Question 1

The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.

Under which heading of the change management approach should this requirement be recorded?

Options:

A.

State characteristics

B.

Enabling activities

C.

Resources

D.

Responsibilities

Question 2

As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.

Under which ‘directing a project’ activity is this informal consultation provided?

Options:

A.

Authorize a stage or exception plan

B.

Give ongoing direction

C.

Authorize initiation

D.

Authorize the project

Question 3

During stage 3, the project manager forecasts that the stage-level recycling tolerance will be exceeded. The project manager records the matter in the issue register and sends only an issue report to the project board.

Is this an appropriate application of the progress practice, and why?

Options:

A.

Yes, because an issue report is sufficient whenever a sustainability target is forecast to be missed

B.

Yes, because the forecast shortfall should be treated only as an off-specification in the issue report

C.

No, because the forecast breach should be escalated to the portfolio office rather than the project board

D.

No, because it is an exception which should be escalated in an exception report

Question 4

At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

Options:

A.

Yes, because the project manager is authorized to manage the project on a day-to-day basis within set tolerances throughout each stage, without requiring additional project board decisions

B.

Yes, because the Portfolio Director, as the commissioning authority, has the right to determine the reporting frequency and format that best suit portfolio-level oversight

C.

No, because it is the City Council, rather than the Portfolio Director, that should hold the authority to commit funding across multiple stages of the project

D.

No, because the project board must review the continued viability of the business case and authorize the next stage at each stage boundary, rather than approving multiple stages in advance

Question 5

During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.

The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?

Options:

A.

Yes, because evaluation confirms that completed quality activities are recorded and that the current status is understood by the relevant parties

B.

Yes, because the team manager should review the work-package information, report progress for the agreed period, and notify the project manager when a tolerance is forecast to be exceeded

C.

No, because only the project manager may evaluate the status of a work package and decide what it should report

D.

No, because a forecast work-package tolerance breach should be reported directly to the project board in an exception report

Question 6

While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.

Is this an appropriate application of ‘starting up a project’, and why?

Options:

A.

Yes, because the primary purpose of assessing the project approach at this stage is to clarify the prospective obligations of the project team and each external supplier when delivering the project products

B.

Yes, because the way the project work will be delivered directly influences how the management approaches are designed, and identifying risks early helps ensure the PID accurately reflects how sustainability will be managed

C.

No, because a risk that is classified as manageable does not pose a threat to overall project viability and should be deferred for consideration during the initiation stage when more detailed planning takes place using the traditional delivery method

D.

No, because any sustainability requirements that the project must satisfy should be captured as user quality expectations in the project product description, not as risks in the project log

Question 7

A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.

Is this an appropriate application of the issues practice, and why?

Options:

A.

Yes, because the legislation may affect the resources available to deliver the project

B.

Yes, because external events must be managed outside the project’s agreed controls

C.

No, because legislation should be recorded after its full effect on delivery is known

D.

No, because external events are managed by the business rather than by the project team

Question 8

During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.

Is this an appropriate use of the ‘give ongoing direction’ activity, and why?

Options:

A.

Yes, because a project board member may raise concerns and provide ongoing direction within the authority delegated to the board

B.

Yes, because the senior user has an obligation to formally approve key specialist products produced during stages 2 and 3 as a standard action within the ‘give ongoing direction’ activity

C.

No, because the ‘give ongoing direction’ activity is only triggered when the project manager proactively requests a review by the project board, not when individual board members identify concerns independently

D.

No, because the Heritage Director should first seek the agreement of the full project board before raising individual concerns, to ensure a unified project board position is presented to the project manager

Question 9

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project

B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package

C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options

D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working

Question 10

BuildyBrick is demobilizing after delivering the shopping centre on time and within budget. Before the remaining supplier personnel leave, the project manager checks that the Council’s operations and facilities teams are ready to receive, operate and maintain the completed centre.

Why is this an appropriate application of the ‘confirm project acceptance’ activity?

Options:

A.

Because the project manager should complete the end project performance assessment before any supplier demobilizes

B.

Because the project manager should arrange a celebration before the contractor leaves the site

C.

Because all project information should be archived before the completed project product is accepted

D.

Because the project manager should confirm that handover to the operational and maintenance environment is complete

Question 11

In stage 4, the Heritage Director delegates a review of the inspection arrangements to the Heritage Manager. The Heritage Manager will work with the BuildyBrick CEO and the project manager, then report whether the planned inspections will provide adequate assurance about impacts on historic buildings.

Is this an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?

Options:

A.

Yes, because the principle requires that communication channels between all internal and external project team members remain open and transparent at all times

B.

Yes, because the Heritage Manager needs a clear understanding of what the Heritage Director requires of them and of what they may reasonably expect from the other parties involved

C.

No, because it is the project manager’s responsibility to specify how inspections of historically significant buildings should be planned and executed

D.

No, because the Heritage Director, as senior user, should personally conduct the assurance review of the inspection plans rather than delegating to the Heritage Manager

Question 12

In stage 4, work is late because the survey and utilities teams have not shared information needed by other teams, and morale is falling. The project manager considers a short weekly coordination forum for questions and information sharing, but rejects it solely because it would take time away from delivery.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because the primary responsibility for improving team morale and overall productivity rests with each individual team manager, not the project manager

B.

Yes, because requiring team managers to attend regular coordination meetings diverts their time away from completing their work packages, thereby risking further delays

C.

No, because the project manager should create mechanisms that strengthen coordination and relationships across the project team

D.

No, because the project manager should formally escalate the missed work package deadlines to the project board via an exception report rather than attempting to resolve the issue through coordination meetings

Question 13

Immediately after initiation is authorized, the Head of the Portfolio Office instructs the LouisShopping project to adopt the Council’s mature issue management approach without any project-specific review or tailoring.

Is this an appropriate application of the issues practice, and why?

Options:

A.

Yes, because a mature organizational approach should always be used without alteration

B.

Yes, because portfolio funding gives the portfolio office authority to prohibit all project-level tailoring

C.

No, because the project manager should consider the nature of the products, delivery method and project context when preparing the issue management approach

D.

No, because product version control must be decided outside the issue management approach by the delivery teams alone

Question 14

During the ‘starting up a project’ process, the project manager works with key business, user, and supplier stakeholders to co-create the project product description, clarify the shopping centre’s scope and agree its quality expectations and acceptance criteria.

What is the MAIN benefit of co-creating the project product description in this way?

Options:

A.

It transfers accountability for approving the project product description to the stakeholders involved

B.

It removes the need for a communication management approach later in the project

C.

It confirms that stakeholders will accept the shopping centre when it is handed over

D.

It brings together business, user, and supplier perspectives, improving adoption and reducing handover risks

Question 15

While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.

Is this an appropriate application of the ‘plans’ practice, and why?

Options:

A.

Yes, because data from previous projects should determine the schedule without reviewing the dependencies between the products

B.

Yes, because product dependencies determine sequence, and independent work packages may be planned to run in parallel

C.

No, because work delivered by the same supplier must be scheduled sequentially and should avoid running in parallel

D.

No, because setting work-package tolerances determines the order in which products must be produced

Question 16

BUSINESS CASE

Here are three statements related to the ‘business case’ practice.

In which management product should each statement be recorded?

Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.

Options:

A.

Business case

B.

Benefits management approach

C.

Sustainability management approach

D.

End stage report

E.

Project brief

F.

Commercial management approach

Statement 1:

The project will use a linear-sequential delivery method, and a reputable external supplier will deliver most of the specialist work.

Statement 2:

One sustainability target is to reduce the number of visitors arriving in internal-combustion vehicles. The Chief Technology Officer will implement monitoring technology, and the Business Opportunities Director will