PRINCE2 Project Management Practitioner (Version 7) Questions and Answers
The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.
Under which heading of the change management approach should this requirement be recorded?
As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.
Under which ‘directing a project’ activity is this informal consultation provided?
During stage 3, the project manager forecasts that the stage-level recycling tolerance will be exceeded. The project manager records the matter in the issue register and sends only an issue report to the project board.
Is this an appropriate application of the progress practice, and why?
At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.
Is this an appropriate application of the ‘manage by stages’ principle, and why?
During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.
The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?
While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.
Is this an appropriate application of ‘starting up a project’, and why?
A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.
Is this an appropriate application of the issues practice, and why?
During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.
Is this an appropriate use of the ‘give ongoing direction’ activity, and why?
The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.
Is this an appropriate approach to leading a successful team, and why?
BuildyBrick is demobilizing after delivering the shopping centre on time and within budget. Before the remaining supplier personnel leave, the project manager checks that the Council’s operations and facilities teams are ready to receive, operate and maintain the completed centre.
Why is this an appropriate application of the ‘confirm project acceptance’ activity?
In stage 4, the Heritage Director delegates a review of the inspection arrangements to the Heritage Manager. The Heritage Manager will work with the BuildyBrick CEO and the project manager, then report whether the planned inspections will provide adequate assurance about impacts on historic buildings.
Is this an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?
In stage 4, work is late because the survey and utilities teams have not shared information needed by other teams, and morale is falling. The project manager considers a short weekly coordination forum for questions and information sharing, but rejects it solely because it would take time away from delivery.
Is this an appropriate approach to leading a successful team, and why?
Immediately after initiation is authorized, the Head of the Portfolio Office instructs the LouisShopping project to adopt the Council’s mature issue management approach without any project-specific review or tailoring.
Is this an appropriate application of the issues practice, and why?
During the ‘starting up a project’ process, the project manager works with key business, user, and supplier stakeholders to co-create the project product description, clarify the shopping centre’s scope and agree its quality expectations and acceptance criteria.
What is the MAIN benefit of co-creating the project product description in this way?
While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.
Is this an appropriate application of the ‘plans’ practice, and why?
BUSINESS CASE
Here are three statements related to the ‘business case’ practice.
In which management product should each statement be recorded?
Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.