Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dumps65

SAP C_TS422_2021 Dumps

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Question 1

Which materials have a negative quantity in a bill of materials or in a recipe?

Options:

A.

Bulk materials

B.

Co-products

C.

By-products

D.

Waste products

E.

Continuous flow materials

Question 2

Which master data object governs the relationship between supply source and demand source in the Kanban process?

Options:

A.

Control cycle

B.

Production supply area

C.

Replenishment strategy

D.

Rate routing

Question 3

You need to model goods receipt processing time in detailed scheduling. Whic modeling options do you have?

Options:

A.

Model a transportation resorce in the location master.

B.

Model a seperate resource in the production data structure.

C.

Model a resource inbound in the location master.

D.

Model a handling resource in the location master and goods receipt time in the material master.

Question 4

What could be the reason for multiple commitment of invidula capacities, where several operations have the same scheduled dates on a work center (or resource) after planing?

Options:

A.

The work center has several invidula capacities.

B.

The finite Scheduling indicator is NOT set in the strategy profile.

C.

The Change Planning Direction indicator is set in strategy profile.

D.

Alternative work centers are fully occupied.

Question 5

Which mhetods are available for goods issue posting of material components for process orders?

Options:

A.

Transfer order

B.

Picking list

C.

Blackflushing

D.

Kanban

Question 6

What are the consequences if the Dispatched operation status is set for a production order operation?

Options:

A.

You can reschedule the operation using midpoint scheduling in a planning table.

B.

You can reschedule the operation using finite scheduling in planning table

C.

You can reschedule the operation using lead time scheduling in a planning table

D.

You can reschedule the order using infinite scheduling in a planing table

Question 7

What type of time element can be reduced by strategy settings while dispatching?

Options:

A.

Transportation time

B.

Wait time

C.

Queue time

D.

Setup time

Question 8

Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?

Options:

A.

Run MRP with quota arrangement.

B.

Run MRP with automatic selection of production version.

C.

Assign planned orders manual lying the planning table.

D.

Run PP/DS heuristics for repetitive manufacturing.

Question 9

What does a line hierarchy in repetitive manufacturing represent?

Options:

A.

A production line with a parallel sequence in the routing

B.

A production line with prioritized alternative work centers

C.

A production line with more than one work center

D.

A production line with an alternative sequence in the routing

Question 10

Which item statuses can you select inside a material BOM?

Options:

A.

Service

B.

Sales

C.

Quality management

D.

Engineering

Question 11

Which of the following elements does MRP take into account during net requirement calculation?

Options:

A.

Purchase orders

B.

Lot size

C.

Maximum stock level

D.

Safety stock

Question 12

You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?

Options:

A.

Material requirements planning

B.

Manual planning without check

C.

Forecast planning

D.

Consumption-based planning

Page: 1 / 8
Total 82 questions