Pre-Summer Sale Discount Flat 70% Offer - Ends in 0d 00h 00m 00s - Coupon code: 70diswrap

Scrum PSM-I Dumps

Page: 1 / 30
Total 298 questions

Professional Scrum Master I Questions and Answers

Question 1

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

Options:

A.

Identifying high priority process improvements for the next Sprint.

B.

The order of items in the Product Backlog.

C.

How the team collaborates.

D.

Documenting acceptance criteria for items in the next Sprint.

Question 2

When can a Development Team cancel a Sprint?

Options:

A.

It can’t. Only Product Owners can cancel Sprints.

B.

When functional expectations are not well understood.

C.

When the Product Owner is absent too often.

D.

When the selected Product Backlog items for the Sprint become unachievable.

E.

When a technical dependency cannot be resolved.

Question 3

Which two things are appropriate for a Scrum Master to do if the Development Team doesn’t have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose two.)

Options:

A.

Coach the Development Team to improve its skills, tools, and infrastructure over time and adjust the Definition of “Done” accordingly.

B.

Encourage the Product Owner to accept partially “Done” increments until the situation improves.

C.

Refocus the current Sprint on establishing the Development Team’s infrastructure instead of delivering an increment.

D.

Declare the Development Team not ready for Scrum.

E.

Have the Development Team establish a Definition of “Done” that is actually possible to achieve given current circumstances.

Question 4

When do Development Team members take ownership of a Sprint Backlog item?

Options:

A.

At the Sprint planning meeting.

B.

During the Daily Scrum.

C.

Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each one may be done by an individual Development Team member.

D.

Whenever a team member can accommodate more work.

Question 5

The Definition of Done serves which three purposes?

(choose the best three answers)

Options:

A.

Create a shared understanding of when work is complete.

B.

Guide the Developers on how many Product Backlog items to select for the

Sprint.

C.

Increase transparency.

D.

Describe the work that must be mostly done before the Sprint is allowed to end.

E.

Describe the purpose, Objective, and timebox Of each Scrum event.

Question 6

(How is management that is external to the Scrum Team involved in the Daily Scrum?

Choose the best answer.)

Options:

A.

Management gives an update at the start of each Daily Scrum.

B.

Managers are not required at the Daily Scrum.

C.

The Product Owner represents their opinions.

D.

The Scrum Master speaks on their behalf.

Question 7

Which three questions might be answered by Development Team members at the Daily Scrum? (Choose three.)

Options:

A.

How is the Sprint proceeding?

B.

What did I do yesterday that helped the Development Team meet the Sprint Goal?

C.

Why were you late?

D.

What will I do today to help the Development Team meet the Sprint Goal?

E.

How many hours did I spend on the project yesterday?

F.

What will I be working on tomorrow?

G.

Do I see any impediment that prevents me or the Development Team from meeting the Sprint Goal?

Question 8

What is the timebox for the sprint Review? (choose the best answer)

Options:

A.

1 day

B.

4 hours for a one-month Sprint.

C.

As long as needed

D.

2 hours for a one-month Sprint.

Question 9

What two factors are best considered when establishing the Sprint length? (Choose two.)

Options:

A.

The organization has mandated similar length sprints.

B.

The level of uncertainty over the technology to be used.

C.

The frequency at which team formation can be changed.

D.

The risk of being disconnected from the stakeholders.

Question 10

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

Options:

A.

Without a new vocabulary as a reminder of the change, very little change may actually happen.

B.

The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.

C.

Management may feel less anxious.

D.

All answers apply.

Question 11

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

Options:

A.

The Scrum Team.

B.

The Product Owner.

C.

The Developers.

D.

The Project Manager.

Question 12

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

Options:

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Development Team’s ability to deliver.

D.

Its Definition of “Done”.

E.

All of the above.

Question 13

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Options:

A.

The Sprint Backlog.

B.

The Sprint Goal

C.

The release plan.

D.

Sprint Review minutes.

Question 14

Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item? (choose the best two answers)

Options:

A.

Declare the Scrum Team not ready for Scrum.

B.

Coach the Scrum Team to improve its skills, tools and environment over time and adjust the Definition of Done accordingly.

C.

Encourage the Product Owner to accept partially done Increments until the

situation improves.

D.

Refocus the current Sprint on establishing the Scrum Team ' s environment instead of delivering an Increment.

E.

Have the Scrum Team establish a Definition of Done that is actually possible to achieve given current circumstances.

Question 15

What is the function or purpose of management in Scrum?

(choose the best answer)

Options:

A.

To identify and remove people that are not working hard enough.

B.

To monitor the productivity of the Developers.

C.

To present the Scrum Teams with insights and resources that help them improve.

D.

To continually monitor staffing levels of the Scrum Team.

Question 16

Who is responsible for the Sprint Backlog?

(choose the best answer)

Options:

A.

The Scrum Team.

B.

The Scrum Master.

C.

The Developers.

D.

The Product Owner.

Question 17

A properly functioning Scrum Team will have at least one Release Sprint and may well have several.

Options:

A.

True

B.

False

Question 18

When multiple teams work together on the same product, each team should maintain a separate Product Backlog.

Options:

A.

True

B.

False

Question 19

What may be included in the Sprint Backlog? (choose the best answer)

Options:

A.

User Stones

B.

Tasks

C.

Use Cases

D.

Tests

E.

Any of the above (or others) which ate a decomposition of the selected Product Backlog items

Question 20

True or False: A scrum Master Fulfills me same role as a traditional project Manager.

Options:

A.

True

B.

False

Question 21

What is a Development Team responsible for? (Choose two.)

Options:

A.

Resolving internal team conflicts.

B.

Reporting productivity.

C.

Selecting the Product Owner.

D.

Organizing the work required to meet the Sprint Goal.

Question 22

(Who must attend the Daily Scrum?

Choose the best answer.)

Options:

A.

The Scrum Master and Product Owner.

B.

The Developers and Scrum Master.

C.

The Developers.

D.

The Developers and Product Owner.

E.

The Scrum Team.

Question 23

Which two things should the Development Team do during the first Sprint? (Choose two.)

Options:

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Define the major product features and release plan architecture

E.

Create an increment of potentially releasable software.

Question 24

When many Scrum Teams are working on a single product, what best describes the Definition of Done?

(Choose the best answer.)

Options:

A.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a

hardening Sprint.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

D.

All Scrum Teams must have a Definition of Done that makes their combined work potentially releasable.

Question 25

Who is responsible for tracking the remaining work of the Sprint?

Options:

A.

The Development Team.

B.

The Scrum Master.

C.

The Project Manager.

D.

The Development Team is consultation with the Product Owner.

E.

The Product Owner.

Question 26

The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.

Options:

A.

True

B.

False

Question 27

User documentation is part of your definition of “Done”. However, there aren ' t enough technical writers for all teams. Your Development Team doesn ' t have a technical writer. What should you do?

Options:

A.

Form a separate team of technical writers that will work on an on-demand basis for the various Product Owners. Work order will be first in, first out.

B.

Let the user documentation remain undone and accumulate until after the last development Sprint. It will then be done by any available technical writers.

C.

Wait until you have a technical writer on your Development Team to take care of this.

D.

Your Development Team is still responsible for creating user documentation. In this case, the Development Team members will write it.

Question 28

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give? (Choose the best answer.)

Options:

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the people doing the work.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

Question 29

Which statement best describes the Sprint Review?

Options:

A.

It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.

B.

It is a demo at the end of the Sprint for everyone in the organization to check on the work done.

C.

It is a mechanism to control the Development Team’s activities during a Sprint.

D.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.

Question 30

Every Scrum team must have a Product Owner and Scrum Master.

Options:

A.

True. Outcomes affected by their participation and availability.

B.

False. A Product Owner can be replaced by a business analyst in the Development Team.

C.

False. A Scrum Master is only required when asked for by the Development Team.

D.

True. Each must be 100% dedicated to the Scrum Team.

Question 31

True or False: An increment must be released to customers or users at the end of each sprint.

Options:

A.

True

B.

False

Question 32

Why should the Product Owner be present at the Daily Scrum?

Options:

A.

He/She doesn’t need to be there.

B.

To hear about impediments in functionality.

C.

To represent the stakeholders’ point of view.

D.

To participate as a Scrum Team member.

Question 33

You are the Scrum Master of a new, to be developed product. Development is going to require 45 people. What is a good first question for you to suggest the group thinks about when forming into teams?

Options:

A.

How will we make sure all teams have the right amount or expertise?

B.

What is the right mixture of senior and junior people on each team?

C.

Who are going to be the team leads?

D.

Who are the subject matter experts on each team?

Question 34

Which outcome is expected as Scrum Teams mature?

Options:

A.

They will improve their definition of “Done” to include more stringent criteria.

B.

The Sprint Retrospectives will grow to be longer than 4 hours.

C.

There is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.

D.

Sprint Reviews will no longer be needed.

E.

A Scrum Master is no longer needed since they are a mature team now.

Question 35

You are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the developers come to you complaining that work identified for the upcoming two Sprints will require full-time commitment from a technical specialist who is external to the teams. What are two key concerns for the Scrum Master to take into account in this situation? (Choose two.)

Options:

A.

The desire to maintain a stable velocity.

B.

The benefit of Development Teams figuring out a solution for themselves.

C.

The need to have enough work to keep all Development Team members busy.

D.

The ability of the Development Teams to produce integrated Increments.

Question 36

Multiple Scrum Teams working on the same project must have the same Sprint start date.

Options:

A.

True

B.

False

Question 37

What is the role of management in Scrum?

Options:

A.

To facilitate the Scrum Teams with insights and resources that help them improve.

B.

To monitor the Development Team’s productivity.

C.

To identify and remove people that aren’t working hard enough.

D.

To continually monitor staffing levels of the Development Team.

Question 38

Who is accountable for tracking the remaining work toward the Sprint Goal? (Choose the best answer.)

Options:

A.

The Developers.

B.

The Scrum Master.

C.

The Product Owner.

D.

The Project Manager.

Question 39

What does it mean for a Development Team to be cross-functional?

Options:

A.

The Development Team includes not only developers but also business analysts, architects, and testers.

B.

The Development Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment of software.

C.

Developers on the Development Team work closely with business analysts, architects, developers and testers who are not on the team.

D.

The Development Team is a virtual team drawing from separate teams of business analysts, architects, developers and testers.

Question 40

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.

A good way to continue is:

Options:

A.

The Development Team makes sure that all of the selected scope per Sprint is as “Done” as possible. The undone work is estimated and added to the Sprint Backlog of the next Sprint, so it doesn’t mess up the Product Backlog.

B.

Add enough people to the Development Team for the deadline to be made.

C.

The opportunity to inspect and adapt is lost. Opaqueness has replaced transparency. Predictability has dropped below zero. The produced software is not usable. As the rules of Scrum have not been respected, it is the Scrum Master’s duty to assess whether repair is possible, or a restart with a more reliable team. If not, the Scrum Master should cancel the project.

D.

The Development Team should remind Marian to find funding for enough Release Sprints in which the remaining work can be done.

Question 41

A Sprint Retrospective should be held:

Options:

A.

At the end of each Sprint.

B.

At the beginning of each Sprint.

C.

Only when the Scrum Team determines it needs one.

D.

At the end of the last Sprint in a project or a release.

Question 42

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

Options:

A.

Recruit additional Developers before the work can begim

B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.

C.

The Developers work overtime during this Sprint

D.

Cancel the Sprint

E.

Remove or change selected Product Backlog items.

Question 43

What does n mean tor a scrum Team to be cross-function at? (choose the best answer)

Options:

A.

The Scrum Team includes skilled individuals who together have all the skins necessary to create value each sprint

B.

Developers on the Scrum Team work closely with business analysis architects developers, and testers who are not on the team

C.

The Scrum Team includes not only developers but also business analysts, architects, and testers

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers

Question 44

What is the best suited structure for Development Teams in order to produce integrated Increments?

Options:

A.

Each Development Team works only one technical layer of the system (e.g. GUI, database, middle tier, interfaces).

B.

Each Development Team develops functionality from beginning to end throughout all technical layers.

Question 45

In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however.

Which of the following two actions should the Scrum Master support? (Choose two.)

Options:

A.

Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.

B.

Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.

C.

Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the Development Team to make a complete forecast. Then start the Sprint.

D.

Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.

E.

Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.

Question 46

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum?

(choose the best two answers)

Options:

A.

Identification of impediments that may prevent the Developers from achieving the Sprint Goal.

B.

An update of completed tasks and of the remaining work so the Scrum Master

can plan the next day.

C.

An updated Scrum board to make Sprint progress transparent for the

stakeholders.

D.

A shared understanding of the most important work to be undertaken next to

achieve the best possible progress toward the Sprint goal.

E.

A status report for the upper management indicating what each individual has done, will be doing, and what is impeding him/her.

Question 47

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

Options:

A.

The Developers after clarifying requirements with the Product Owner

B.

The Scrum Master.

C.

The Product Owner with input from the Developers.

D.

The Developers, alone.

E.

The most senior people in the organization, including architects and subject matter experts.

Question 48

Who can abnormally terminate a Sprint?

Options:

A.

The Scrum Master

B.

The Development Team or its members.

C.

The Product Owner

D.

The Stakeholders

Question 49

How do you know that a Scrum Team is cross-functional? (Choose the best answer.)

Options:

A.

Scrum Team has all the skills to create an increment by the end of every Sprint.

B.

A few of the Development Team members pair program and do Test Driven Development.

C.

There are no conflicts within the Scrum Team.

D.

Every member of the Scrum Team is able to perform every task.

Question 50

The Product Owner must release each Increment to production.

Options:

A.

When it makes sense.

B.

To make sure the Development Team is done every Sprint.

C.

Whenever the product is free of defects.

D.

Without exception.

Question 51

Which of the following is an example of an Increment? (Choose the best answer.)

Options:

A.

A plan for the overall product release.

B.

A mock-up of the product marketing materials.

C.

A design for the product.

D.

A product roll-out plan.

E.

A valuable, useful set of products featured.

F.

All of the above.

Question 52

Select two ways in which technical debt impacts transparency. (Choose two.)

Options:

A.

When calculated and estimated, the total amount of technical debt shows exactly how long until the Product Owner can release the Increment.

B.

It leads to false assumptions about the current state of the system, specifically of an Increment being releasable at the end of a Sprint.

C.

As development progresses and code is added, the system becomes more difficult to stabilize, which results in future work being slowed down in unpredictable ways.

D.

It enhances transparency for the Product Owner as a Development Team is not allowed to do additional feature development in a Sprint as long as there is technical debt.

Question 53

user documentation is part of your Definition of Done. However, there are not enough technical

writers for all teams. Your Scrum Team does not have a technical writer. What should the

Scrum Team do?

(choose the best answer)

Options:

A.

The Developers on the Scrum Team should write the user documentation

B.

Wait until you have a technical writer on your Scrum Team to take care of this.

C.

Form a separate team of technical writers that will work on an on-demand basis tor

the various Product Owners. Work order will be first in, first out.

D.

Let the user documentation remain undone and accumulate until after the last

development Sprint. It will then be done by any available technical writers.

Question 54

Which of the following are topics for the Developers to discuss at the Daily scrum as they inspect their progress toward the Sprint Goal?

(choose the best three answers)

Options:

A.

what have we learned since yesterday, and now should we modify our plan to increase our ability to meet the Sprint Goal?

B.

Are mere any impediments Clocking progress toward the sprint Goal?

C.

What will I be working on tomorrow?

D.

Are mere any decisions that need to be made to maintain progress toward the sprint Goal?

E.

Why were you late?

F.

How many hours Old I spend on the project yesterday

G.

win todays work negatively impact our ability to meet the sprint Goal for the Split following this one?

Question 55

Who has the final say on the order of the Product Backlog?

Options:

A.

The Development Team.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Stakeholders.

E.

The CEO.

Question 56

Who starts the Daily Scrum?

Options:

A.

The person coming in last. This encourages people to be on time and helps to stay within the time-box.

B.

Whoever the Development Team decides should start.

C.

The person who has the token.

D.

The Scrum Master. This ensures that the Development Team has the meeting and stays within the time-box.

E.

The person who last broke the build.

Question 57

What two techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which development techniques to apply? (Choose two.)

Options:

A.

Involve the complete Development Team.

B.

Use coaching techniques; such as open questions and active listening.

C.

Ask an external technical specialist to make the decision.

D.

Send every team member to the company’s HR department to express their concerns.

Question 58

During a Sprint Retrospective, for what is the Scrum Master responsible?

Options:

A.

Prioritizing the resulting action items.

B.

Participating as a Scrum team member and facilitating as requested or needed.

C.

Acting as a scribe to capture the Development Team’s answers.

D.

Summarizing and reporting the discussions to management.

Question 59

What are three ways Scrum promotes self-management?

Options:

A.

By having the Scrum Master protect the Scrum Team.

B.

By the Scrum Team deciding what work to do in a Sprint.

C.

By being a lightweight framework.

D.

By removing titles for Scrum Team members.

Question 60

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

Options:

A.

Opportunities to insect and adapt the Sprint Backlog are lost.

B.

Impediments are raised and resolved more slowly.

C.

The Product Owner cannot accurately report progress to the stakeholders.

D.

Too much work is spent updating the Scrum board before the meeting.

E.

The Scrum Master loses the ability to update the Gantt chart properly.

F.

The Sprint plan may become inaccurate.

Question 61

User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What should the Scrum Team do?

(choose the best answer)

Options:

A.

Let the user documentation remain undone and accumulate until after the last development Sprint. It will then be done by any available technical writers.

B.

The Developers on the Scrum Team should write the user documentation.

C.

Wait until you have a technical writer on your Scrum Team to take care of this.

D.

Form a separate team of technical writers that will work on an on-demand basis for the various Product Owners. Work order will be first in, first out.

Question 62

How do you know that a Development Team is cross-functional?

Options:

A.

Development Team has all the skills to create a potentially releasable increment by the end of every Sprint.

B.

A few of the Development Team members pair program and do Test Driven Development.

C.

There are no conflicts within the Development Team.

D.

Every member of the Development Team is able to perform every task.

Question 63

(You have just been hired by a company new to Scrum. Management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario.

Choose the best two answers.)

Options:

A.

There should be only one Product Owner.

B.

The product has one Product Backlog.

C.

Each Scrum Team should have a separate Product Backlog.

D.

There should be six Product Owners, reporting to a Chief Product Owner.

E.

There should be six Product Owners, one for each Scrum Team.

Question 64

What does it mean to say that an event has a time-box?

Options:

A.

The event must happen at a set time.

B.

The event must happen by a given time.

C.

The event must take at least a minimum amount of time.

D.

The event can take no more than a maximum amount of time.

Question 65

How much time is required after a Sprint to prepare for the next Sprint?

Options:

A.

The break between Sprints is time-boxed to 1 week for 30 day Sprints, and usually less for shorter sprints.

B.

Enough time for the requirements for the next Sprint to be determined and documented.

C.

Enough time for the Development team to finish the testing from the last Sprint.

D.

None. A new Sprint starts immediately following the end of the previous Sprint.

E.

All of the above are allowed depending on the situation.

Question 66

(Who should make sure everyone on the Scrum Team does their tasks for the Sprint?

Choose the best answer.)

Options:

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Scrum Team.

E.

All of the above.

Question 67

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?

Options:

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the Development Team.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

Question 68

What does it mean for a Scrum Team to be cross-functional?

(choose the best answer)

Options:

A.

The Scrum Team includes not only developers but also business analysts, architects, and testers.

B.

The Scrum Team includes skilled individuals who together have all the skills

necessary to create value each Sprint.

C.

Developers on the Scrum Team work closely with business analysts, architects,

developers, and testers who are not on the team.

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers.

Question 69

Who should know the most about the progress toward a business objective or a release?

Options:

A.

The Project Manager.

B.

The Scrum Master.

C.

The Development Team.

D.

The Product Owner.

Question 70

Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)

Options:

A.

The Project Manager

B.

The Product Owner

C.

The Scrum Master

D.

The Scrum Team

E.

All of the above

Question 71

How much of the Sprint Backlog must be defined during the Sprint Planning event?

Options:

A.

Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.

B.

The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.

C.

Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.

D.

Just enough to understand design and architectural implications.

Question 72

What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)

Options:

A.

By ensuring the meetings start and end at the proper time.

B.

By removing impediments that hinder the Development Team.

C.

By facilitating Development Team decisions.

D.

By keeping high value features high in the Product Backlog.

Question 73

When is it most appropriate for a Scrum Team to change the Definition of Done?

(choose the best answer)

Options:

A.

During Product Backlog refinement.

B.

During the Sprint Retrospective.

C.

During Sprint Planning.

D.

Prior to starting a new project.

Question 74

The CEO asks the Developers to add a " very important " item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

Options:

A.

Add the item to the Sprint Backlog for the next Sprint.

B.

Add the item to the top of the Product Backlog.

C.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

D.

Add the item to the current Sprint and drop an item of equal size.

E.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.

Question 75

When is it most appropriate for a Scrum Team to change the definition of “Done”?

Options:

A.

During Spring Planning.

B.

Prior to starting a new Sprint.

C.

During the Sprint Retrospective.

D.

Prior to starting a new project.

Question 76

If burndown charts are used to visualize progress, what do they track?

Options:

A.

Accumulated cost.

B.

Individual worker productivity.

C.

Work remaining across time.

D.

Accumulated business value delivered to the customer.

Question 77

Which does a self-organizing Development Team choose?

Options:

A.

Sprint length.

B.

How to best accomplish its work.

C.

Stakeholders for the Sprint Review.

D.

When to release, based on its progress.

E.

Product Backlog ordering.

Question 78

When does the second Sprint start?

Options:

A.

Once the architectural changes for the second Sprint have been approved by the senior architect.

B.

After the Product Backlog for the second Sprint has been selected.

C.

Immediately after the first Sprint.

D.

After the customer completes acceptance testing of the first Sprint.

Question 79

Who should make sure everyone on the Development Team does their tasks for the Sprint?

Options:

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Development Team.

E.

All of the above.

Question 80

What is the key concern when multiple Development Teams are working from the same Product Backlog?

Options:

A.

Minimizing dependencies between teams.

B.

Clear definition of requirements.

C.

Meeting original scope projections.

D.

Making sure there’s enough work for everyone on every team.

E.

Maximizing velocity.

Question 81

Which of the following is a Developer accountable for? (Choose the best two answers.)

Options:

A.

Selecting the Product Owner.

B.

Reporting productivity.

C.

Creating a plan for the Sprint, the Sprint Backlog.

D.

Organizing the work required to meet the Sprint Goal.

Question 82

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

Options:

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update management on what is being worked on.

D.

Answer QUESTION NO:s from the Development Team about items in the current Sprint.

Question 83

(Which of the following activities will a Product Owner engage in during a Sprint?

Choose the best answer.)

Options:

A.

Answer questions from the Developers about items in the current Sprint.

B.

Prioritize the Developers’ work on the Sprint Backlog.

C.

Run the Daily Scrum.

D.

Update management on what is being worked on.

Question 84

True or False: The purpose of a Sprint Is lo produce a valuable useful Inclement.

Options:

A.

True

B.

False

Question 85

(What are the two primary ways a Scrum Master helps a Scrum Team work at its highest level of productivity?

Choose the best two answers.)

Options:

A.

By keeping high-value features high in the Product Backlog.

B.

By facilitating Scrum Team decisions.

C.

By ensuring the meetings start and end at the proper time.

D.

By removing impediments that hinder the Scrum Team.

Question 86

Which best describes the Product Backlog?

Options:

A.

It is allowed to grow and change as more is learned about the product and its customers.

B.

It provides just enough information to enable a Scrum team to start the design phase of a product.

C.

It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.

D.

It is baselined to follow change management processes.

Question 87

Which of the following is an accountability of a Tester on a Scrum Team?

(choose the best answer)

Options:

A.

Executing tests, finding defects, and reporting them to the Developers.

B.

Refreshing and communicating the Definition of Done to the Product Owner.

C.

Scrum has no Tester accountability. The Developers are accountable for quality.

D.

Verifying the work of the Developers.

E.

Tracking defect rates to ensure they improve each Sprint.

Question 88

What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)

Options:

A.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

B.

Add security concerns to the definition of “Done”.

C.

Add a Sprint to specifically resolve all security concerns.

D.

Delegate the work to the concerned department.

E.

Have the Scrum Team create Product Backlog items for each concern.

Question 89

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

Options:

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

Page: 1 / 30
Total 298 questions