders.

B.

Create a prioritized backlog and define iteration review sessions with stakeholders.

C.

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders.

D.

Schedule a daily meeting to review team performance and impediments.

Question 60

A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support atproject completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology.

What should the project manager do to resolve the conflict?

Options:

A.

Acknowledge the lack of approval and focus on a resolution that will benefit the customer.

B.

Maintain and adhere to project plans to ensure the project delivers successful outcomes.

C.

Seek to understand the project stakeholders’ needs in an effort to support the new technology.

D.

Communicate the project's progress to the stakeholders and promote the new technology.

Question 61

Some of the team members who are working on a new software tool are in a public space, arguing over a new feature being coded instead of completingthe coding. How should the project manager handle this situation and get the team to complete the task?

Options:

A.

Bring the team members to the meeting room to discuss the new feature and to reach a common understanding of the necessary coding.

B.

Contact the human resources (HR) department to tell them there is an argument in a public space and that they need to intervene immediately.

C.

Engage in the conversation in the public space by telling them the expectations of the feature and advise them to return to their workspace.

D.

Listen to the argument from a nearby location to understand the situation, then offer insight into the features when the team is calm.

Question 62

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses toapprove the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource’s refusal?

Options:

A.

Communicate with their supervisor.

B.

Speak directly with the resource.

C.

Organize a team meeting.

D.

Speak with their colleague.

Question 63

On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project managerrealized that some of the keyactivities were scheduled over the holiday periods in the overseas offices.

What shouldthe project manager do next?

Options:

A.

Hire additional personnel on a temporary basis to cover the extra workload during the holiday seasons.

B.

Request that the offices in overseas locations work overtime to mitigate schedule slippages.

C.

Update the schedule to reflect the holidays and notify the project sponsor of the delayed completion.

D.

Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage.

Question 64

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed

concerns about the use of new tools on such an important project.

What should the project manager do?

Options:

A.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

B.

Review the adaptive tools' impact and obtain agreement from the functional manager.

C.

Follow the functional manager's recommendation to implement only predictive tools in the project.

D.

Make the decision on which project approach to use that would best fit the project.

Question 65

An agile project team is creating an enterprise workflow system for a company. One of the project team members, who is the system design architect, keeps receiving telephone calls from the users who are

asking questions about the system. The calls are impacting the architect's daily work schedule.

What should the project manager do?

Options:

A.

Revise the backlog and assign stories to another team member to reduce the architect's workload.

B.

Include user training materials as part of the project deliverables so that users can receive self-help.

C.

Ask the system architect to write up a self-help manual so that the users can resolve the questions by themselves.

D.

Ask the users to send emails instead of calling so that the system architect can reply when they areavailable.

Question 66

Some project teams are voicing frustration because of conflicting priorities between agile and predictive work in a complex project. Which leadership style would effectively promote collaboration across the

project teams?

Options:

A.

Delegative leadership

B.

Servant leadership

C.

Directive leadership

D.

Leadership by example

Question 67

A project manager is assigned to a new project. The project management office (PMO) and the project manager agree that this is the right opportunity to include daily standup meetings. The project team has

never used such tools, and a few members are challenging the decision.

What should the project manager do in this situation?

Options:

A.

Engage an external vendor to perform the design phase under an iterative approach.

B.

Define the ground rules, responsibilities, and conflict management strategies.

C.

Request that new team members familiar with iterative approaches be assigned to this project.

D.

Update the project schedule to consider a daily standup as part of the project design phase.

Question 68

A project manager is performing the role of scrum master for a team of developers. There is a conflict among the developers, generated by differences in how a feature can be delivered.

The project manager organized a few spikes to resolve this conflict.

What should the project manager do next?

Options:

A.

Ask the project sponsor to decide which option should be implemented.

B.

Organize a multivoting event to achieve consensus of the whole team.

C.

Allow the team to decide on their own which option should be implemented.

D.

Organize more spike events until consensus of the team is reached.

Question 69

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent

to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

Options:

A.

Seek an external expert to review the framework.

B.

Arrange for external training amid the tight project schedules.

C.

Add new members for the underperforming team.

D.

Foster knowledge sharing and coaching among team members.

Question 70

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not

be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

Options:

A.

Schedule a meeting with all stakeholders to extend the project deadline.

B.

Review and update the issue log and determine if any alternative components can be offered.

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Replace the vendor with a new vendor who can offer the component on time.

Question 71

A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.

Which evaluation practice should the project lead use to obtain accurate usage data?

Options:

A.

Build the functionality in the software to collect the operational usage data.

B.

Send out a questionnaire to all users regarding the most useful features.

C.

Embed a feedback form into the system for users to respond.

D.

Interview a sampling of users to obtain the usage data.

Question 72

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

Options:

A.

Update the stakeholder register.

B.

Consult the project sponsor.

C.

Refer to the resource management plan.

D.

Modify the statement of work (SOW).

Question 73

A project manager has been assigned to a new project. There is one team member who never says anything during meetings. After meetings, however, the team member

sends detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?

Options:

A.

Motivate the team members to speak freely in the meeting.

B.

Arrange a team-building activity to involve all team members.

C.

Remind the team members to follow the team charter.

D.

Review the communications management plan with the team members.

Question 74

A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the

organization and have varying levels of interest.

Which approach should the project manager use with the stakeholders?

Options:

A.

Schedule one-on-one meetings with stakeholders to provide project updates.

B.

Provide daily reports to maximize stakeholder communication.

C.

Share all relevant project information with the stakeholders.

D.

Minimize communication until project completion as it will be finished quickly.

Question 75

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significantchange in the technical architecture and an additional release.

What should the project lead do first?

Options:

A.

Discuss with the solution architect

B.

Discuss with the development team

C.

Discuss with the product owner

D.

Discuss with the technical lead

Question 76

In an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the scheduleperformance index (SPI)?

Options:

A.

40/70

B.

30/70

C.

30/40

D.

40/30

Question 77

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed.

During a recent external audit, the project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Options:

A.

Ensured that all the required approvals were received per the organizational procedures

B.

Ensured that all defects identified during testing were resolved before implementation

C.

Ensured that all of the required tasks identified in the scope were completed successfully

D.

Ensured that all documentation was completed post implementation before closing the project

Question 78

A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and thestakeholder notices that an important functionality for their area was not tested.

Which tool should the project manager have used to prevent this situation?

Options:

A.

Project charter

B.

Stakeholder register

C.

Project scope statement

D.

Issue log

Question 79

An external project manager is managing the construction of new corporate offices for a large company. The project management plan states that it is

necessary to contract a highly trained external resource to revise and validate an important project component. The client has rejected hiring the external

resource because of the high cost, even though it is within the project budget.

What should the project manager do to resolve this issue?

Options:

A.

Hire the resource in order to achieve the project objectives.

B.

Evaluate the consequences and meet with the client to explain the possible scenarios.

C.

Ask the client for a meeting and explain that the task will not be performed.

D.

Try to accomplish the task internally by leveling resources from other projects.

Question 80

A company is initiating a project to enhance one of its existing products. All of its products are developed internally.

What should the project manager do?

Options:

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Create a lessons learned document for the initiation phase.

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Review the lessons learned from the previous project

Question 81

A project manager has access to risk management tools but chooses to use a quantitative method to evaluate the project risks. During

project execution, the project sponsor asks for an updated risk matrix.

What should the project manager do next?

Options:

A.

Use integrated risk management software to evaluate the risks.

B.

Use their own professional knowledge to reassess the risks.

C.

Add new risks and send the risk matrix to leadership for approval.

D.

Trust in the quantitative method already chosen as it is a precise method.

Question 82

A company plans to initiate a project involving a new technology. Approval for the project is required.

What should the project manager do?

Options:

A.

Review the cost and schedule baselines for execution.

B.

Identify the risks in implementing the new technology.

C.

Define change management for the new technology.

D.

Analyze the cost and identify the project benefits.

Question 83

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who

is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during

meetings.

How should the project manager handle this moving forward?

Options:

A.

Update the project schedule to cater to this particular stakeholder.

B.

Allocate time to gain buy-in from the stakeholder prior to key decision meetings.

C.

Ask that only key decision makers attend the project meetings. O

D.

Update the risk register to consider the possible project impacts.

Question 84

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The

project manager starts to present the budget, but the CEO suddenly asks to end the meeting.

What should the project manager have done to avoid this situation?

Options:

A.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register.

B.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting.

C.

Reviewed the communications management plan before inviting an external client representative to the meeting.

D.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting.

Question 85

A project manager is working on a project that is required to deliver value on an incremental basis. Which action should the project manager take to enable successful project execution?

Options:

A.

Engage with the project sponsor to understand the scope.

B.

Develop a comprehensive set of requirements.

C.

Create a project schedule containing milestones.

D.

Identify the tangible and intangible benefits.

Question 86

A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently

implemented.

What should the project manager do?

Options:

A.

Escalate the team member's performance to the project sponsor.

B.

Ask the team member to learn the new system as on-the-job training.

C.

Issue a change request to extend the project schedule.

D.

Assign an experienced resource to support the team member.

Question 87

A project manager has commissioned a design study from a consulting firm to investigate a number of alternatives. The project managerhas a strict policy on the cost of the study and has established a number of cost triggers and trend analyses.

Which tool is the project manager using?

Options:

A.

Secureanalysis

B.

Time and materials (T&M) contract

C.

Earned value (EV)

D.

Control chart

Question 88

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?

Options:

A.

Requested robust documentation for the component's build.

B.

Outsourced development of the specific component to another team.

C.

Facilitated cross-functional knowledge transfer during the project.

D.

Acquired more than one resource skilled in each component.

Question 89

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to

ensure the project will remain on track and achieve its goals.

What should the project manager do?

Options:

A.

Conduct an integration meeting among all stakeholders.

B.

Consider cultural differences among stakeholders.

C.

Understand how political aspects can affect the project.

D.

Schedule communication training for management-level stakeholders.

Question 90

A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project manager knows this teammember could add value to the project.

What should the project manager do to get the most value from this team member?

Options:

A.

Advise the team member to focus on the current project and consider the past conflicts as lessons learned.

B.

Advise the team member not to share personal information from past projects with the entire team.

C.

Consult with the project sponsor to find out if it is allowed to share personal information with the entire team.

D.

Consult with human resources (HR) and check company policies on what is allowed to advise the team member.

Question 91

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

Options:

A.

Adjust the original budget estimates with the current cost variance.

B.

Perform a root cause analysis of the project performance.

C.

Review the activity duration to reforecast the project completion date.

D.

Negotiate the project changes and adjust stakeholder expectations.

Question 92

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even

after 1 week of maintenance.

What should the senior project manager do now?

Options:

A.

Use interpersonal skills to expedite the issue.

B.

Update the issue log with the status and priority.

C.

Send a gentle reminder to the technical service team.

D.

Issue a formal warning to the technical service team.

Question 93

The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has

performed the code inspections, however the records are not complete.

What should the project manager do?

Options:

A.

Hold a meeting with the project team, project sponsor, and the client to agree to the further work required to close the project and add to lessons learned.

B.

Close the project and hand over the deliverables to the client.

C.

Hold a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects.

D.

Seek expert legal advice on the interpretation of the clauses in the contract.

Question 94

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. In a project review meeting, a key stakeholder reports that the latest documentation

provided by the project manager includes a reference to unrelated products.

What should the project manager do?

Options:

A.

Ask the project management office (PMO) to support and review all deliverables.

B.

Log the issue in the risk register and the issue log.

C.

Develop a standard for document quality control.

D.

Assign a technical writer to the project.

Question 95

Afew key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, theproject schedule is seriouslydelayed.

What should the project manager do?

Options:

A.

Request additional resources to be incorporated to the project team.

B.

Observe the project team and give them time to catch up before escalating.

C.

Review the issues and adjust the project plan to give a realistic schedule.

D.

Escalate to the project sponsor and seek alternatives to resolve the issue.

Question 96

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

Options:

A.

Keep activities as planned regardless of the resource change.

B.

Update the burndown chart to reflect this resource's absence.

C.

Have a meeting with the resource to understand the issue.

D.

Request an additional resource to finish the project.

Question 97

An agile project is running its second iteration out of six. A marketing director, who is a key stakeholder, contacts the project lead for a highlevel report of the project.

What should the project lead do?

Options:

A.

Tell the stakeholder that a new report will be produced at the end of the iteration.

B.

Explain to the stakeholder that the key indicators are by iteration.

C.

Ask the product owner to develop the new report based on the iteration information.

D.

Develop the requested report based on the iteration information.

Question 98

After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for thecompany's newest offering. Theproject manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. Theproject manager fears that thecompetitor's offering is better in multiple ways compared to the project manager's project.

What should the project manager do?

Options:

A.

Perform a Kano analysis factoring in the competitor's offering and present it to the stakeholders.

B.

Meet with the development team to see what changes will improve the project compared to the competition's deliverable.

C.

Meet with the project team to discuss the concerns and determine how to ensure the project's deliverable can compete with the competitor's.

D.

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor's offerings.

Question 99

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified

the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

Options:

A.

Conducted periodic reviews with the manager on resource availability.

B.

Defined the skill requirements more clearly in the scope statement.

C.

Consulted with the installation team on a regular basis to check for conflicts.

D.

Asked the manager to follow the agreed-upon resource management plan.

Question 100

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agilepractices, which are relevantto the project.

What should the project manager do to gain buy-in from the different stakeholders?

Options:

A.

Organize a meeting with relevant stakeholders explaining the benefits of agile and the practices relevant for the project.

B.

Send the project management plan, which includes the suggested agile practices, to the stakeholders.

C.

Organize a meeting with a consultant to provide training to the stakeholders on agile practices.

D.

Ask the project management office (PMO) to get buy-in from the stakeholders because agile is an approach that differs from their previous ways of working.

Question 101

A project manager prepared a project benefits management plan. Which of the following should be included in this document?

Options:

A.

Target benefits, benefits owner, lessons learned

B.

Project requirements, target benefits, issue log, metrics

C.

Target benefits, strategic alignment, time frame for realizing benefits

D.

Strategic alignment, benefits owner, risk register

Question 102

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is

dissatisfied, stating that the deliverables do not meet the quality specifications.

What should the project manager do in this situation?

Options:

A.

Notify the stakeholder that arbitration procedures will be followed.

B.

Review the requirements traceability matrix and conduct inspections.

C.

Document the issue in the issue log and send a report to management.

D.

Inform the project sponsor of the stakeholder's dissatisfaction.

Question 103

A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of therequirements. The project manager is concerned about scope creep.

Which action should the project manager take to control the scope?

Options:

A.

Accept only those changes that are approved by the change control board (CCB) prior to being implemented.

B.

Accept only those changes to requirements that provide additional value to the project.

C.

Ensure that all key stakeholders agree to the project deliverables and there will be no need for changes.

D.

Reject all changes that will increase the budget or increase the time line of the project.

Question 104

A project manager has been assigned to an education project with the objective of training a workforce in application development. One ofthe deliverables is to provideinternships to the best students in the customer's active projects. However, the customer does not have enough projects in progress right now. The project manager decidesto create several internal projects in order to ensure the internships.

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose 3)

Options:

A.

Influence the client to initiate a new project.

B.

Create a change request with the scope of the new internal projects.

C.

Use the project's contingency budget.

D.

Manage the quality of the delivery.

E.

Create a work breakdown structure (WBS) of the new scope with the internal projects.

Question 105

A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables.How should the project managerrespond?

Options:

A.

Implement stricter controls so that project artifact creation is given the utmost importance.

B.

Facilitate the implementation of an automated tool for the team to manage project artifacts.

C.

Advise the team that solely focusing on artifacts will not produce successful project deliverables.

D.

Recognize the team’s efforts for documenting artifacts and motivate them with an incentive mechanism

Question 106

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around theproject has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

Options:

A.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.

B.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.

C.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.

D.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.

Page: 1 / 35
Total 354 questions