Project Management Professional (2024 Version) Questions and Answers
After 35 years of service, a company's CEO has retired. The new CEO is planning to digitally transform the company and has assigned a new project manager to assist in this endeavor. The initial backlog has been created and agreed upon, and the team members have been assigned.
What should the project manager do before the project kick-off meeting?
As part of a company’s planning effort for team capacity building, the project manager was asked to provide management with a list ofrequired trainings for the project team. What should the project manager do?
A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path,
and any delay would impact project completion.
What should the project manager do?
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned
to work on the details and estimates as requested by the client.
What should the project manager do before sending the information to the client?
A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a
timely manner.
In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch. There is a risk of a partner's system being unavailable which could impact the project negatively.
What key activity is needed to ensure the project's success?
A client has requested that a product be implemented in 4 months and is ready to increase their budget to do this quickly. The project manager cannot comply with the request with the current resources or
even additional resources. The project manager estimates that 8 to 12 months are needed for the product to go live.
What should the project manager do to address this situation?
A project team consists of eight resources working on a complex project. The chief technical designer prefers to work alone and seldom talks in meetings, but produces good designs. The technical lead is always energetic, has lots of opinions about the project, and constantly clarifies their thoughts in discussions.
What should the project manager do to improve overall team performance?
A project manager is newly assigned to the second phase ofan ongoing project. During theimplementation, a defect occurred and no oneknows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.
What should the project manager do first?
A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard.
What should the project manager do?
In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1.25. The project manager must provide the first project status review soon and wants to emphasize that the project is under control.
How should the project manager report the project status to key stakeholders?
A project manager noticed that a team member has been struggling with some tasks, which may ultimately impact the completion date.
Team morale is low because they will not get the expected bonus if they do not finish on time.
What should the project manager do next?
During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the
senior managers claim not to know about the deliverable.
What should the project manager do next?
A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain. When attempting to gain an understanding of the risks for this agile project, what is the primary tool the project manager should employ?
A project manager is working on a project for a startup company. The company launched cloud-based agile project management and DevOps training modules via the learning platform to support multiple self-paced and virtual learning formats. In a recent sprint, the quality assurance team failed to thoroughly inspect the modules before deployment, resulting in a poor customer experience.
Which of the following issues is the project manager facing?
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to allstakeholders; however, the last department to migrate indicated that they have not received the notification.
What should the project manager do?
A project manager is part of a cross-functional agile team. Throughout the project, it has become obvious that team members from different functional units have different perspectives of what the outcomeshould be.
What should the project manager do to resolve this?
A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee.
+ Actual progress = 2 units
+ Planned progress = 3 units
+ Actual cost (AC) = 2 units
+ Budgeted cost = 3 units
What statement should the project manager make to the project steering committee?
A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know
how frequently the risks are being reviewed.
Which document project manager should check first?
Due to a recent company merger, a project manager from company B has been assigned to a team that is comprised of team members from company A. At the start of the project, conflicts arise due to a lack
of clarity on processes and the project manager's relationship with company B.
What should the project manager do to resolve this conflict?
A project manager for an application development firm is meeting with stakeholders prior to the launch of the latest release of the company's most profitable application. The stakeholder mentions the following key points:
• A major corporate rebrand was scheduled to occur with this launch, but the rebrand has been delayed by 3 weeks.
• Development processing improvements will be ready in 4 weeks.
• The company is preselling the updated product with a release date of next week.
Which action should the project manager recommend to the sponsor?
A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the processes and procedures, the
project manager notices similarities to a previous project that experienced similar roadblocks. The project manager reviews the task schedule and finds that certain tasks are
well behind expectations. In speaking with the project team, the project manager confirms that the team is following the processes exactly.
What should the project manager do?
An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.
What should the project manager do?
During the daily standup meeting that is assessing progress against the current sprint, ateam member reports some delayscomponent managed by an external vendor. How should the project manager address the team member's concern?
The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.
What should the project manager do?
A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?
A project manager is preparing the business case for a project in a not for profit organization. The project manager justifies the cost of the project to a group of sponsors.
Which benefits realization metric should the project manager use?
A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new capability
to perform a what-if analysis in the tool based on the customer demand and forecast.
What should the project manager do next?
A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.
What should the project manager do?
A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customerdetailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent theproject from being completed in the number of iterations initially planned.
What should the project manager do next?
A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.
How should the project manager address this situation?
A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project.How should the project manageradjust their responsibilities accordingly?
A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.
What should the project manager do?
An agile project is approaching its first release date, and the product will be supported by the operations team. To ensure proper support for the product, what should the project manager do?
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeksdue to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects. The project manager would like to minimize the impact of the
stakeholder's behavior on the development team.
What training should the project manager choose for their team to help with this situation?
A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition.
However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of contract to sign with the vendor responsible
for migrating the systems. The project manager is concerned about controlling finances while delivering results.
How should the project manager address this situation?
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
A project manager is transitioning from a predictive life cycle project to a new agile project. How should the project manager manage and control the scope for the new project?
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the
system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used
to reading traditional reports related to progress and cost, and they want to continue viewing this information.
How should the PMO implement a better way to report the project's health?
Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing
manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.
What should the project manager do?
A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on theproject due to a lack of resources. What should the project manager do next?
Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two
members are tense around each other and are taking everything personally.
What should the project manager do?
A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
A project manager has been assigned to a corporate project management office (PMO). They are responsible for leading the development and rollout of updated project management procedures and templates
that would include both predictive and agile approaches,
What should the project manager do after the documents are completed?
A project presently in the testing stage is nearing the closing phase, which will transition the completed project to the company’s operations support team. However, many new members have just been added
to the operations support team who are not familiar with the project and the project's acceptance is now at risk.
What should the project manager do to mitigate this transition risk?
One of the team members is always late to the daily standup meeting. What should the project manager do?
A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner.
Which activity should the project manager undertake?
A local company is developing a new product and, for the first time, using a remote team for the programming tasks of features. The design for the product comes from the
local team. During the third sprint review, the product owner has concerns about the project's outcomes. The remote development team is complaining that they do not
clearly understand the requirements conveyed in the daily standup meetings.
How should the project manager address this situation?
A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project managerrealizes that a significant regulatory feature is missing in the project backlog.
What should the project manager do?
A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design andexecution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitanttoprovide support for the project.
What should the project manager do?
Team members are having a discussion with the project manager. In the last retrospective meeting, the team realized that the obsolete equipment could affect the next
iteration of the project. The team recommends buying new equipment because it is critical to the success of the final deliverable.
What should the project manager do next?
A large project is affecting the neighborhood in which it is located. The neighbors are not satisfied with the project, and their resistance to the project may affect the project
deadline.
What two actions should the project manager take? (Choose two.)
A project team is working to deliver a solution to manage nationwide crisis relief operations. The project team is spending most of its time in
meetings with end users. The meetings have been slowing down project progress.
What should the project manager do to keep the deployment on track while obtaining stakeholder approval?
While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined.
The actual invoice payments received have also been late and were outside of the contracted payment schedule. Recent invoices have only been partially paid.
What should the project manager do?
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do toimprove project performance?
A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand
for this product and wants it to launch as soon as possible.
What should the project manager do to realize this opportunity?
A team has been working on a project for several months, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some
deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.
How can the project manager prevent this situation from happening in the future?
A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support atproject completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology.
What should the project manager do to resolve the conflict?
Some of the team members who are working on a new software tool are in a public space, arguing over a new feature being coded instead of completingthe coding. How should the project manager handle this situation and get the team to complete the task?
A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses toapprove the proposed project plan.
What should the project manager do to gain an understanding of the cause for the resource’s refusal?
On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project managerrealized that some of the keyactivities were scheduled over the holiday periods in the overseas offices.
What shouldthe project manager do next?
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed
concerns about the use of new tools on such an important project.
What should the project manager do?
An agile project team is creating an enterprise workflow system for a company. One of the project team members, who is the system design architect, keeps receiving telephone calls from the users who are
asking questions about the system. The calls are impacting the architect's daily work schedule.
What should the project manager do?
Some project teams are voicing frustration because of conflicting priorities between agile and predictive work in a complex project. Which leadership style would effectively promote collaboration across the
project teams?
A project manager is assigned to a new project. The project management office (PMO) and the project manager agree that this is the right opportunity to include daily standup meetings. The project team has
never used such tools, and a few members are challenging the decision.
What should the project manager do in this situation?
A project manager is performing the role of scrum master for a team of developers. There is a conflict among the developers, generated by differences in how a feature can be delivered.
The project manager organized a few spikes to resolve this conflict.
What should the project manager do next?
A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent
to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?
A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not
be shipped on time, which will impact the schedule.
What should project manager to do next to minimize the impact on the project?
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.
Which evaluation practice should the project lead use to obtain accurate usage data?
Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?
A project manager has been assigned to a new project. There is one team member who never says anything during meetings. After meetings, however, the team member
sends detailed emails with very good suggestions that help with project execution.
How should the project manager guide the team members?
A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the
organization and have varying levels of interest.
Which approach should the project manager use with the stakeholders?
An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significantchange in the technical architecture and an additional release.
What should the project lead do first?
In an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the scheduleperformance index (SPI)?
A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed.
During a recent external audit, the project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.
What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?
A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and thestakeholder notices that an important functionality for their area was not tested.
Which tool should the project manager have used to prevent this situation?
An external project manager is managing the construction of new corporate offices for a large company. The project management plan states that it is
necessary to contract a highly trained external resource to revise and validate an important project component. The client has rejected hiring the external
resource because of the high cost, even though it is within the project budget.
What should the project manager do to resolve this issue?
A company is initiating a project to enhance one of its existing products. All of its products are developed internally.
What should the project manager do?
A project manager has access to risk management tools but chooses to use a quantitative method to evaluate the project risks. During
project execution, the project sponsor asks for an updated risk matrix.
What should the project manager do next?
A company plans to initiate a project involving a new technology. Approval for the project is required.
What should the project manager do?
During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who
is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during
meetings.
How should the project manager handle this moving forward?
A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The
project manager starts to present the budget, but the CEO suddenly asks to end the meeting.
What should the project manager have done to avoid this situation?
A project manager is working on a project that is required to deliver value on an incremental basis. Which action should the project manager take to enable successful project execution?
A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently
implemented.
What should the project manager do?
A project manager has commissioned a design study from a consulting firm to investigate a number of alternatives. The project managerhas a strict policy on the cost of the study and has established a number of cost triggers and trend analyses.
Which tool is the project manager using?
A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.
What should the project manager have done to prevent this?
In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to
ensure the project will remain on track and achieve its goals.
What should the project manager do?
A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project manager knows this teammember could add value to the project.
What should the project manager do to get the most value from this team member?
During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.
What should the project manager do?
A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even
after 1 week of maintenance.
What should the senior project manager do now?
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has
performed the code inspections, however the records are not complete.
What should the project manager do?
A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. In a project review meeting, a key stakeholder reports that the latest documentation
provided by the project manager includes a reference to unrelated products.
What should the project manager do?
Afew key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, theproject schedule is seriouslydelayed.
What should the project manager do?
During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
An agile project is running its second iteration out of six. A marketing director, who is a key stakeholder, contacts the project lead for a highlevel report of the project.
What should the project lead do?
After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for thecompany's newest offering. Theproject manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. Theproject manager fears that thecompetitor's offering is better in multiple ways compared to the project manager's project.
What should the project manager do?
A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified
the project manager that there is a capacity issue for the team doing the installation.
What should the project manager have done to prevent this situation from happening?
An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agilepractices, which are relevantto the project.
What should the project manager do to gain buy-in from the different stakeholders?
A project manager prepared a project benefits management plan. Which of the following should be included in this document?
A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is
dissatisfied, stating that the deliverables do not meet the quality specifications.
What should the project manager do in this situation?
A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of therequirements. The project manager is concerned about scope creep.
Which action should the project manager take to control the scope?
A project manager has been assigned to an education project with the objective of training a workforce in application development. One ofthe deliverables is to provideinternships to the best students in the customer's active projects. However, the customer does not have enough projects in progress right now. The project manager decidesto create several internal projects in order to ensure the internships.
Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose 3)
A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables.How should the project managerrespond?
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around theproject has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?