SAP C_TS413_2021 Dumps

SAP Certified Application Associate - SAP S/4HANA Asset Management Questions and Answers

Question 1

The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100%. Which date is relevant for the calculation of future planned dates if the maintenance work is delayed?

Options:

A.

Technical completion date of the maintenance order

B.

Date of the final time confirmation

C.

Planned end date of the maintenance order

D.

Planned date of the next call, independent of maintenance orderdates

Question 2

Which of the following statements are correct for SAP S/4HANACIoud - Asset Management? Note: There are 2 correct answers to this question.

Options:

A.

You do NOT have access to the SAP S/4HANA back end system.

B.

You have access to the SAP S/4HANA back end system.

C.

You can configure SAP S/4HANA Cloud via the SAP Asset Intelligence Network.

D.

You can configure SAP S/4HANA Cloud via the self-service configuration UI.

Question 3

You need to create a new functional location. Which actions can you perform with the SAP Fiori app Create Technical Object? Note:There are 3 correct answers to this question.

Options:

A.

Edit classification data and characteristics.

B.

Change a reference location.

C.

Assign a subordinate piece of equipment.

D.

Assign documents.

E.

Create a measuring point.

Question 4

What does a virtual data model provides

Options:

A.

A copy of the database optimized for analytical purpose

B.

Ready to use business reports

C.

consumption ready views of data

D.

Reporting tools for users

Question 5

You want to schedule a performance-based maintenance plan. Which parameters are mandatory? Note: There are 2 correct answers to this question.

Options:

A.

Shift factors

B.

Start counter reading

C.

Estimated annual performance

D.

Scheduling period

Question 6

Which of the following can you assign to an equipment category via a view profile? Note: There are 2 correct answers to this question.

Options:

A.

Configuration

B.

Manufacturer data

C.

Serial data

D.

Warranty

Question 7

You want to create a maintenance order with an external order operation with service items. Which of the following statements arecorrect? Note: There are 3 correct answers to this question.

Options:

A.

The usage of a model service specification is mandatory.

B.

The assignment of a control key with the service indicator set is mandatory.

C.

The actual value entry can only be recorded via the service entrysheet.

D.

The assignment of service master records to an order operation is optional.

E.

The assignment of a control key with the service indicator set is mandatory.

Question 8

You want to display additional document information within the document flow of a maintenance order. For which type of documentmust this be customized?

Options:

A.

Invoice

B.

Service entry sheet

C.

Purchase order

D.

Goods movement

Question 9

Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct answers to this question.

Options:

A.

Scheduling period

B.

Factory calendar

C.

Start date

D.

Scheduling indicator

Question 10

What is the function of the print diversion setting?

Options:

A.

It enables you to define which shop papers are printed as a system default.

B.

It enables you to determine which papers are printed for the technician.

C.

It tells the system that a shop paper for an order is ready to be printed.

D.

It enables you to chose a printer based on certain fields in the order.

Question 11

You want to create a new functional location. Which configurationsteps are required? Note: There are 2 correct answers to this question.

Options:

A.

Define the functional location category.

B.

Define the number range for the functional location category.

C.

Define the reference functional location.

D.

Define the structure indicator.

Question 12

Which functions are available in the Resource Scheduling for Maintenance Planners app? Note: There are 2 correct answers to this question.

Options:

A.

Cancel dispatched maintenance order operations.

B.

Schedule and dispatch maintenance operations by shifts.

C.

Monitor maintenance order operations due in the next 4 weeks.

D.

Print job papers from a maintenance order.

Question 13

Where can the maintenance planner perform a material availability check? Note: There are 2 correct answers to this question.

Options:

A.

Via the Manage Maintenance Order List SAP Fiori app

B.

Via the Change Maintenance Order SAP Fiori app

C.

Within the SAP Fiori-based background job

D.

Via the multi-level order list (SAP GUI)

Page: 1 / 9
Total 87 questions