Weekend Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dumps65

SAP C_S43_2022 Dumps

Page: 1 / 8
Total 80 questions

SAP Certified Application Associate - SAP S/4HANA Asset Management Questions and Answers

Question 1

Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct answers to this question.

Options:

A.

Scheduling period

B.

Start date

C.

Scheduling indicator

D.

Factory calendar

Question 2

Which operations can the responsible person perform after a maintenance order is technically completed? Note: There are 2 correct answers to this question

Options:

A.

Lock or unlock the order

B.

Update the estimated costs

C.

Change the settlement rule

D.

Change the planned costs

Question 3

How does a maintenance request within the phase-based process differ from a maintenance notification in the standard process?

Options:

A.

It always uses the risk-based assessment for prioritization.

B.

It is a new business object with no connection to a maintenance notification.

C.

It is mandatory to assign a task list to the maintenance request.

D.

It contains an additional screening phase where requests can be accepted or rejected.

Question 4

How is Phase-based Maintenance Processing activated in the SAP system? Note: There are 2 correct answers to this question

Options:

A.

Through Best Practices scope items 4HH and 4HI.

B.

Phase-based maintenance is always active in all S/4HANA 2021 editions and above

C.

By installing the corresponding enhancement pack and activating the related business function

D.

By manually activating the corresponding Business Feature in case Best Practices are not used.

Question 5

Which objects can you assign to a Maintenance Service Order Item? Note: There are 2 correct answers to this question.

Options:

A.

Service Product

B.

DIP Profile

C.

Service Work Center

D.

Service Master Record

Question 6

Which objects have been enhanced with linear data in maintenance processes? Note: There are 3 correct answers to this question

Options:

A.

Maintenance plan header

B.

Work order confirmation

C.

Maintenance plan item

D.

Equipment task list

E.

Notification item

Question 7

The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100% which date is relevant for the calculation of future planned dates if the maintenance work is delayed?

Options:

A.

Planned date of the next call, independent of maintenance order dates

B.

Actual finish date of the maintenance order

C.

The date of the final confirmation

D.

Technical completion date of the maintenance order

Question 8

You want to create a maintenance order with an external order operation that includes service items.

How can you achieve this? Note: There are 2 correct answers to this question

Options:

A.

The usage of a model service specification is mandatory.

B.

The assignment of a control key with the service indicator set is mandatory

C.

The actual value entry can be recorded only via the service entry sheet

D.

The assignment of a control key with key externally processed operation is sufficient.

Question 9

How can you assign a material BOM to a piece of equipment?

Options:

A.

Via field model number in the equipment master

B.

Via material BOM header in the serialization data

C.

Via creation of an equipment BOM

D.

Via field construction type

Question 10

Which functionalities are available in the SAP Service and Asset Manager (SAP Asset Manager) for a maintenance worker? Note: There are 2 correct answers to this question

Options:

A.

Confirm time sheets

•Attach documents

B.

Schedule resources

•Change task list

C.

Display maps

•Display and maintain technical objects

D.

Change BOM

•Create a work order on the ESRI map

Question 11

Which requirements have to be fulfilled so that an Inspection Checklist with Inspection Lots is generated? Note: There are 2 correct answers to this question.

Options:

A.

An Inspection Plan and a technical object must be assigned to the same class.

B.

A PM task list with inspection point type must be assigned to the maintenance order

C.

An object list must have been generated manually or automatically.

D.

A checklist type must be assigned to the maintenance order header.

Question 12

During the implementation project you need to define the organizational units relevant for Plant Maintenance. Which of the following objects can you directly assign to a maintenance plant? Note: There are 2 correct answers to this question

Options:

A.

Maintenance work center

B.

Maintenance planner group

C.

Organizational unit

D.

Storage location

Question 13

Which component is used to display data in the Technical Object Breakdowns and Technical Object Damages app?

Options:

A.

SAP Asset Strategy and Performance Management

B.

SAP Lumira Designer

C.

SAP S/4HANA Core Data Services

D.

SAP Predictive Analysis

Question 14

You want to assign components to a General Maintenance Task List. What are prerequisites for assigning material components to a task list operation? Note: There are 2 correct answers to this question

Options:

A.

Assign the header material of a material BOM as assembly to a task list operation.

B.

Assign the BOM usage for free assignment of material in Customizing

C.

Assign the header material of a material ROM to the assembly field of the task list header

D.

Assign a piece of equipment with allocated material BOM to a task list operation.

Question 15

What do you have to consider regarding a cross-plant planning scenario?

Options:

A.

Multiple maintenance plants are assigned to a planning plant (n: 1).

B.

Only a maximum number of five maintenance plants can be assigned to a planning plant.

C.

Multiple planning plants are assigned to a maintenance plant (m: 1).

D.

It is only possible within the same company code.

Question 16

What do you need to configure to enable entries in the action log of a piece of equipment?

Options:

A.

Define history related fields in the usage period customizing.

B.

Activate the change documents for the equipment category.

C.

Define the corresponding history related field for the equipment reference category.

D.

Activate the change documents for the equipment reference category.

Question 17

You want to display additional document information within the document flow of a maintenance order.

For which type of document must this be customized?

Options:

A.

Invoice

B.

Purchase order

C.

Goods movement

D.

Service entry sheet

Question 18

Where can the maintenance planner perform a material availability check? Note: There are 2 correct answers to this question?

Options:

A.

Via the SAP Fiori app "Manage Maintenance Order List"

B.

Within the SAP Fion-based background job

C.

Via the SAP Fiori app "Maintenance Scheduling Board"

D.

Via the SAP Fiori epp "Manage Maintenance Planning Buckets"

Question 19

The planner adds non-stock material in a released maintenance order. What are possible options within the maintenance order? Note: There are 3 correct answers to this question?

Options:

A.

A purchase requisition can be created automatically as soon as the order is saved.

B.

The maintenance order can be set to TECO before the invoice is created

C.

A goods receipt can be posted after the maintenance order is technically completed.

D.

A purchase order is created automatically as soon as the order is saved.

E.

A purchase requisition will ALWAYS be created as soon as the order is saved.

Question 20

What do you have to consider when implementing Ul technologies in SAP S/4HANA Asset Management? Note: There are 2 correct answers to this question

Options:

A.

Web Dynpro apps can be used in the SAP Fiori Launchpad.

B.

SAP Fiori Launchpad supports only SAPUIS apps.

C.

SAP GUI for HTML can be used in the SAP Fiori Launchpad.

D.

The cloud version can also use SAP GUI for Windows.

Question 21

Which of the following is a prerequisite for external refurbishment?

Options:

A.

Define the order type for external refurbishment.

B.

Select the material group for externally refurbished materials.

C.

Assign an external work center to a maintenance order operation

D.

Activate the subcontracting indicator in an external activity.

Question 22

What are mandatory characteristics of orders with Operation Account Assignment (OAA)? Note: There are 3 correct answers to this question

Options:

A.

Overall costs are dynamically summed up on the header level.

B.

A technical object must be assigned to an order operation

C.

Costs are stored only for the operation object

D.

Purchase requisitions have the operation as account assignment.

E.

The settlement rule is maintained on the header level.

Question 23

You settle a refurbishment order with the batches (valuation types) having price control standard price. What is the effect? Note. There are 2 correct answers to this question.

Options:

A.

The effective costs are posted as a credit memo to a price difference account

B.

The effective costs are posted to the respective batch (valuation type).

C.

The goods receipt for the batch refurbished is posted with the value of the standard price.

D.

The goods receipt for the batch refurbished is posted with the value of the moving average price

Question 24

You want to set up a scenario for regular maintenance. The first event should take place after 1 year, after that, it is a regular cycle of 6 months. Which parameter do you have to use to map this in the system?

Options:

A.

Package hierarchy

B.

Scheduling indicator

C.

Maintenance package offset

D.

Cycle modification factor

Page: 1 / 8
Total 80 questions