SAP E_ACTCLD_23 Dumps

Page: 1 / 17
Total 168 questions

SAP Certified Specialist - SAP Activate for Cloud Solutions Project Manager Questions and Answers

Question 1

What is the purpose of a firm-up sprint?

Options:

A.

To revise the release plan and sprint plan

B.

To run an end-to-end integration test

C.

To demonstrate functionality from previous sprints

D.

To perform string test

Question 2

Implementation of which solutions are supported by the SAP Activate Framework?

Options:

A.

C4C

B.

SAP S/4HANA On-Premise

C.

SAP S/4HANA Cloud

D.

BW/4HANA On-Premise

E.

SAP SuccessFactors

Question 3

What is the objective of a sprint retrospective meeting? Please choose the correct answer.

Options:

A.

Review and prioritize the backlog

B.

Improve the SCRUM process

C.

Define the stakeholder management approach

D.

Provide formal feedback to the project manager

Question 4

What kind of user is enabled by SAP Cloud ALM for operations to identify disruptions and react to them? Note: There are 2 answers to this question.

Options:

A.

Line of business user

B.

Reference user

C.

Communication user

D.

IT user

E.

End user

Question 5

Which artifacts are part of the Solution Adoption workstream? 3 correct answers

Options:

A.

Learning Content

B.

Detailed Design-Business Processes

C.

End User Learning Needs Analysis

D.

Change Managament Roadmap

E.

Project Plan

Question 6

What can be found in the SAP Solution Implementation Roadmaps?

Options:

A.

Value Maps

B.

Deliverables in each Phase

C.

Accelerators to be used in the Project Library

D.

Detailed description of implementation tasks

Question 7

What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of SAP Activate? Please choose the answer.

Options:

A.

Learning plan

B.

Project Documentation

C.

Project Charter

D.

Knowledge transfer to end users

Question 8

What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 answers to this question.

Options:

A.

On-premise only

B.

Start with SAP Best Practices

C.

Validate solution

D.

Premium engagement ready

E.

Fixed scope

Question 9

In which of the following project phases is it important to plan and schedule data loads followed by load validation activities?

Options:

A.

Prepare

B.

Explore

C.

Deploy

D.

Realize

Question 10

What can cloud-centric customers do with SAP Cloud ALM?

Options:

A.

Manage the Intelligent Enterprise

B.

Update cloud releases

C.

Configure their cloud products

D.

Track cloud services

Question 11

What are some goals of the Fit-to-Standard workshops?

Options:

A.

To identify relevant data migration objects.

B.

To review the SAP Best Practices in the starter system.

C.

To identify customer-defined configuration changes within the scope of the service.

D.

To define the Integration and API List for the solution.

E.

To gather input for customer-defined customizations to the solution.

Question 12

In which SAP Activate methodology phase does the team complete the Integration Validation? Please choose the correct answer.

Options:

A.

Realize

B.

Deploy

C.

Explore

D.

Prepare

Question 13

What is Scrum of Scrums?

Options:

A.

Integration meeting among the various Scrum teams

B.

Alternative to regular Scrum process for smaller teams

C.

Mechanism for gathering and validating requirements

D.

Frequent inspection of code and configuration prior to quality gates

Question 14

What do you do during Sprint Execution? Please choose the answer.

Options:

A.

Measure the sprint progress with a percentage complete report

B.

Present status of selected user stories in the sprint scope on a scrumboard

C.

Hold a retrospective at the end of each week

D.

End a sprint when the sprint backlog items are all complete

Question 15

In what respect is SAP Activate Methodology different from the ASAP Methodology? Please choose the answer.

Options:

A.

Includes Fit/Gap analysis instead of Blueprint

B.

Supports cloud deployments

C.

Leverages iterative incremental build

D.

Supports only new implementations

Question 16

How do you gain access to the SAP Activate Methodology Jam site?

Options:

A.

Send e-mail to SAP contact address

B.

Register on SAP Service Marketplace

C.

Join SAP S/4HANA group on SAP Community Network

D.

Submit e-mail address via online form

Question 17

What are some characteristics of SAP S/4HANA Cloud?

Options:

A.

SAP S/4HANA Cloud provides additional functionality for customers that require broad extensions and deep configuration capabilities.

B.

SAP S/4HANA Cloud includes quarterly innovation cycles.

C.

SAP S/4HANA Cloud is single-tenant; meaning your service runs in a dedicated environment.

D.

SAP S/4HANA Cloud is multi-tenant, meaning your service runs in a shared environment.

E.

SAP S/4HANA Cloud runs in an infrastructure with private, managed services for SAP solutions.

Question 18

What are some of the values of SAP Cloud ALM for implementation? 3 correct answers

Options:

A.

Accelerated time to market

B.

Central cost and effort management

C.

NO additional cost of product

D.

Pre-delivered SAP Activate tasks

E.

Comprehensive document repository

Question 19

Which of the following are levels in the structure of an SAP Best practices solution package? There are 2 answers to this question.

Options:

A.

Configuration guides

B.

Building blocks

C.

Scope items

D.

Business process scenarios

Question 20

What types of extensibility are supported directly in the SAP S/4HANA Cloud solution?

Options:

A.

Managed Extensibility

B.

Classic Extensibility

C.

In-App (Key User) Extensibility

D.

Side-by-Side Extensibility

Question 21

Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 answers to this question.

Options:

A.

System consolidation

B.

Consolidation through online data replication

C.

Security migration

D.

Extraction of business units

E.

System upgrade

Question 22

How can the project manager help to keep momentum in the project and help to keep the customer involved?

Options:

A.

Increase the number of Q-Gates

B.

Add customer resources to the project to reduce the need for formal training

C.

Leverage agile cycles to build and test the solution

D.

Walk through the solution processes with the stakeholders

Question 23

Which of the following are benefits of using ready-to-use content? Note: There are 2 correct answers to this question.

Options:

A.

Predictable results

B.

Fast time-to-value

C.

Exhaustive solution documentation

D.

Minimized total cost of ownership

Question 24

What is the purpose of the Solution Validation activity in the Explore phase? There are 3 answers to this question.

Options:

A.

To identify gaps

B.

To log additional scope items

C.

To verify technical installation

D.

To challenge changes to standard

E.

To educate project participants

Question 25

Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?

Options:

A.

Timelines of the sprint many differ dues to the workload

B.

User Stories are in Ready state for only the first 2 to 3 sprints

C.

Go-live scope is fixed on the first of January the following year

D.

Project scope and planning are compelted and final

Page: 1 / 17
Total 168 questions